Microgrid and DER Handbook companion

Microgrids and DER Quick Reference

Rules of thumb for fast, defensible answers

Matthew W. Huber

Version 1.0 · November 2026

Microgrids and DER Quick ReferenceMatthew W. Huber

Cards

Rules of thumb for fast, defensible answers

L-01Loads · ChecklistFor sales · engineering · everyoneTypical

What do I need from the customer to size a system?

Quick answer
12+ monthsof interval data
plus critical loads, motors, tariff and site limits
In plain words

Sizing needs a year of the meter's detailed readings, a list of what needs to stay on and for how long, and the rate schedule the utility charges. One peak number is like sizing a fuel tank from a car's top speed: it says nothing about how far you need to go.

Checklist

Usage data

Loads to protect

Motors and special loads

Money and goals

Site

Watch out
  • One year gives one sample of the annual peak; weather can move it 5–15% from year to year.
  • "Eight hours of backup" is not a requirement until it names the loads, the season and the tolerable break.
  • Adding up nameplates of critical loads overstates the real peak; ask for measured, time-matched data.
Call an engineer when

When large motors start on backup, loads cannot tolerate any break, interval data are missing, or the tariff carries standby charges.

Typical: Common practice in demand-charge and verification analysis; not a standard.
Go deeper
ROT-LOAD-03 · LOAD-001 · LOAD-021 · LOAD-022 · LOAD-023 · ROT-LOAD-06 · SYS-001 · ROT-SYS-09
L-02Loads · CompareFor sales · engineering · everyoneSolid

Peak or energy: which one sizes what?

Quick answer
Four numbers
peak, energy, start-up surge and allowed break each size something
In plain words

Peak power in kilowatts sets how big the inverter or generator has to be, while energy in kilowatt-hours sets how much battery or fuel you need. It is like a water system: the pipe has to handle the busiest moment, and the tank has to last the whole outage.

Side by side
Peak powerEnergyStart-up surgeAllowed break
Plain meaningHighest steady draw of the loads that stay onTotal used over the outageShort jump when motors start or blocks of load switch onHow long a load can go dark
Time scaleAbout 1 minute, sustainedHoursCycles to about 30 secondsThousandths of a second to minutes
UnitkW, and kVA for equipmentkWhkVASeconds
What it sizesContinuous rating of inverters and generatorsBattery storage or fuelShort-time capability and voltage dipTransfer scheme, uninterruptible power supply (UPS) and restart order
Handbook example600 kW measured critical peak400 kW average × 4 h = 1,600 kWhOne 75 hp motor start can govern the sourceNone, 10 seconds or minutes, set per load
Where to go nextInverters; GeneratorsBatteries; GeneratorsL-06; Inverters; GeneratorsHow a microgrid behaves
Watch out
  • Fifteen-minute billing peaks understate the 1-minute peak an island has to carry; ask for finer data on critical loads.
  • The 1,600 kWh is at the loads; the battery's own use and conversion losses come on top (see Batteries).
  • The average says nothing about start-up surges; a single motor start can size the source instead of the peak.
Call an engineer when

When one large motor, a fire pump or a load that tolerates no break could set the source size instead of the peak.

Solid: Definitions and exact arithmetic; example values are synthetic handbook data.
Go deeper
LOAD-021 · LOAD-022 · LOAD-018 · LOAD-023 · LOAD-001 · LOAD-002
L-03Loads · NumberFor sales · engineering · everyoneTypical

What does load factor tell me about a site?

Quick answer
Average ÷ peak
low means peaky, high means flat
In plain words

Load factor is average power divided by peak power: near 1.0 a site runs close to its peak, near 0.3 it spends most hours far below it. It is like a car's average speed against its top speed: it shows how much of the engine you really use, and how short and sharp the peaks are.

Quick math

Load factor = average kW ÷ peak kW = yearly kWh ÷ (peak kW × 8,760 h)

  1. Average: 3,250,000 kWh a year ÷ 8,760 h ≈ 371 kW
  2. Load factor: 371 kW ÷ 820 kW peak ≈ 0.45, so the peak is about 2.2 times the average
  3. Read it: under 0.3 very peaky; 0.3–0.45 peaky (schools); 0.45–0.65 moderate (offices, retail); 0.65–0.85 flat (hospitals, grocery, cold storage)
  4. Turned around for a bill with no demand meter: 186,000 kWh over 30 days at an assumed monthly load factor of 0.55 gives 186,000 ÷ (0.55 × 720 h) ≈ 470 kW peak
Load factor about 0.45: a generator sized to the peak would average about 45% load; the bill-only peak is a screening guess of about 430–520 kW
What moves this number
← lessmore →
Peakier site than assumedload factor 0.55 → 0.50
about 10% higher estimated peak
Flatter site than assumedload factor 0.55 → 0.60
about 8% lower estimated peak
Longer billing period30 → 31 days, same kWh
about 3% lower estimated peak
−10%0+10%
Watch out
  • Load factor says nothing about when the peak happens; two sites with the same figure can need very different battery energy.
  • Always state the period and the demand interval; changing either one changes the load factor.
  • Fifteen-minute peaks understate the one-second peaks an island carries, more so with large motors, elevators or chillers.
Call an engineer when

When a bill-only peak is used for demand-charge savings or battery sizing, or an island has to carry motor and elevator surges.

Typical: The definition is exact; facility bands are screening judgment.
Go deeper
LOAD-005 · LOAD-006 · LOAD-007 · LOAD-002 · ROT-LOAD-03 · ROT-LOAD-01 · ROT-LOAD-05
L-04Loads · NumberFor sales · engineeringRough guide

We have several buildings. Can I just add up their peaks?

Quick answer
0.75–0.95× the summed peaks
2–10 similar commercial buildings, 15-minute demand
In plain words

No: buildings rarely all hit their peak in the same 15 minutes, so the combined peak is smaller than the sum of each building's own peak. It is like a family's morning showers: everyone showers, but not all at 7:00, so the water heater does not have to serve every shower at once.

Quick math

Combined peak ≈ sum of each building's own peak × coincidence factor

  1. Four buildings peak at 310, 520, 260 and 640 kW: sum 1,730 kW
  2. Measured campus peak: 1,420 kW
  3. Coincidence factor: 1,420 ÷ 1,730 ≈ 0.82
  4. Connected nameplate load is 3,200 kW, about 2.25 times the real campus peak
About 1,420 kW, not 1,730 kW: adding the peaks would oversize the sources by about 22%
What moves this number
← lessmore →
Added the building peaksfactor 0.82 → 1.00
about 22% bigger sources than needed
Very similar schedulesfactor 0.82 → 0.95
about 16% higher combined peak
More varied schedulesfactor 0.82 → 0.75
about 9% lower combined peak
−25%0+25%
Watch out
  • Mixed schedules, such as residence halls with offices, run about 0.6–0.8; groups of 50 or more homes, about 0.3–0.5.
  • After an outage, heating and cooling restart together and the factor heads toward 1.0 for minutes to hours.
  • Fleet vehicles charging at once, or a group dominated by one large load, do not spread out; see L-08.
Call an engineer when

When the combined peak sets transformer, utility connection or generator size; a campus meter's own data should replace the factor.

Rough guide: Commercial bands are author judgment; the residential band follows planning texts.
Go deeper
LOAD-010 · LOAD-009 · LOAD-008 · ROT-LOAD-02 · ROT-MG-13 · MG-022
L-05Loads · DecideFor sales · engineering · everyoneTypical

Should we back up the whole building or just the critical loads?

Quick answer
Tier it
critical loads first; shed the rest as outages run long
In plain words

Backing up the whole building means sizing for its full peak and full energy. Backing up only what matters, in priority groups, cut the energy needed by about 38% in one handbook example, like a lifeboat: seats for people first, luggage after.

How to choose
Whole building
Choose when
  • The site is small, or critical circuits cannot be separated at the panels
  • The owner wants no visible change during an outage and accepts the cost
Avoid when
  • Large heating, cooling or process loads would size the battery for hours they need not run
  • Motor starts of loads nobody needs in an outage would set the source size
Critical loads only
Choose when
  • Code-required life-safety loads or a short, clear list of loads that matter
  • Critical circuits are, or can be, on their own panels
Avoid when
  • The list is built from nameplates rather than measured, time-matched data
  • Everyone's loads get called critical until the list is the whole building
Tiered, shed as the outage runs
Choose when
  • Long outages where stored energy or fuel, not power, is the limit
  • Controls can shed and restore each tier automatically while islanded
Avoid when
  • Shedding depends on someone switching breakers by hand
  • There is no spare battery charge or fuel to bring shed tiers back later
Watch out
  • Nameplates overstate: in one handbook example the measured critical peak was 600 kW against 1,050 kW connected.
  • Loads that were off restart together when power returns; restart order belongs in How a microgrid behaves.
  • Code-required emergency loads follow the electrical code as adopted locally, not owner preference.
Call an engineer when

When life-safety loads are involved, critical circuits share panels with others, tiers are shed automatically, or the site is continuous process or a data center.

Typical: Practice-based; figures come from the handbook's synthetic worked examples.
Go deeper
LOAD-021 · LOAD-022 · ROT-LOAD-09 · ROT-LOAD-11 · ROT-CTRL-19
L-06Loads · NumberFor sales · engineering · everyoneTypical

Why do motors matter so much when the building runs on backup power?

Quick answer
6–8×full-load current
standard induction motor started straight across the line
In plain words

A motor started at full voltage draws six to eight times its normal current for a few seconds, so the voltage sags for everything else on the circuit. The utility shrugs that off like a river losing a bucket, but a backup generator is a pond, and the same start makes a much bigger dip.

Quick math

Starting kVA ≈ code-letter kVA per hp × horsepower; starting amps ≈ 1,000 × starting kVA ÷ (1.73 × volts)

  1. 100 hp pump, code letter G (up to 6.3 kVA per hp): 6.3 × 100 = 630 kVA at standstill
  2. At 460 V: 1,000 × 630 ÷ (1.73 × 460) ≈ 791 A, about 6.4 times the 124 A code-table full-load current
  3. Running at full load it needs about 91 kVA by calculation (95% efficient, power factor 0.86), or about 99 kVA from the table's 124 A, so the start is 6.4–7 times bigger
  4. Voltage dip: about 2.6% on a 1,500 kVA utility transformer, about 9–15% on a 1,000 kVA generator
About 630 kVA and 790 A for the seconds it takes to start; the same start dips the generator's voltage roughly 3.5–6 times as much as the utility's
What moves this number
← lessmore →
Higher code letterG → J (up to 8.0 kVA per hp)
about 27% more starting kVA
Wye-delta starterabout one-third of across-the-line current
about 67% less starting current, with less torque
Variable frequency driveabout 1.5 × full-load current instead of 6.4 ×
about 76% less starting current
−80%0+80%
Watch out
  • High-efficiency motors can exceed 8 times; final studies use the motor's own data sheet.
  • Batteries limit current rather than sag; whether one can start a motor is in Inverters, generator load steps in Generators.
  • Starting power factor is low, about 0.3–0.45 for 20–200 hp, so the surge is mostly kVA, not kW.
Call an engineer when

When any motor above about 10 hp starts on backup power, a fire pump is involved, or several motors could start together.

Typical: Starting multiple is widespread practice; the dip example uses assumed source data.
Go deeper
LOAD-014 · LOAD-015 · LOAD-016 · LOAD-017 · LOAD-019 · LOAD-023 · ROT-LOAD-06 · ROT-LOAD-07 · ROT-LOAD-10
L-07Loads · DecideFor sales · engineeringTypical

How much load growth should we allow for?

Quick answer
Two horizons
wires to end of life; batteries to year 5–10
In plain words

Size the parts that are hard to enlarge later, such as transformers, switchgear and the utility connection, for the high case at the end of the project's life. Size modular parts, such as batteries, generators and solar, for year 5 to 10 with room to add more: pour the foundation big, furnish only the rooms you use.

How to choose
Size now for end of life (20–30 years)
Choose when
  • Switchgear, transformers, feeders and the utility connection
  • Each later addition would trigger a new utility interconnection study
Avoid when
  • Equipment that comes in modules and can be added on prepared pads
Size for year 5–10 and leave room
Choose when
  • Batteries, generator sets and solar arrays that can be added in modules
  • Pads, spare breakers and conduit can be placed now for the later units
Avoid when
  • Adding a module would need new switchgear or a new utility study
Size for year 1 only
Choose when
  • Guarantees and acceptance tests, which should rest on metered load
  • Starting battery energy when adding capacity later is already planned
Avoid when
  • Anything costly to enlarge once it is energized
Watch out
  • With no identified projects, organic growth is judged at 0–1.5% a year; above 2% usually hides projects to list separately.
  • Compounding adds up: 850 kW growing 1.5% a year reaches about 986 kW in 10 years and 1,145 kW in 20.
  • Fleet charging, heat pumps and new buildings are steps, not percentages; add each as its own block (see L-08).
Call an engineer when

When electrification, fleet charging or campus expansion is planned, or each addition would trigger a new utility interconnection study.

Typical: Widespread planning practice; the growth rates themselves are author judgment.
Go deeper
ROT-LOAD-12 · ROT-LOAD-13 · LOAD-024 · LOAD-025 · LOAD-027 · ROT-LOAD-15
L-08Loads · NumberFor sales · engineering · everyoneTypical

What does electric vehicle charging add to the load?

Quick answer
70–100%of charger ratings
unmanaged fleet depot; managed, 25–50%
In plain words

Fleet vehicles that come back to the depot together all plug in at once, so without controls nearly every charger runs at full power at the same time. Managed charging spreads the same energy across the night, like staggering showers in a house, and can hold the peak to a quarter or half of the chargers' rating.

Quick math

Unmanaged peak ≈ chargers × charger kW × share charging at once; managed limit ≈ (1 + margin) × nightly kWh ÷ efficiency ÷ hours parked

  1. 40 vans, each needing 48 kWh a night, on 19.2 kW chargers, all back within 1.5 hours
  2. Each charge takes 48 ÷ 0.90 ÷ 19.2 ≈ 2.8 hours, longer than the arrival spread, so all 40 run at once: 40 × 19.2 = 768 kW
  3. Nightly energy from the grid: 40 × 48 ÷ 0.90 ≈ 2,133 kWh
  4. Managed over 10 parked hours with 20% margin: 1.20 × 2,133 ÷ 10 ≈ 256 kW
768 kW unmanaged against about 256 kW managed, one-third of the chargers' total rating, for the same energy
What moves this number
← lessmore →
Managed chargingall at once → spread over 10 h
about 67% lower peak
Arrivals spread out1.5 h → 3.5 h
about 21% lower peak, about 600 kW
Vehicles accept less power19.2 → 11.5 kW per charger
about 40% lower peak, longer charges
−70%0+70%
Watch out
  • Count managed charging only if the microgrid controls run it and it falls back to a safe limit if communications fail.
  • Winter cabin heating raises energy per mile; fast chargers add 50–350 kW each in short peaks the energy math misses.
  • Under about 10 chargers, plan for all at once; workplace chargers overlap less, about 0.3–0.6 by judgment.
Call an engineer when

When chargers share a service with critical loads, fast chargers or several shifts are planned, or charge management is counted toward sizing.

Typical: Arrival-spread arithmetic; the managed range comes from depot practice.
Go deeper
LOAD-037 · LOAD-029 · LOAD-036 · LOAD-010 · ROT-LOAD-20 · ROT-LOAD-17
L-09Loads · NumberFor sales · engineering · everyoneTypical

How much load can we turn down instead of buying more battery?

Quick answer
50–80%of tested flexible kW
credit toward battery sizing; zero if untested
In plain words

Loads like cooling, water heating or batch processes can be turned down in an outage, but they rarely deliver their full rating, so count only the share proven in tests. Count nothing for life-safety or critical loads, or for anything the controls cannot reach while islanded, just as you rely on a friend only once they have shown up before.

Quick math

Energy the battery covers ≈ outage energy − proven share × flexible kW × hours turned down

  1. A 4-hour outage needs 2,000 kWh, with a 650 kW peak
  2. 120 kW of cooling can be turned down for all 4 hours; past events show 70% delivered
  3. Energy: 2,000 − 0.70 × 120 × 4 = 1,664 kWh
  4. Peak: 650 − 0.70 × 120 = 566 kW
Size the battery for about 1,664 kWh and 566 kW instead of 2,000 kWh and 650 kW, about 17% less energy
What moves this number
← lessmore →
No test data yetcredit 0.70 → 0
about 20% more energy, back to 2,000 kWh
Turned down for half the outage4 h → 2 h
about 10% more energy
Better proven share0.70 → 0.80
about 3% less energy
−20%0+20%
Watch out
  • Flexibility that relies on utility signals, or on building controls without backup power, may vanish on an island.
  • Released loads come back harder: cooling can recover half to all of the energy it skipped within 1–3 hours.
  • The risk is one-sided: an undersized battery fails on the one day the flexibility does not show up.
Call an engineer when

When flexible load is counted in battery or generator size, controls are untested in island mode, or rebound falls inside the outage.

Typical: Widespread practice; no standard sets the credit share.
Go deeper
LOAD-040 · ROT-LOAD-21 · LOAD-032 · LOAD-033 · ROT-LOAD-18 · ROT-LOAD-19
S-01Solar and other renewables · NumberFor sales · engineering · everyoneTypical

How many kWh a year will each kW of solar make?

Quick answer
1,050–1,900kWh per kW a year
of panel rating, fixed tilt, lower 48 states
In plain words

Each kilowatt of panels makes roughly 1,050 kilowatt-hours a year in the cloudy north and up to about 1,900 in the desert Southwest, after normal losses. The panel rating is like a car's top speed: the yearly total depends on how much sun the site gets, not on the label alone.

Quick math

Yearly kWh ≈ panel rating in kW × regional yield (kWh per kW per year)

  1. Site: 500 kW of panels, mid-latitude, fixed tilt; regional yield about 1,350 kWh per kW per year
  2. Typical year: 500 × 1,350 = 675,000 kWh
  3. One-in-ten poor year, with 5% uncertainty: 675,000 × (1 − 1.282 × 0.05) ≈ 632,000 kWh
About 675,000 kWh (675 MWh) in a typical first year, about 632,000 kWh in a one-in-ten poor year
What moves this number
← lessmore →
Single-axis trackerfixed tilt → tracker, Mid-Atlantic midpoints 1,300 → 1,500
about 15% more energy a year
Cloudier northern regionMid-Atlantic → Great Lakes, midpoints 1,300 → 1,150
about 12% less energy a year
Hot climate or flush roof mountperformance ratio 0.80 → 0.75
about 6% less energy a year
−15%0+15%
Watch out
  • Regional yield already includes normal losses; multiplying it by a performance ratio again undercounts by about 20%.
  • A typical-year figure is not a worst-week figure; an outage plan needs the poor-day number (see S-08).
  • South-central Alaska yields only about 700–950 kWh per kW a year.
Call an engineer when

Before quoting energy or savings in a proposal: run an hourly solar simulation for the actual site, tilt, shading and inverter.

Typical: Representative simulation ranges by region; confirm the site with a solar model.
Go deeper
PV-001 · PV-002 · PV-003 · PV-004 · ROT-PV-01
S-02Solar and other renewables · NumberFor sales · engineering · everyoneTypical

How much roof or land does solar need?

Quick answer
3–5 acresper megawatt of panels (DC)
whole site: near 3 for fixed tilt, 4–5 for trackers
In plain words

Plan about 3–5 acres per megawatt (MW) of panels on the ground, near 3 for fixed tilt and 4–5 for trackers, or about 9 watts per square foot of flat roof (7–11) after walkways and fire paths. Rows need gaps so they do not shade each other, like seats in a theater spaced so everyone can see the stage.

Quick math

Roof kW ≈ gross roof ft² × usable share × row coverage × panel watts per ft² ÷ 1,000

  1. Flat roof 40,000 ft²; usable share 0.70; tilted rows cover 0.65 of it: 40,000 × 0.70 × 0.65 = 18,200 ft² of panels
  2. Panels at 21.5% efficiency make 215 watts per square meter, or 215 ÷ 10.764 ≈ 20 watts per ft²
  3. 18,200 × 19.97 ÷ 1,000 ≈ 364 kW, about 9 watts per ft² of gross roof
About 364 kW of panels on a 40,000 ft² flat roof; about 3–5 acres per MW of panels on the ground
What moves this number
← lessmore →
Single-axis tracker on the groundabout 3 → 4.2 acres per MW of panels
about 40% more land
More fire paths or weak roof areasusable roof share 0.70 → 0.60
about 14% less solar on the roof
Higher-efficiency panels21.5% → 23% efficiency
about 7% more solar in the same space
−40%0+40%
Watch out
  • Fire pathways, roof structure and wind zones often cut usable roof below 0.6 of gross area.
  • Ballasted roof systems commonly add 3–6 pounds per square foot; a structural engineer confirms the roof can carry it.
  • Carport canopies hold about 15 watts per square foot of canopy; pitched roofs 12–17 on the usable plane.
Call an engineer when

When the roof is old or lightly built, the site is far north, or setbacks and easements could cut the usable area.

Typical: Geometry plus published land-use studies; easements and setbacks dominate small sites.
Go deeper
PV-013 · ROT-PV-07 · ROT-SYS-03 · SYS-003
Public sources
Lawrence Berkeley National Laboratory (2022). Land Requirements for Utility-Scale PV: An Empirical Update on Power and Energy Density.
S-03Solar and other renewables · CompareFor sales · engineeringTypical

Why is the solar array bigger than the inverter (DC/AC ratio)?

Quick answer
1.20–1.30panel kW per inverter kW
starting point, grid-connected commercial and utility
In plain words

Panels rarely reach their full rating, so the panel rating in direct current (DC) is often set about 1.2–1.3 times the inverter's alternating current (AC) rating. The cost is a sliver of energy lost on the brightest hours, called clipping, like a slightly narrow funnel that overflows only in a rare full pour.

Side by side
Typical DC/AC ratioWhy
Homes, string or microinverters1.10–1.25Roof direction limits the gain
Commercial rooftop, fixed tilt1.15–1.35Low tilt lowers the peak, so a higher ratio clips little
Utility, fixed tilt1.25–1.40Grid connection capacity is the expensive limit
Utility, single-axis tracker1.20–1.35Broad daily output clips sooner
Solar plus storage sharing one inverter (DC-coupled)1.40–2.00The battery soaks up energy that would be clipped
Microgrid that has to run islanded1.10–1.30Inverter headroom is kept for reactive power and load steps
Watch out
  • Clipping is roughly under 0.5% of yearly energy at 1.1–1.2, 2–5% at 1.4, 4–8% at 1.5; rough, confirm by simulation.
  • A higher ratio adds no capacity in an island: the inverter rating, not the panels, sets what it can deliver.
  • Cold, bright days can push panels above their rating and clip more than an hourly model shows.
Call an engineer when

When the ratio goes above about 1.3, the site has to run islanded, or clipped energy is counted in the savings.

Typical: Widespread project practice; clipping percentages are author estimates.
Go deeper
ROT-PV-04 · ROT-PV-05 · PV-009 · PV-010 · PV-011 · PCS-029
S-04Solar and other renewables · NumberFor engineering · salesTypical

How much energy is lost between the panels and the inverter output?

Quick answer
15–25%of ideal output lost
panel rating to inverter output, new system, yearly
In plain words

A new, well-built system delivers about 75–85% of what its panel rating and the sunshine would ideally give; dust, shade, heat, wiring and the inverter each take a few percent. The losses multiply like small fees on every transaction: none is large, but together they take a fifth.

Quick math

Performance ratio = (1 − loss 1) × (1 − loss 2) × … ; delivered kWh = ideal kWh × performance ratio

  1. Small losses at common modeling defaults (soiling 2%, shading 3%, mismatch 2%, wiring 2.5%, panel tolerance and early fade 2.5%, downtime 3%): combined factor ≈ 0.859, about 14% lost
  2. Heat on panels, 5% (range 3–10%): 0.859 × 0.95 ≈ 0.816
  3. Inverter conversion, 4% (a conservative default; new units often 2%): 0.816 × 0.96 ≈ 0.784
Performance ratio about 0.78: about 22% of the ideal energy is lost before the inverter output
What moves this number
← lessmore →
Hot site or flush roof mountheat loss 5% → 10%
about 5% less delivered energy
Dusty site, never washedsoiling 2% → 10%
about 8% less delivered energy
Meter on the high side of a step-up transformeradd 2% transformer and wiring loss
about 2% less at that meter
−10%0+10%
Watch out
  • Clipping and deliberate output limits show up as low performance ratio even when nothing is broken; exclude those hours first.
  • Snowy climates can lose 0–15% of yearly energy to snow, which common modeling defaults leave at zero.
  • State where the energy is measured; a ratio quoted at the inverter does not apply at the utility meter.
Call an engineer when

When the guaranteed output is in a contract, the site is dusty or snowy, or measured output falls short of the model.

Typical: Widespread practice and published fleet analyses; individual losses vary by site.
Go deeper
PV-004 · ROT-PV-01 · PV-001 · ROT-PV-05
S-05Solar and other renewables · NumberFor sales · engineering · everyoneTypical

How fast does solar output fade with age?

Quick answer
about 0.5%less output per year
modern panels; 0.5–0.75% at whole-system level
In plain words

Modern panels lose about half a percent of output a year, and whole systems 0.5–0.75%, so after 25 years a system still makes roughly 83–89% of its first-year energy. It fades like a car's gas mileage over many years: steady, small and easy to plan for, unless something is defective.

Quick math

Year-n output = year-1 output × (1 − yearly fade)^(n − 1)

  1. Year 1: 675,000 kWh; fade 0.5% a year
  2. Year 25: 675,000 × 0.995^24 ≈ 598,000 kWh, 88.7% of year 1
  3. 25-year total: 675,000 × (1 − 0.995^25) ÷ 0.005 ≈ 15.9 million kWh, versus 16.9 million with no fade
About 598,000 kWh in year 25; lifetime energy about 6% below a no-fade estimate
What moves this number
← lessmore →
Whole-system fade, including inverters and soiling trends0.5% → 0.75% a year
about 6% less output in year 25
Older p-type panelsadd 2% first-year light-induced loss
about 2% less every year
Straight-line warranty curve instead of compound fadesame 0.5% a year
about 1% less in year 25; the curve shape barely matters
−10%0+10%
Watch out
  • Warranty fade rates are limits, not predictions; plan on field rates.
  • Fleets have a tail of fast faders from defects; this rule misses early failures.
  • Hot, humid or high-sun climates sit at the upper end of every fade range.
Call an engineer when

When output drops faster than about 1% a year, panels show visible defects, or a financing model needs a lender's fade assumption.

Typical: Several published fleet studies agree for established makers and sound installs.
Go deeper
PV-012 · ROT-PV-06
S-06Solar and other renewables · CompareFor sales · engineering · everyoneTypical

Why won't solar alone keep the lights on in an outage?

Quick answer
Not alone
solar needs a battery or generator to run islanded
In plain words

Most solar inverters follow the grid like a dancer following a lead partner: when the grid drops, they stop, by design and by code. Even with a partner, solar stops at night and sags in clouds, so planners count it as zero firm capacity and let a battery or generator carry the island.

Side by side
Solar aloneSolar + batterySolar + generator
Grid failsShuts off: usual solar inverters are grid-followingKeeps running if the battery inverter is grid-formingKeeps running once the generator sets voltage and frequency
At nightNothingBattery carries the load until it runs lowGenerator carries the load on fuel
Firm capacity counted in an island planZeroZero for solar; the battery countsZero for solar; generator at its site-derated rating
Poor winter day, cloudy northern siteAbout 10–25% of an average dayBattery may not refillGenerator fuel fills the gap
Midday, battery full or load lowNot applicableSolar is cut back (curtailed)Solar is cut back to keep the generator above its minimum load
Watch out
  • Some inverters can form the grid; confirm it in the listing and settings, not the brochure.
  • How much solar an island can safely carry belongs to the microgrid behavior cards; see How a microgrid behaves.
  • Islands with a high solar share need a dynamic stability study before anyone promises backup.
Call an engineer when

When a customer expects solar to carry loads in an outage, or solar could exceed what battery and generators can absorb.

Typical: Widespread planning practice; poor-day share is rough author judgment.
Go deeper
ROT-MG-04 · ROT-WND-05 · PV-014 · ROT-PV-08 · ROT-PV-04 · CTRL-035 · ROT-MG-16 · MG-027
S-07Solar and other renewables · NumberFor engineering · salesTypical

What do hot and cold weather do to solar output?

Quick answer
0.24–0.37%less power per °C
of cell temperature above 25 °C, silicon panels
In plain words

Panels make less power when hot: on a 35 °C (95 °F) afternoon the cells run near 66 °C, and output drops about 10–15% below the label. Like a runner in the heat, the same sunshine produces less work; on a cold, clear day the panels can beat their rating.

Quick math

Power ≈ panel rating × (sun ÷ 1,000 W/m²) × [1 + temperature coefficient × (cell °C − 25)]

  1. Cell temperature: 35 °C air + (45 − 20) ÷ 800 × 1,000 W/m² ≈ 66 °C, using a datasheet operating cell temperature of 45 °C
  2. Heat factor at −0.30% per °C: 1 − 0.0030 × (66.25 − 25) ≈ 0.876
  3. 500 kW of panels in full sun: 500 × 0.876 ≈ 438 kW
About 438 kW from a 500 kW array, about 12% below rating, before dust, wiring and inverter losses
What moves this number
← lessmore →
Older p-type panelscoefficient −0.30 → −0.36% per °C
about 3% less hot-day power
Flush roof mount instead of open rackcell rise 31 → 40 °C above air, at 35 °C air
about 3% less hot-day power
Cold, clear daycell 66 °C → 25 °C
about 14% more power than the hot afternoon
−15%0+15%
Watch out
  • Cold, bright, snow-reflected days can push panels 10% or more above rating; that tests clipping and wire current margins.
  • Cold raises string voltage; the electrical code's cold-voltage limit, as adopted locally, sets how many panels per string.
  • Hot days also derate inverters; see Inverters.
Call an engineer when

When strings run near the inverter's voltage limit, the site sees extreme cold or heat, or output guarantees cover summer peaks.

Typical: Datasheet coefficients and published thermal models; mounting band edges are judgment.
Go deeper
PV-005 · PV-006 · ROT-PV-02 · PV-007 · PV-008 · ROT-PV-03
S-08Solar and other renewables · NumberFor engineering · salesRough guide

What does a bad week of sun look like for an island?

Quick answer
10–25%of an average day's solar
poor winter day, cloudy northern climate
In plain words

On a poor December day in the cloudy north, solar can make only a tenth to a quarter of an average day's energy, and poor days come in runs. Planning an outage on the yearly average is like packing for a winter trip using the yearly average temperature.

Quick math

Poor-day kWh ≈ panel kW × poor-day sun hours × performance ratio × (1 − snow loss)

  1. 500 kW of panels, northern December, one-in-ten poor day at 0.5 sun hours: 500 × 0.5 × 0.80 = 200 kWh
  2. Compare: average December day 500 × 2.0 × 0.80 = 800 kWh; average day of the year 1,680 kWh
  3. Critical load 1,200 kWh a day: 1,200 − 200 = 1,000 kWh short
About 200 kWh, roughly 12% of an average day; about 1,000 kWh a day has to come from storage or fuel
What moves this number
← lessmore →
Snow covering the arraysnow loss 0 → 100%
near zero output, possibly for days
Average December day instead of a poor one0.5 → 2.0 sun hours
four times the poor-day energy, still under half an average day
Sunny southern site, summer outagemidpoints 17.5% → 50% of an average day
nearly three times the poor-day output
−300%0+300%
Watch out
  • Poor days come in runs; size for the worst run of several days, not one bad day.
  • Hurricane outages arrive with cloud bands, so the outage and the poor sun coincide.
  • Rough rule only; derive the poor-day value from at least 10 years of the site's daily sun data.
Call an engineer when

When solar is counted on to stretch fuel or battery in an outage longer than a day; ask for a multi-year hour-by-hour simulation.

Rough guide: Author judgment; the site's daily weather record replaces it.
Go deeper
PV-014 · ROT-PV-08 · PV-001 · MG-027 · MG-036
S-09Solar and other renewables · DecideFor sales · engineeringRough guide

Is wind or small hydro worth a look?

Quick answer
Only with data
measured wind or flow records come before any estimate
In plain words

Wind and small hydro can be worth it, but only where measured wind or stream flow says so; guesses from nameplate ratings or a feeling are usually wrong. Wind power rises with the cube of wind speed, so a small error in wind speed becomes a large error in energy.

How to choose
Wind turbine
Choose when
  • Measured hub-height yearly average wind of 6 meters per second (13 mph) or more: capacity factor about 20–28% at 6, 27–36% at 7
  • Open rural or coastal site; rotor bottom at least 30 ft above anything within about 500 ft
  • Certified power curve, test report and local service access
Avoid when
  • Rooftop, urban or wooded sites: output falls below the low end of every estimate
  • Average wind about 5 meters per second (11 mph): capacity factor only about 12–20%
  • Rating claims much more than about 450 watts per square meter of rotor area
Small hydro (run-of-river)
Choose when
  • A stream with medium or high drop (head) and flow most of the year
  • At least 10 years of flow records and the agency's required bypass flow are available
  • An off-grid site wants steady energy: size for the flow present 80–95% of the time
Avoid when
  • Low drop, where civil works and fish passage dominate the cost
  • The island needs energy in the dry season; the handbook's example plant makes nothing about 20% of the year
Biogas or biomass
Choose when
  • A steady on-site fuel source exists, such as a digester, landfill or wood supply, and dispatchable power is wanted
Avoid when
  • Fuel supply or gas quality is uncertain; treat it as an engine project (see Generators)
Watch out
  • A 10% error in wind speed is about a 33% error in power below rated output.
  • Small turbines have often produced less than estimated: optimistic wind, obstacle wakes, uncertified power curves.
  • In an island, count a few wind turbines, and hydro above its low-flow output, at zero firm capacity; count only their energy.
Call an engineer when

Before any wind or hydro number reaches a customer: a measured site wind study or 10+ years of flow data, plus permitting review.

Rough guide: Siting rules are solid practice; wind capacity factor bands are author computation.
Go deeper
ROT-WND-01 · ROT-WND-02 · ROT-WND-03 · ROT-WND-04 · ROT-WND-05 · WND-001 · WND-006 · WND-008 · WND-009 · WND-010
G-01Generators and fuel · NumberFor sales · engineeringTypical

How big a generator do I need?

Quick answer
1.2–1.4×the critical peak, in site-rated kW
running fleet, plus one spare unit for redundancy
In plain words

Plan to run generators at about 70–85% of what they can really deliver at your site. That makes the running fleet about 1.2 to 1.4 times the peak it carries, and then you add one spare unit in case one fails. Like a moving crew, you hire enough people that nobody works flat out, plus one extra in case someone calls in sick.

Quick math

Units needed = peak ÷ (design loading × site rating per unit), rounded up; install one more (N+1)

  1. Site rating: a 1,000 kW standby set at 5,000 ft and 45 °C intake air: 1,000 × 0.94 altitude × 0.98 heat ≈ 921 kW
  2. Divide: 1,800 kW critical peak ÷ (0.80 × 921 kW) = 2.44, round up to 3 units
  3. Add one spare: install 4 units, about 2,440 kW of rated capacity needed in the running fleet
  4. Check loading: about 49% each with all 4 running, about 65% with one out; whole units put the running fleet at 1.5 times the peak, above the 1.2–1.4 band, because 2 units would run at 98%
Four 1,000 kW sets (three carry the peak, one spare)
What moves this number
← lessmore →
Cool site near sea levelno altitude or heat derate
about 8% less capacity needed
Lower design loading0.80 → 0.70 of site rating
about 14% more capacity needed
Long islands need the prime ratingstandby label → prime label
about 10% more capacity needed
−15%0+15%
Watch out
  • Use the site rating, not the label: altitude and hot intake air shave capacity before any other check.
  • Size to the critical peak of loads that run together, not the sum of every nameplate on the panel.
  • Big load steps or motor starts can force a bigger set than the peak does; see the step-load card.
Call an engineer when

When the site is high or hot, loads step in large blocks, motors start across the line, or life-safety code classifies the system.

Typical: Arithmetic is exact; loading band is common practice, derate coefficients are rough.
Go deeper
GEN-011 · GEN-002 · GEN-001 · GEN-010 · ROT-MG-19 · ROT-GEN-01 · ROT-GEN-03 · LOAD-021
G-02Generators and fuel · NumberFor sales · engineering · everyoneTypical

How much fuel does a diesel generator burn per kWh and per day?

Quick answer
0.065–0.080gallons of diesel per kWh
75–100% load, sets 250 kW and larger
In plain words

A large diesel generator turns one gallon into about 12–15 kWh when it is working hard, which is 0.25–0.30 liters per kWh. Run it lightly and it wastes more per kWh, because it burns a fixed amount just to keep spinning, like a car idling in traffic.

Quick math

Fuel per hour ≈ idle burn + slope × kW output (two points from the datasheet); fuel per day = fuel per hour × 24

  1. Datasheet, 500 kW set: 11.1 gal/h at 125 kW and 35.5 gal/h at 500 kW
  2. Slope: (35.5 − 11.1) ÷ (500 − 125) ≈ 0.065 gal per kWh; idle burn ≈ 35.5 − 0.065 × 500 ≈ 2.97 gal/h
  3. At 200 kW: 2.97 + 0.065 × 200 ≈ 16.0 gal/h, or about 0.080 gal/kWh
  4. Per day: 16.0 × 24 ≈ 384 gal
About 384 gal a day at 200 kW; the full-load shortcut says 341 gal, about 11% low
What moves this number
← lessmore →
Same set run near full load200 kW → 500 kW
about 11% less fuel per kWh
Two sets share the same loadone 500 kW set → two at 100 kW each
about 19% more fuel per hour
Smaller set class250 kW+ → 50–250 kW, range midpoints
about 14% more fuel per kWh
−20%0+20%
Watch out
  • Below about 20–25% load the straight-line fuel estimate reads low; light loading burns even more than shown.
  • Datasheet fuel figures carry about ±5% tolerance and leave out the fuel used to clean the exhaust filter.
  • Natural gas sets are quoted as heat rate in Btu per kWh; check whether higher or lower heating value.
Call an engineer when

When the fuel budget sets tank size, contract terms or emissions permits, or the set will run long at light load.

Typical: Consistent across published fuel tables; the datasheet curve replaces it.
Go deeper
GEN-003 · GEN-006 · GEN-004 · GEN-005 · ROT-GEN-04
G-03Generators and fuel · NumberFor engineering · salesTypical

How lightly loaded can a diesel generator run?

Quick answer
about 30%of rated kW, for sustained running
diesel; 25–40% depending on the maker
In plain words

A diesel that idles along for hours runs cold: unburned fuel and oil collect in the exhaust (called wet stacking) and newer engines cannot clean their exhaust filters without an extra regeneration burn. Keep each running set above about 30% of its rating, the way a wood stove kept smoldering on low soots up its chimney.

Quick math

Room left for other sources = load − (minimum fraction × rating of each running set)

  1. Midday load 400 kW, two 500 kW sets running, each held at 30% or more: 2 × 150 = 300 kW
  2. Room for solar or other sources: 400 − 300 = 100 kW
  3. Shut one set down: 400 − 150 = 250 kW of room, and the remaining set still covers 400 kW
Running one set instead of two leaves 250 kW of room instead of 100 kW
What moves this number
← lessmore →
Maker allows lower loading30% → 25% minimum, one set
about 10% more room
Newer engine with exhaust filter30% → 40% minimum, one set
about 20% less room
Both sets kept runningone set → two sets online
about 60% less room
−60%0+60%
Watch out
  • This is a maintenance and emissions limit, not an electrical one; short low-load periods are fine if followed by a loaded run.
  • Shutting a set down to stay above minimum loading cuts the reserve; check the remaining set can take a sudden drop in solar output.
  • How much solar an island can carry is a whole-system question; see How a microgrid behaves.
Call an engineer when

When generators share an island with solar and no battery, or the set has modern exhaust aftertreatment.

Typical: Consistent in maker guidance; the maker's own low-load limit governs.
Go deeper
GEN-007 · ROT-GEN-05 · ROT-MG-19 · ROT-MG-16 · GEN-010
G-04Generators and fuel · CompareFor engineering · salesRough guide

How big a load can a generator pick up in one step?

Quick answer
10–100%of rating in the first step
from no load, by engine type
In plain words

When a block of load lands on a generator, its speed and voltage sag until the engine catches up, and some engines catch up much faster than others. A standby diesel may be offered to take its whole rating at once. A lean-burn gas engine may take only a tenth to a third, like a sprinter versus a freight train.

Side by side
First step it can take, from no loadTypical use
Standby diesel offered for one-step pickupabout 100% of ratingEmergency backup, automatic transfer
High-output prime-rated dieselabout 40–70%Long-running islands
Rich-burn natural gas engineabout 30–100%; many standby models take full ratingStandby and prime, smaller sets
Lean-burn natural gas engineabout 10–30%Combined heat and power, base load
Screening check for each blockblock kW ÷ (running sets × site kW) under the maker's step limitEvery transfer and restart step
Watch out
  • Blocks that transfer together add up: 300 and 350 kW on one 921 kW set is 71%, over the 60% limit in that example.
  • A motor start loads the engine at its starting kW and the alternator at its starting kVA; check both.
  • Sagging gas pressure is a common reason a gas engine fails a load step; size the gas service for full load.
Call an engineer when

Always for life-safety transfer, large motors, or gas engines: get the maker's transient simulation or factory test, repeated at commissioning.

Rough guide: Wide spread between models; author judgment from maker transient data.
Go deeper
GEN-008 · GEN-009 · ROT-GEN-06 · ROT-LOAD-11 · GEN-004 · LOAD-018
G-05Generators and fuel · DecideFor sales · engineeringTypical

Standby, prime or continuous rating: which one do I need?

Quick answer
Outage: standby
long islands or daily running need prime
In plain words

The same engine carries different kW labels depending on how many hours a year and how hard it will run. The standby label is about 10% higher than the prime label because it is meant for occasional outages only, like a car's top speed versus its comfortable cruising speed.

How to choose
Emergency standby
Choose when
  • Backup during utility outages only
  • Up to about 200 hours a year, averaging about 70% load
Avoid when
  • Daily peak shaving or market participation
  • Planned multi-week islands
Prime
Choose when
  • Islanded microgrids and long outages
  • Unlimited hours with varying load, averaging about 70%
Avoid when
  • Constant full load around the clock
Limited-time running
Choose when
  • Scheduled peak running at constant load, up to about 500 hours a year
Avoid when
  • Unplanned long outages that could exceed the hours
Continuous
Choose when
  • Constant base load with no grid, such as remote islands
Avoid when
  • Sites that only need backup; about 0.7–0.9 times the prime label costs capacity
Watch out
  • A 1,000 kW standby set is roughly 870–930 kW prime; compare quotes on the same rating.
  • Running an emergency engine for savings usually breaks its air permit; maintenance and testing are commonly capped near 100 hours a year.
  • Maker ratings differ in hours, load and overload terms; the datasheet for each rating replaces these ratios.
Call an engineer when

When the set will run for savings, markets or planned islands, or the air permit and rating class are unclear.

Typical: Common pattern in published diesel datasheets; gas sets differ.
Go deeper
ROT-GEN-01 · GEN-001 · GEN-006
G-06Generators and fuel · NumberFor sales · engineering · everyoneRough guide

How many days will my fuel tank last?

Quick answer
85–90%of the tank is usable fuel
then divide by real hourly burn, not average
In plain words

Not every gallon in the tank can be pumped out, some fuel is held back for the next delivery, and every running set burns fuel just to idle. Work out the burn hour by hour, like budgeting a road trip by the legs you actually drive rather than the average speed.

Quick math

Run hours = (tank × usable fraction − reserve) ÷ average hourly burn from the load profile

  1. Night, 10 h: one 500 kW set at 360 kW burns about 26.4 gal/h
  2. Day, 14 h: two sets at 320 kW each burn about 47.6 gal/h
  3. Daily burn: 10 × 26.4 + 14 × 47.6 ≈ 930 gal
  4. Usable fuel: 10,000 gal × 0.90 − 1,000 gal reserve = 8,000 gal; 8,000 ÷ (930 ÷ 24) ≈ 206 h
About 206 h (8.6 days) with a 1,000 gal reserve; holding 3 days of burn back instead leaves about 160 h (6.7 days)
What moves this number
← lessmore →
Average-load shortcut523 kW average × full-load fuel rate
about 4% too optimistic, worse for lightly loaded plants
Keep 3 days of burn in reserve1,000 gal → about 2,790 gal held back
about 22% fewer run hours
Less of the tank is usable90% → 85% of nominal
about 6% fewer run hours
−25%0+25%
Watch out
  • Stored diesel ages; plan to use or polish it within about 12 months and test it at least yearly.
  • Day-tank fuel only counts if its transfer pump runs on backed-up power.
  • Life-safety codes, as adopted locally, can set a minimum run time; the owner's target can be longer.
Call an engineer when

When outages may outlast deliveries, the code sets a run-time class, or several sets and boilers share one tank.

Rough guide: Arithmetic is exact; usable-fuel and reserve values are author judgment.
Go deeper
MG-026 · GEN-012 · GEN-003 · ROT-MG-20 · ROT-MG-21
G-07Generators and fuel · DecideFor sales · engineeringTypical

Diesel or natural gas generator?

Quick answer
Backup: diesel
long running hours or heat recovery lean toward gas
In plain words

Diesel brings its own fuel on site and picks up big load blocks quickly, which suits emergency backup. Natural gas needs no delivery truck and burns cleaner for long running. But it depends on the pipeline staying up and usually takes load in smaller steps, like the difference between a full pantry and grocery delivery.

How to choose
Diesel
Choose when
  • Emergency backup where large load blocks transfer at once
  • Fuel on site is required or the gas supply is interruptible
  • Running hours stay low, mostly testing and outages
Avoid when
  • Daily or long running, where cleaner engines and air permits get costly
  • No one will manage fuel testing, polishing and turnover
Natural gas
Choose when
  • Long running hours, base load or combined heat and power
  • A firm gas supply that the local authority accepts for backup
  • Fuel deliveries during a disaster are doubtful
Avoid when
  • Loads arrive in big steps and the gas model lacks one-step pickup
  • High or hot sites, where gas engines lose more capacity than diesels
Watch out
  • Whether pipeline gas counts as an emergency fuel source is the local authority's call, as adopted locally.
  • Lean-burn gas engines may take only about 10–30% of rating in one step; plan staged transfer or a battery.
  • Gas engines lose about 3–5% per 1,000 ft of altitude above a lower threshold than diesels.
Call an engineer when

When life-safety loads depend on gas, the site is high or hot, or the plan includes running for savings.

Typical: Trade-offs are well established; step and derate numbers vary by model.
Go deeper
ROT-GEN-06 · ROT-GEN-03 · ROT-MG-21 · GEN-004 · GEN-012 · CHP-005
G-08Generators and fuel · CompareFor sales · engineeringTypical

Combined heat and power, microturbines and fuel cells: are they worth a look?

Quick answer
If heat is used
the site uses the heat most hours
In plain words

Combined heat and power (CHP) means making electricity on site and using the engine's waste heat for hot water or steam. It pays only if the building really uses that heat most of the year, like a wood stove that is only a bargain if you also cook on it.

Side by side
Gas engineMicroturbineHydrogen fuel cell (proton exchange membrane, PEM)Fuel cell, solid oxide
Electric efficiency, higher heating valueabout 27–41%about 22–28%about 35–45%about 45–55%
Total efficiency, heat usedabout 75–80%about 60–70%about 55–75%about 70–85%
Size range0.1–10 MW30–1,000 kWVaries by productVaries by product
Start to full loadMinutesAbout 1–3 minutesSeconds to minutes, warmMany hours, cold
Handling load changesGood stepsRamp-limitedFast stack, slower support equipmentSlow ramps; best at steady load
Watch out
  • "Up to 90% efficient" usually means lower heating value, full load, and heat available rather than heat used.
  • Slow-ramping fuel cells and microturbines need a battery or other source to take load steps in an island.
  • Hydrogen stored and turned back into power returns only about 20–40% of the electricity put in.
Call an engineer when

When a CHP offer is on the table: ask for an hour-by-hour heat and power study and the utility's standby charges.

Typical: Representative published ranges; heat-use hours are author judgment.
Go deeper
CHP-001 · CHP-002 · CHP-003 · CHP-005 · ROT-CHP-01 · ROT-CHP-02 · ROT-CHP-03 · CHP-009
B-01Batteries · NumberFor sales · engineering · everyoneTypical

How big a battery do I need to ride through an outage?

Quick answer
1.5–1.8×the energy the load needs
battery nameplate, sized to end of life
In plain words

A battery never gives back its full label size: some is held in reserve to protect it, it fades with age, cold shrinks it, and converting its power for the building loses a little. So you buy about one and a half to almost two times the energy your loads will use, like packing a bigger fuel tank than the trip needs.

Quick math

Battery nameplate ≈ energy needed ÷ (usable window × end-of-life health × temperature factor × discharge efficiency)

  1. Load energy: 400 kW × 4 h = 1,600 kWh
  2. Add the battery's own cooling and controls: 8 kW × 4 h = 32 kWh, total 1,632 kWh
  3. Multiply the factors: 0.80 usable window (a design allowance; a new lithium iron phosphate system's limits allow 90–95%) × 0.85 health × 0.95 cold × 0.92 efficiency ≈ 0.594
  4. Divide: 1,632 ÷ 0.594 ≈ 2,750 kWh of nameplate
About 2,750 kWh (2.75 MWh) of nameplate, about 1.7 times the energy needed
What moves this number
← lessmore →
Sized for new battery onlyhealth 0.85 → 1.00
about 15% smaller battery, but short in later years
Wider usable window0.80 → 0.90 of nameplate
about 11% smaller battery
Lower end-of-life pointhealth 0.85 → 0.80
about 6% bigger battery
−15%0+15%
Watch out
  • A maker's usable-energy guarantee already includes window and aging factors; applying them again oversizes. Health 0.85 assumes blocks are added later.
  • Leaving out the battery's own cooling and controls comes up about 2% short in this example.
  • Cold outdoor systems can need more than 2 times the energy needed; removing the cold factor alone saves only about 5%.
Call an engineer when

When the load changes through the outage, solar or generators share the load, the site is cold and outdoors, or life-safety loads depend on it.

Typical: Arithmetic is exact; the factor ranges are datasheet-based judgment.
Go deeper
ESS-027 · ESS-028 · ESS-029 · ESS-030 · ESS-026 · ROT-ESS-16 · ROT-ESS-08 · ROT-ESS-10 · ROT-ESS-28
B-02Batteries · NumberFor sales · engineeringTypical

How big a battery do I need to shave my demand peak?

Quick answer
1–4 hof energy per kW shaved
delivered energy; nameplate about 1.7× more
In plain words

The battery's power has to cover the gap between the peak and the target, and its energy has to cover that gap for as long as the peak lasts. A broad afternoon peak is like a hill that widens toward the bottom: each extra slice off the top costs more energy than the last.

Quick math

Power = peak − target; energy = sum of (load − target) over the worst day; nameplate ≈ energy ÷ (window × health × cold × efficiency)

  1. Worst day, 13:00–18:00: 900, 960, 1,000, 980, 910 kW; target 850 kW
  2. Power: 1,000 − 850 = 150 kW
  3. Energy above target: 50 + 110 + 150 + 130 + 60 = 500 kWh, about 3.3 hours at 150 kW
  4. Nameplate sized to end of life: 500 ÷ (0.80 × 0.85 × 0.95 × 0.92 ≈ 0.594) ≈ 841 kWh, so pick about 900 kWh (own use not included; add about 2%)
150 kW with about 900 kWh of nameplate cuts this peak by 15%
What moves this number
← lessmore →
Shallower shavetarget 850 → 900 kW
about 50% less energy for 33% less peak cut
Sized for new battery onlyhealth 0.85 → 1.00
about 15% smaller battery, but short in later years
Wider usable window0.80 → 0.90 of nameplate
about 11% smaller battery
−50%0+50%
Watch out
  • Hourly data hides 15-minute spikes; size from the meter's own billing interval and the worst day of each month.
  • Recharging has to stay under the target too, or the battery sets a new peak overnight.
  • Needle peaks shave cheaply and flat loads expensively; run several targets before quoting savings.
Call an engineer when

Before quoting savings: it needs a year of interval data, the tariff's demand window, forecast-error margin and a recharge check under the target.

Typical: Arithmetic is exact; the load profile, not a rule, sets the answer.
Go deeper
ESS-033 · ESS-034 · ESS-028 · ESS-037 · ROT-ESS-15 · ROT-ESS-18
B-03Batteries · NumberFor sales · engineering · everyoneTypical

Why does a 1 MWh battery not deliver 1 MWh?

Quick answer
83–91%of the label reaches the building
new lithium iron phosphate system, mild weather, before own use
In plain words

The label counts all the kilowatt-hours in the cells, but the controls keep the top and bottom few percent off-limits, and converting to alternating current loses a little more. Later, aging and cold take more, like a phone that lasted a full day when new and three-quarters of one a few years on.

Quick math

Delivered ≈ nameplate × usable share × health × temperature factor × discharge efficiency − own use

  1. Nameplate 1,000 kWh, new lithium iron phosphate (LFP), mild weather
  2. Usable energy when new is 0.92 of nameplate (lithium iron phosphate range 0.90–0.95): 1,000 × 0.92 = 920 kWh inside the limits
  3. Discharge efficiency 0.94: 920 × 0.94 ≈ 865 kWh at the building's wiring
About 865 kWh, or 86% of the label, when new and warm, before the battery's own use
What moves this number
← lessmore →
Aged to end of design lifehealth 1.00 → 0.80
about 20% less, about 692 kWh
Cold cells0–10 °C, factor about 0.92
about 8% less
Own cooling and controls3% of discharged energy
about 3% less to the load
−20%0+20%
Watch out
  • Some makers state usable energy as the label; ask which one the datasheet means before applying the window again.
  • Nickel manganese cobalt (NMC) systems keep a narrower usable share, about 85–92% of nameplate when new.
  • Round trip is a separate loss: planning value about 85–90% AC to AC, before own use (a rough figure).
Call an engineer when

When a contract guarantees delivered energy, the site runs cold or hot, or the datasheet's energy basis (DC, AC or usable) is unclear.

Typical: Datasheet ranges; the arithmetic is exact.
Go deeper
ESS-029 · ESS-026 · ESS-031 · ROT-ESS-08 · ROT-ESS-16 · ROT-ESS-10 · ROT-ESS-28 · ROT-ESS-20
B-04Batteries · DecideFor sales · engineering · everyoneTypical

Which battery duration fits which job?

Quick answer
Job sets hours
power jobs under 1 h; backup 2–8 h
In plain words

Duration is how many hours a battery can run at its full power. A job that needs a short burst, like holding the site while a generator starts, needs power more than energy; a job that has to last through the evening or an outage needs energy, like a marathon runner rather than a sprinter.

How to choose
Under 1 hour (power jobs)
Choose when
  • Bridging until a generator picks up: under about 0.1 h, so power governs
  • Frequency regulation: about 0.25–1 h
  • A reserve block held for black start: about 0.25–1 h
Avoid when
  • The job is to cover an afternoon peak or an outage
1–4 hours
Choose when
  • Peak shaving: 1–4 h, with broad afternoon peaks toward 4
  • Capacity and energy-shift programs: commonly 4 h
Avoid when
  • The peak is wide and flat, so energy grows much faster than the cut
2–8 hours
Choose when
  • Backup of critical loads in an island: set by the owner's design outage
  • Time-of-use shifting and storing surplus solar: about 2–6 h
Avoid when
  • The outage runs for days; that needs an hour-by-hour simulation with solar and generators
Watch out
  • Several jobs on one battery need an hour-by-hour simulation; the longest job does not simply win.
  • Market programs set their own qualifying duration and test; check the rule before sizing.
  • Duration quoted as label energy divided by inverter rating overstates what the battery can deliver.
Call an engineer when

When jobs are stacked, outages last more than a day, solar dominates an island, or a market program sets the duration.

Typical: Widespread practice and program structures; not a standard.
Go deeper
ROT-ESS-15 · ROT-ESS-04 · ESS-031 · ESS-007 · ESS-033 · ESS-036 · ESS-043
B-05Batteries · NumberFor sales · engineering · everyoneTypical

How many cycles and years will the battery last?

Quick answer
10–15 yearsto 70–80% of new capacity
lithium iron phosphate, one cycle a day, cooled
In plain words

A battery wears out two ways at once: by the calendar, like food on a shelf, and by use, like miles on a car. In a cooled lithium iron phosphate battery cycled less than once a day, age usually wins, so heat and how full it is kept matter more than a 3,000–8,000 cycle rating.

Quick math

Cycles per year = yearly energy out of the cells ÷ nameplate; compare with the warranty's cycle cap

  1. Peak shaver: 900 kWh nameplate, 500 kWh delivered on 250 weekdays a year
  2. Out of the cells: 500 ÷ 0.92 ≈ 543 kWh a day; × 250 ≈ 135,900 kWh a year
  3. Cycles: 135,900 ÷ 900 ≈ 151 a year, about 1,510 in 10 years
  4. Warranty cap of 3,650 cycles: about 41% used
About 151 cycles a year; age, not the cycle cap, is likely to limit this battery's life
What moves this number
← lessmore →
Used every day250 → 365 days a year
about 46% more cycles
Two discharges a day500 → 1,000 kWh a day
about 100% more cycles
Deeper daily discharge500 → 750 kWh a day
about 50% more cycles
−100%0+100%
Watch out
  • Cycle ratings are cell tests at 25 °C; the installed system ages faster, and the warranty curve governs.
  • Fade speeds up after a late-life knee; early straight-line trends overstate remaining life.
  • Count cycles the way the warranty does: same nameplate basis and same cycle definition.
Call an engineer when

For more than one cycle a day, hot sites, backup batteries kept full, or any warranty or financial model past 10 years.

Typical: Warranty curves and aging studies; little field data past 10 years.
Go deeper
ROT-ESS-10 · ESS-042 · ESS-018 · ESS-019 · ESS-021 · ROT-ESS-11
B-06Batteries · CompareFor sales · engineering · everyoneTypical

LFP or NMC — what is the difference?

Quick answer
LFP, usually
for stationary storage at most sites today
In plain words

Lithium iron phosphate (LFP) stores a little less energy per pound but lasts more cycles and needs more heat before a cell runs away, so it dominates stationary storage. Nickel manganese cobalt (NMC) packs more energy into less weight and space, which matters more in a car than on a concrete pad.

Side by side
LFPNMC
Market position (2025)Dominant in stationary storageMature, declining share
Energy per kilogram, cellabout 150–205 Wh/kgabout 200–280 Wh/kg
Cycles to 80% capacity, cell at 25 °Cabout 3,000–8,000about 1,000–4,000
Fade from age alone, first yearsabout 1–2% per year at mid chargeabout 1.5–3% per year, more if kept full
Usable share of nameplate, new systemabout 90–95%about 85–92%
Charging temperature rangeabout 0–55 °Cabout 0–45 °C
Thermal runaway triggerabout 200–280 °Cabout 150–230 °C
Main hazard if a cell failsFlammable gas build-up (deflagration)Flammable gas build-up plus fire and spread; the cell releases oxygen
Watch out
  • These are cell ranges at 25 °C; the installed system's life is shorter and depends on heat, charge level and use.
  • Lower risk is not no risk: lithium iron phosphate vent gas is flammable and can ignite inside an enclosure.
  • Compare the specific product's datasheet, warranty and fire test report, not the chemistry name.
Call an engineer when

When chemistry affects fire code spacing, enclosure explosion control, cold-climate charging, or a warranty longer than 10 years.

Typical: Published datasheet ranges; several still flagged for source confirmation.
Go deeper
ROT-ESS-08 · ROT-ESS-10 · ROT-ESS-11 · ROT-ESS-12 · ROT-ESS-03 · ESS-002 · ESS-019
B-07Batteries · NumberFor sales · engineering · everyoneTypical

What do heat and cold do to a battery?

Quick answer
about 2×faster aging per 10 °C hotter
midpoint of 1.3–3×; cells 20–45 °C, idle aging
In plain words

Heat ages the cells even while they sit idle, roughly doubling the yearly fade for every 10 °C, much as food spoils faster on a warm counter. Cold does different harm: it holds less, and most lithium-ion types will not charge below freezing, so solar may not refill a frozen battery after an outage.

Quick math

Fade rate at a new temperature ≈ fade rate at 25 °C × 2 ^ ((new temperature − 25) ÷ 10)

  1. Lithium iron phosphate idle fade at 25 °C: about 1.5% a year
  2. Cells running at 35 °C: 1.5% × 2 = 3% a year
  3. Over 10 years, before the late-life knee: about 15% lost at 25 °C versus about 30% at 35 °C
A battery kept 10 °C hotter loses about twice as much capacity to age
What moves this number
← lessmore →
Gentle temperature effectfactor 2 → 1.3 per 10 °C
about 35% less fade at 35 °C
Strong temperature effectfactor 2 → 3 per 10 °C
about 50% more fade at 35 °C
Cold cells, 0–10 °Ctemperature factor 1.00 → 0.92
about 8% less usable energy while cold
−50%0+50%
Watch out
  • Plan no charging below 0 °C cell temperature, and slower charging up to about 10–15 °C, unless the maker says otherwise.
  • Sitting full and hot is the fastest-aging combination; rest at about 30–60% charge where the job allows.
  • These are cell temperatures, not outdoor air; the enclosure's cooling and heating set the gap.
Call an engineer when

For cold outdoor sites that need to recharge after an outage, hot sites without cooling margin, or backup batteries held full.

Typical: Several published aging studies; the factor spans 1.3–3× per 10 °C.
Go deeper
ROT-ESS-09 · ESS-020 · ROT-ESS-12 · ROT-ESS-11 · ESS-026 · ESS-022
B-08Batteries · NumberFor sales · engineeringTypical

How fast can the battery recharge after it is used?

Quick answer
+15–30%more time than energy ÷ power
lithium-ion, mild weather; less at slow charge rates, slower when cold
In plain words

Recharge time is the energy to put back divided by the charging power, plus a little loss; the last part of a charge slows, like filling a glass carefully near the brim. Allow 15–30% extra time, and remember that a second outage arriving mid-recharge finds the battery partly empty.

Quick math

Recharge hours ≈ energy delivered ÷ discharge efficiency ÷ (charge power × charge efficiency), plus 15–30% for the slow finish

  1. Backup battery delivered 1,632 kWh, load plus own use (B-01)
  2. Back into the cells: 1,632 ÷ 0.92 ≈ 1,774 kWh
  3. At 300 kW charging, 0.94 efficient: 1,774 ÷ (300 × 0.94) ≈ 6.3 h
  4. Add 25% for the slow finish (less at this slow rate; the maker's curve governs): about 7.9 h; the grid supplies about 1,887 kWh, 1.16 per kWh delivered
About 8 hours to refill: fits an 8-hour window, barely
What moves this number
← lessmore →
Less charging power300 → 200 kW
about 50% longer, about 11.8 h: misses the window
More charging power300 → 400 kW
about 25% shorter
Slow finish left out25% allowance → none
looks about 20% faster on paper than it is
−50%0+50%
Watch out
  • A peak shaver has to recharge below its target, so the gap under the target caps its charging power.
  • Cold batteries may need heating before they accept charge; the maker's charge-limit table governs.
  • The grid figure leaves out the battery's own cooling and controls during recharge; add them for a bill estimate.
Call an engineer when

When outages can repeat within a day, recharge comes only from solar or a generator, or the site is cold.

Typical: Recharge arithmetic is exact; the slow-finish share is product-specific.
Go deeper
ESS-037 · ROT-ESS-19 · ROT-ESS-12 · ESS-038 · ESS-007 · ROT-ESS-20
B-09Batteries · DecideFor sales · engineeringRough guide

What is augmentation, and should I plan for it?

Quick answer
Yes, if >10 yr
for a fixed energy promise; shorter terms oversize once
In plain words

Augmentation means adding battery blocks partway through a project's life to make up for fade, instead of buying all the extra on day one. It is like topping up a slowly leaking tank on a schedule rather than buying a much bigger tank at the start.

How to choose
Oversize once at the start
Choose when
  • The energy promise lasts 10 years or less: 15–25% above the required usable energy usually covers it
  • The site is tight, with no room reserved for later blocks
Avoid when
  • The promise runs down to 70% of new capacity: that alone adds about 21% nameplate versus sizing to 85% health, in the handbook example
Add blocks in steps
Choose when
  • The promise runs 15–20 years: plan steps of 5–15% of first nameplate, starting around years 3–8
  • Battery prices keep falling (a forecast, not a promise)
  • Pad space, wiring and the interconnection application can reserve room now
Avoid when
  • New cells would have to share strings with old ones; generations are not normally mixed
No promise: accept the fade
Choose when
  • Savings-only projects, where a smaller battery late in life just means smaller savings
Avoid when
  • A contract, program or critical load needs the same energy every year
Watch out
  • Over 20 years at about one cycle a day, expect about 15–30% of first usable energy added, in two or three events.
  • Each added block brings its own inverter or converter; reserve its place on the drawings from the start.
  • What augmentation costs and how prices trend belong to Cost and value.
Call an engineer when

When an energy guarantee runs past 10 years, the site has no spare pad space, or warranties would span mixed battery vintages.

Rough guide: Common project structures; author judgment, not survey data.
Go deeper
ROT-ESS-21 · ROT-ECON-07 · ESS-040 · ESS-041 · ROT-ESS-10
B-10Batteries · NumberFor sales · engineeringTypical

How much power does the battery use itself?

Quick answer
1.5–4%of the energy it discharges
daily cycling, liquid-cooled, mild climate
In plain words

A battery system runs its own cooling, heating, controls and safety equipment around the clock, whether or not it is working. Like a refrigerator that keeps humming while the house is empty, the less the battery is used, the bigger its own use looks as a share.

Quick math

Own use per year ≈ yearly energy discharged × own-use share (1.5–4% mild, 4–8% hot, cold or air-cooled)

  1. Battery discharges 1,800 kWh a day, every day: 1,800 × 365 = 657,000 kWh a year
  2. Mild climate, liquid-cooled, 2.5%: 657,000 × 0.025 ≈ 16,400 kWh a year
  3. Spread over the year: 16,400 ÷ 8,760 h ≈ 1.9 kW of average draw
About 16,400 kWh a year, close to 2 kW running all the time
What moves this number
← lessmore →
Hot or cold site, or air-cooled2.5% → 6%
about 140% more own use
Battery used half as much657,000 → 328,500 kWh a year
own-use share about doubles, since the draw is nearly fixed
Best case2.5% → 1.5%
about 40% less own use
−140%0+140%
Watch out
  • State the basis: battery-side or building-side energy, and share of discharged energy or a fixed kW per MWh.
  • In an outage the battery feeds its own cooling and controls; leaving them out makes backup fall short (see B-01).
  • When use is uncertain, ask the maker for kWh per year at the site's temperatures, not a percentage.
Call an engineer when

For hot or cold sites, air-cooled enclosures, rarely used backup batteries, or when own use counts against a performance guarantee.

Typical: Widespread practice and project data; climate moves it most.
Go deeper
ROT-ESS-28 · ROT-ECON-06 · ESS-039 · ESS-049 · ESS-027
B-11Batteries · ChecklistFor engineering · everyoneTypical

What does the battery management system actually do?

Quick answer
Guard + gauge
watches every cell, sets limits, trips if needed
In plain words

The battery management system is the battery's own nervous system. It measures every cell, works out how full and how healthy the battery is, and tells the inverter how hard it may charge or discharge. If a limit is crossed it opens the battery's own switches, like a circuit breaker with a brain.

Checklist

What it watches

What it does

What to ask the maker

Watch out
  • The inverter cannot see one hot or high cell inside a string; only the battery management system (BMS) can.
  • Settings are tied to the certification and warranty; nobody changes them without the maker.
  • Sampled temperature sensors can miss a hot spot, so the limits carry deliberate margins.
Call an engineer when

When an island depends on battery limits, settings differ from the certification report, or communication-loss behavior is undefined.

Typical: The functions are standard; every setting value is product-specific.
Go deeper
ESS-044 · ESS-014 · ESS-046 · ESS-047 · ROT-ESS-02 · ROT-ESS-07 · ROT-ESS-23
B-12Batteries · CompareFor sales · engineering · everyoneRough guide

Sodium-ion or flow batteries: are they worth a look?

Quick answer
Niche, for now
lithium iron phosphate remains the default for most sites
In plain words

Sodium-ion cells work like lithium-ion but use sodium, so they need no lithium, nickel or cobalt and claim better cold charging; they are early in the market. Flow batteries keep their energy in tanks of liquid pumped through a stack, so more hours just means bigger tanks, like adding fuel tanks without changing the engine.

Side by side
Sodium-ionVanadium flowLithium iron phosphate
Market position (2025)Early commercial; most projects in ChinaCommercial, small shareDominant
Energy per kilogramabout 80–160 Wh/kg, cell, mostly datasheets; see B-16about 10–20 Wh/kg, electrolyteabout 150–205 Wh/kg, cell
Cycles to 80% capacityabout 2,000–5,000 on typical datasheets; some makers claim far more (B-16); little independent dataabout 10,000–20,000, stackabout 3,000–8,000, cell
Cold weatherMakers claim charging to about −20 °CElectrolyte kept about 10–40 °CNo charging below about 0 °C
Adding hours meansMore cellsBigger tanks; the stack sets the kWMore cells
Round trip, battery sideLimited data; measureabout 70–80% at the stack, before pumpsHigher: about 93–96% DC when new; see B-03 for AC planning
Main hazardFlammable electrolyte; limited dataAcid spill, small hydrogen releaseFlammable gas build-up (deflagration)
Check firstListings and fire test report for the exact product; first-of-a-kind warrantyFootprint per MWh; pump and heating power in standbyFire test report and warranty curve
Watch out
  • Sodium-ion figures come from few datasheets; one independent cell test measured about 80 Wh/kg, without testing cycle life.
  • Flow battery pumps and temperature control run in standby too, so own use is significant.
  • Iron-air, aimed at about 100-hour multi-day storage, is only at first pilots.
Call an engineer when

Before committing to either, ask for independent test data, safety listings, fire test report and full warranty terms; B-15 to B-17 go further.

Rough guide: Few datasheets; values dated 2025 and changing fast.
Go deeper
ROT-ESS-03 · ESS-002 · ROT-ESS-12 · ROT-ESS-08 · ROT-COM-13
B-13Batteries · NumberFor sales · engineeringTypical

What state of charge window should I plan around?

Quick answer
90–95%of nameplate usable between limits
new lithium iron phosphate; sizing math often uses 80–90%
In plain words

State of charge is the battery's fuel gauge. The maker allows most of the gauge. A backup reserve comes out of that same window, so peak shaving gets only the part above it, like a driver who never goes below a quarter tank.

Quick math

Daily band = top limit − reserve setting; energy = nameplate × band × health × temperature factor

  1. 2,000 kWh lithium iron phosphate, limits 5–95%: window 0.90 (usable energy when new; sizing math often uses 0.80–0.90)
  2. Backup reserve set at 30%; aged to health 0.85; winter factor 0.97
  3. Reserve: 2,000 × (0.30 − 0.05) × 0.85 × 0.97 ≈ 412 kWh
  4. Daily band 30–95%: 2,000 × 0.65 × 0.85 × 0.97 ≈ 1,072 kWh
About 1,070 kWh a day of DC energy in the cells for peak shaving from a 2,000 kWh label; the reserve takes 28% of the window
What moves this number
← lessmore →
Smaller reserve30% → 20%
about 15% more daily energy
Colder wintertemperature factor 0.97 → 0.92
about 5% less daily energy
New batteryhealth 0.85 → 1.00
about 18% more daily energy, early years only
−20%0+20%
Watch out
  • A lithium iron phosphate gauge drifts a few percent between full charges; hold a margin or schedule periodic full charges.
  • Some systems show a rescaled 0–100% user gauge; confirm which one the controller reads before setting the reserve.
  • Resting near full ages cells fastest; a backup battery trades some life for readiness, so count that cost.
Call an engineer when

When the reserve has to cover black start or a guaranteed outage, or the same battery is also bid into a market.

Typical: Window from datasheets; the reserve is the owner's choice.
Go deeper
ROT-ESS-08 · ESS-017 · ESS-043 · ESS-026 · ROT-ESS-02 · ROT-ESS-11 · ROT-ESS-22
B-14Batteries · NumberFor engineering · everyoneTypical

How much heat does a battery make?

Quick answer
1–3%of battery power becomes heat
lithium iron phosphate, 2–4 hour rates, inverter outside
In plain words

Every cell has a little internal resistance, so some of the power flowing in or out turns into heat, the way a cord warms when it carries a heater's current. The faster it charges or discharges, the bigger that share, so a 2-hour battery runs warmer than a 4-hour one. Cooling is sized above the cell heat to cover sun on the walls and equipment inside.

Quick math

Cell heat ≈ heat share × battery power; cooling capacity ≈ 1.2–1.6 × cell heat

  1. 2,000 kWh battery discharging at 1,000 kW, a 2-hour rate
  2. Heat share at this rate about 2%: 1,000 × 0.02 = 20 kW
  3. Cooling capacity: 20 × 1.4 = 28 kW, after own use, wall gain and margin
About 20 kW of heat; plan about 28 kW of cooling for new cells, more at end of life
What moves this number
← lessmore →
4-hour battery, same power2,000 → 4,000 kWh at 1,000 kW
about 50% less heat
Aged or cold cellsinternal resistance doubles
about 100% more heat
Inverter inside the enclosureadds about 2% of its power
about 20 kW more, roughly double
−100%0+100%
Watch out
  • Nickel manganese cobalt and aged cells run hotter; size cooling at end-of-life resistance.
  • Cooling power is part of the battery's own use; a hotter battery raises that bill (see B-10).
  • The maker's heat-rejection data govern the final cooling design.
Call an engineer when

For 1-hour or faster batteries, inverters inside the enclosure, hot climates, or indoor rooms where building cooling carries the heat.

Typical: Consistent with published efficiencies and maker heat-rejection data.
Go deeper
ROT-ESS-27 · ESS-023 · ESS-048 · ROT-ESS-13 · ESS-049
B-15Batteries · ChecklistFor sales · engineering · everyoneTypical

What makes a new battery technology bankable?

Quick answer
Evidence first
field history, test data, listings, a warranty that holds
In plain words

A battery is bankable when lenders, insurers and the fire official accept it on the evidence in hand, not when its chemistry looks promising. Think of a new driver: a clean test record and years of insured miles count; a fast car does not.

Checklist

Lenders and their independent engineer

Insurers

The fire official

The owner

Watch out
  • As of late 2026 practice is changing fast; no lender publishes minimum years of history. The product's evidence governs.
  • A supplier ranking measures acceptance, not quality; its publisher points banks to technical due diligence.
  • Lenders usually keep the loan term inside the capacity warranty and offtake contract terms.
Call an engineer when

Before financing a first-of-a-kind battery: commission an independent engineer's technology review and get the lender's and insurer's evidence requirements in writing.

Typical: Lender practice is published only in pieces; terms vary by deal.
Go deeper
ROT-ECON-19 · ECON-033 · ROT-ECON-23 · ECON-041 · STD-005 · STD-008 · ROT-STD-06 · ROT-STD-07
Public sources
Sargent & Lundy (2026). Battery energy storage systems independent engineering due diligence.
U.S. Department of Energy (2025). Lithium-ion BESS Technical Specifications.
Energy-Storage.news (2024). BloombergNEF launches Tier 1 list (criteria as reported).
ESS News (2025). What insurers want battery developers to understand right now (underwriter interview).
B-16Batteries · CompareFor sales · engineering · everyoneRough guide

Sodium-ion chemistries: which is which, and how close are they?

Quick answer
Still early
as of late 2026; little independent field data
In plain words

Sodium-ion is a family: the positive-side material, the cathode, sets voltage, energy and life, as flour sets bread. Sodium chromium oxide has published half-cell lab results but almost no independent full-cell data yet.

Side by side
Layered oxideSodium chromium oxidePolyanionPrussian blue analog
Energy per kg165 Wh/kg, lab cell. One maker claims about 160Not public; cathode 129–130 milliamp-hours per gram, half cellsAbout 80 Wh/kg, independent test. Makers claim about 100About 100–130 Wh/kg, one startup cell
Cycle life (test)Lab cell: 92% after 100. Maker claims 15,000; no report publicHalf cells 75–81% after 1,000 (5–10C); full cell 67% after 250. Maker claims more; no report publicNo independent test. Maker claims 20,000; no report publicA weak point, per reviews; no public test
Safety evidenceFull-cell tests: runaway from about 135–277 °C; one at 30% chargeMaterial abstracts: stable to about 250 °C. No full-cell data or listing. Maker claims fire test; no report publicCoin-cell tests only; no listing found. Maker claims fire test; no report publicNo public abuse data or listing
Status, late 2026Deliveries announced, large orders; no independent field reportPre-commercial; first cell shipments reportedU.S. pilot 2025, supply deals 2027–2030; no independent field reportOne U.S. maker closed in 2025
Open questionDoes field life match the datasheet?Full-cell safety and life data, independent of the makerEnergy per kg; independent cycle dataCan any maker reach scale?
Watch out
  • As of late 2026 the field moves fast; the specific product's tests, listing and warranty govern.
  • Half cells test the cathode against pure sodium; full cells usually keep less. Ask which.
  • Voltage swings wider full to empty than lithium iron phosphate; check the inverter's direct current window.
Call an engineer when

Before specifying: an independent engineer's technology review, the lender's requirements and the exact product's full-cell data and listing.

Rough guide: Mostly maker claims and lab cells.
Go deeper
ROT-ESS-03 · ESS-003 · ESS-002 · ROT-STD-06
Public sources
Microstructures (2024). Layered cathode review.
MDPI Batteries. Electrode thermal runaway.
Sandia National Labs (2026). Sodium-ion safety.
RSC (2025). Cell thermal runaway.
RSC. NaCrO2 high-rate cathode.
Electrochem. Soc. (2013). NaCrO2 safety abstract.
CSIR. NFPP cell test.
PubMed Central. Prussian blue data review.
B-17Batteries · CompareFor sales · engineering · everyoneRough guide

Beyond lithium and sodium: which long-duration technologies are getting close?

Quick answer
Close, not yet
as of late 2026; pilots and single suppliers dominate
In plain words

Long-duration storage aims to hold energy for many hours or days, the way a pantry holds a week of food rather than tonight's dinner. Some types have years in service but one supplier, others have one pilot, so each is missing a different piece of evidence.

Side by side
Iron-airZinc-basedVanadium flowSodium-sulfur
How it worksIron-air chemistry aimed at multi-day storageZinc chemistry instead of lithiumLiquid pumped from tanks through a stackSodium and sulfur, run at high temperature
Duration classMaker aims for about 100 hours, multi-dayNot stated in the public sources reviewed4 hours at the largest public site; tanks set the hoursMaker states 6–8 hours
Largest public deploymentOne 1.5 MW / 150 MWh pilot, ground broken 2024; reports conflict on whether it runsDeployed total not public; maker targets large factory output by end-2026100 MW / 400 MWh first phase grid-connected in China, 2022Maker claims about 720 MW / 5,000 MWh at over 250 sites since 2002
Evidence in handGroundbreaking reported 2024; the maker says it operated in late 2025, not independently confirmedMaker's datasheet lists system and module listings and fire testingGrid-connected at large scale since 2022; little operating data publishedIn commercial service since 2002, per the maker
Still missingMulti-year field performance, measured round-trip efficiency, independent confirmation it runsField fade data from a fleet; deployed totalsPublic warranty terms; operating data from the largest sitesIndependent fleet data; a second supplier
Watch out
  • As of late 2026 this field is changing fast; the specific product's operating data, listing and warranty govern.
  • One major independent engineering firm expects flow and other long-duration types to scale only in the second half of the 2030s.
  • An installed-base figure from a maker is a claim until an owner or utility publishes operating results.
Call an engineer when

Before planning on any long-duration type: get an independent engineer's technology review and the lender's evidence requirements, and ask for operating data from a named site.

Rough guide: Few independent field results; most figures are makers' or press reports.
Go deeper
ESS-002 · ESS-008 · ESS-039 · STD-005
Public sources
UNIDO ITPO Tokyo (2018). NAS sodium-sulfur battery technology entry.
Energy-Storage.news. Long duration energy storage to scale in second half of 2030s, says DNV (as reported).
I-01Inverters and conversion · NumberFor sales · engineeringTypical

How big an inverter do I need, and why is it rated in kVA instead of kW?

Quick answer
1.1–1.3×peak kW, stated in kVA
island serving mixed commercial load
In plain words

An inverter's real limit is current, and motors and lighting draw extra current that does no useful work, so it is rated in kilovolt-amperes (kVA), not kilowatts (kW). Size it like a doorway for a crowd carrying bags: the people are the kilowatts, the bags are the extra current, and the door has to fit both.

Quick math

Inverter kVA ≈ peak kW ÷ power factor, then apply heat and altitude derates

  1. Island peak load: 800 kW
  2. Typical commercial power factor: 0.85
  3. Divide: 800 ÷ 0.85 ≈ 941 kVA
  4. Check the ratio: 941 ÷ 800 ≈ 1.18
About 940 kVA of inverter, about 1.18 times the peak kW
What moves this number
← lessmore →
Poorer power factor0.85 → 0.80
about 6% bigger inverter
Better power factor0.85 → 0.90
about 6% smaller inverter
Grid-connected peak shaving onlypower factor 0.85 → 1.0
about 15% smaller inverter
−15%0+15%
Watch out
  • A utility that asks for full reactive power at rated kW pushes the ratio to about 1.10–1.15, even grid-connected.
  • Ratings hold only at the maker's reference temperature and altitude; hot or high sites lose more (see the derating card).
  • Motor starting is checked separately and can call for a much bigger inverter than the steady load does.
Call an engineer when

When the interconnection requires reactive power support, motors or drives dominate the load, or the site is hot or above 1,000 m.

Typical: Power-triangle arithmetic; two source ranges overlap (1.1–1.25, 1.2–1.3); power factor is judgment.
Go deeper
FUN-009 · FUN-017 · PCS-001 · PCS-003 · ROT-ESS-17 · ROT-FUN-06 · ROT-MG-02 · ROT-PCS-01
I-02Inverters and conversion · CompareFor sales · engineering · everyoneTypical

How efficient is an inverter?

Quick answer
about 98%one way
large inverter without built-in transformer, 30–100% load
In plain words

A modern large inverter passes on about 98 of every 100 kilowatt-hours (kWh) it converts and turns the rest into heat. Like a car's fuel economy, the brochure figure holds at steady cruising; at very light load the fixed losses take a much bigger bite.

Side by side
Efficiency, one wayWhere you see it
Inverter without built-in transformer, above 50 kilovolt-amperes (kVA), 30–100% loadabout 98.0–98.8%Most commercial and utility battery and solar inverters
Large central inverter, 1–5 megavolt-amperes (MVA), best point on the curveabout 98.5–99.0%Peak only; not a yearly average
Inverter with built-in isolation transformerabout 96–97.5%Common in 30–250 kVA commercial units
Home or small-business hybrid inverter, battery to ACabout 94–97%One listed box doing several conversions
DC-to-DC (direct current) converter, no transformerabout 98.5–99.5%Battery or solar converters in DC-coupled designs
Inverter round trip, charge then dischargeabout 96–97.5%Without transformer; about 92–95% with one
Very light load, example inverter at 5% of ratingabout 95.6%Fixed losses dominate below about 10% load
Watch out
  • Datasheet peak and weighted efficiency are not yearly averages; light-load hours and standby losses pull the real figure down.
  • Inverter efficiency is one slice only; battery, transformer and cooling losses come on top (see Batteries).
  • Efficiency shifts with battery voltage and direction; ask for curves at the actual voltage range, charging and discharging.
Call an engineer when

When an efficiency guarantee is in the contract, a transformer sits inside the inverter, or the unit spends many hours near idle.

Typical: Author compilation of datasheets and listed test data, 2020–2025.
Go deeper
PCS-006 · PCS-007 · PCS-014 · PCS-027 · ROT-PCS-03 · ROT-COM-11
I-03Inverters and conversion · NumberFor sales · engineeringTypical

Can the battery inverter start my motors when the grid is down?

Quick answer
4–6×motor running kVA
grid-forming inverter, motor started straight across the line
In plain words

A motor started straight across the line draws about six to eight times its running current for a few seconds. An inverter can push only about 1.2–1.5 times its rating for that long. So with no generator running, the inverter needs roughly four to six times the motor's running kilovolt-amperes (kVA), like a loaded truck that needs full throttle just to get rolling.

Quick math

Inverter kVA needed ≈ target voltage × (motor starting kVA + other load kVA) ÷ inverter short-time overload

  1. Motor: 100 hp, 686 kVA while starting; other load 200 kVA; total 886 kVA
  2. A 500 kVA inverter at 1.5 times rating for 3 seconds gives 750 kVA
  3. Voltage during the start ≈ 750 ÷ 886 ≈ 0.85 of normal, a 15% sag
  4. To hold 0.90 of normal: 0.90 × 886 ÷ 1.5 ≈ 532 kVA
About 530 kVA of grid-forming inverter, not 500
What moves this number
← lessmore →
Weaker overload rating1.5 → 1.2 times rating
about 25% bigger inverter
Motor starts with nothing else onother load 200 → 0 kVA
about 23% smaller inverter
Accept a deeper sag0.90 → 0.85 of normal voltage
about 6% smaller inverter
−25%0+25%
Watch out
  • Grid-following inverters often have no overload beyond about 1.0–1.1 times rating; they cannot start motors on their own.
  • At a 15% sag the motor has only about 72% of its normal starting torque; a loaded pump may stall.
  • Soft starters and drives cut starting current sharply; motor data from the load side are in Loads.
Call an engineer when

When a motor above about 10–15 hp per 100 kVA of inverter starts with no generator online, or loads cannot ride the sag.

Typical: Derived from the inverter current-limit screen and typical motor data.
Go deeper
PCS-024 · PCS-010 · LOAD-023 · ROT-PCS-11 · ROT-PCS-06 · ROT-LOAD-10 · ROT-MG-12
I-04Inverters and conversion · CompareFor sales · engineering · everyoneTypical

Grid-forming or grid-following: what is the difference?

Quick answer
Forming leads
every island needs at least one forming source
In plain words

A grid-following inverter listens for the grid's voltage and pushes current in step with it, so something else has to set the beat. A grid-forming inverter sets voltage and frequency itself, the way a generator does. Think of a band: followers play along with the drummer, and with no drummer, as when the grid is gone, there is no song.

Side by side
Grid-followingGrid-forming
Behaves likeA controlled current sourceA voltage source, like a generator
Keeps in step byTracking the measured grid voltageBalancing power, the way generators share load
Needs another source to runYesNo, if the battery and controls allow
Sudden load changeReacts only after its controls detect the changePicks it up at once, up to its current limit, then frequency and voltage settle
On a weak gridStruggles below the maker's grid-strength limitAdds strength up to its current limit
Short overload, battery invertersOften none beyond about 1.0–1.1 times ratingAbout 1.1–1.2 times for minutes, 1.2–1.5 times for seconds
Role on an islandEnergy source on a bus someone else formsReference, balancing and first response
Watch out
  • An island of only grid-following inverters cannot run: nothing sets frequency or absorbs a sudden mismatch.
  • The label does not prove black start, motor starting or protection performance; each needs its own test evidence.
  • Where the short-circuit ratio is below about 3, plan a detailed study; below about 2, the study decides if a forming source is needed.
Call an engineer when

When grid-forming and grid-following inverters share an island, inverters supply over half the island's sources, or black start relies on inverters.

Typical: Behavior is well established; capability varies widely by product and firmware.
Go deeper
PCS-022 · PCS-023 · PCS-026 · ROT-PCS-06 · ROT-PCS-10 · ROT-PCS-13 · ROT-PCS-14 · ROT-SYS-22
I-05Inverters and conversion · DecideFor sales · engineeringTypical

AC-coupled or DC-coupled solar-plus-storage?

Quick answer
Retrofit: AC
new build with heavy solar clipping leans DC
In plain words

AC-coupled means the solar inverter and the battery inverter each connect to the building's alternating current (AC) wiring on their own; DC-coupled means solar and battery share one inverter on the direct current (DC) side. Think separate front doors versus one shared door: separate doors keep working if one jams, while a shared door saves a step for energy going from panels to battery.

How to choose
AC-coupled
Choose when
  • Existing solar inverters stay as they are, with no battery port
  • Over about half the battery's charge comes from the grid or a generator
  • Solar and battery need separate metering
  • One inverter failure should not take out both solar and battery
Avoid when
  • Solar clipping is large and worth recapturing
DC-coupled
Choose when
  • Inverter clipping exceeds about 2% of available solar energy
  • Grid connection capacity is the binding limit, so solar is oversized
  • Most charging comes from solar
  • Existing solar inverters are near end of life anyway
Avoid when
  • The battery charges mostly from the grid
  • The site needs solar to keep running if the shared inverter fails
Hybrid (one multi-port inverter)
Choose when
  • Homes and small commercial sites wanting one listed box
Avoid when
  • One unit failing would drop solar, battery and backup together
Watch out
  • The efficiency gap is small, about 0.2–1.0% of yearly delivered energy; clipping, standby losses and failure modes usually decide.
  • In an outage, a failed shared DC-coupled inverter takes solar and battery down together.
  • Tax credits: commercial storage now qualifies alone, subject to 2026 sourcing rules; the home credit ended after 2025. Confirm with tax counsel.
Call an engineer when

When clipping exceeds about 2% of solar energy, battery voltage approaches inverter limits, or the island depends on one coupling surviving a failure.

Typical: Efficiency rule is well supported; crossover thresholds are author judgment.
Go deeper
PCS-027 · PCS-028 · PCS-029 · PCS-033 · ROT-PCS-15 · ROT-PCS-16 · ROT-PCS-17 · ROT-PCS-19 · ROT-PV-04
I-06Inverters and conversion · NumberFor engineering · salesRough guide

How much does a hot or high-altitude site cut the inverter's rating?

Quick answer
2–2.5%/°Cof rating lost
above about 40–45 °C at the air inlet
In plain words

Inverters are cooled by fans, and hotter or thinner air carries away less heat, so above a set temperature or altitude the inverter turns its own output down. Expect to lose about 2–2.5% of rating for each degree above about 40–45 °C at the air inlet. Expect about 1% more per 100 m above about 1,000 m, like a runner slowing on a hot day in the mountains.

Quick math

Site rating ≈ nameplate × (1 − loss per °C × degrees over the limit) × (1 − 1% × each 100 m over 1,000 m)

  1. Nameplate 2,500 kVA; design inlet 48 °C, 3 °C over a 45 °C limit
  2. Heat factor: 1 − 0.025 × 3 = 0.925
  3. Altitude 1,800 m, 800 m over 1,000 m: 1 − 0.01 × 8 = 0.92
  4. Site rating: 2,500 × 0.925 × 0.92 ≈ 2,128 kVA
About 2,130 kVA, about 85% of nameplate
What moves this number
← lessmore →
Hotter inlet air48 → 52 °C
about 11% less rating
Low-altitude site1,800 m → below 1,000 m
about 9% more rating
Gentler maker's curve2.5% → 2% per °C
about 2% more rating
−15%0+15%
Watch out
  • Inlet air in sun runs about 3–5 °C above the design outdoor temperature; size on inlet temperature, not the forecast.
  • Liquid-cooled and indoor inverters follow different curves; the product's datasheet curve replaces these screening slopes.
  • Above about 2,000 m insulation can also limit battery voltage; get the maker's written altitude statement.
Call an engineer when

When the design temperature is above about 40 °C, the site is above 1,000 m, or the derated rating sets how many inverters to buy.

Rough guide: Author judgment from a sample of datasheet derate curves.
Go deeper
PCS-008 · PCS-009 · PCS-011 · ROT-PCS-04 · ROT-PCS-05
I-07Inverters and conversion · NumberFor sales · engineering · everyoneTypical

How much energy is lost going from solar to battery to the building?

Quick answer
about 89–91%delivered
solar stored in the battery, then used
In plain words

Every conversion between panel, battery and building skims off a percent or two, and energy that goes through the battery crosses five conversions instead of one. Solar used right away arrives at about 98%, while solar stored and used later arrives at about 89–91%, like paying a small toll at every bridge on a longer route.

Quick math

Path efficiency = the efficiencies of every stage multiplied together

  1. Solar inverter 0.98 × battery inverter charging 0.98
  2. × into the battery 0.975 × out of the battery 0.975
  3. × battery inverter discharging 0.98 ≈ 0.895
  4. So 1,000 kWh of solar sent through the battery delivers about 895 kWh
About 89.5% delivered when AC-coupled; about 91.3% when DC-coupled
What moves this number
← lessmore →
DC-coupled, plain DC-to-DC converterAC → DC coupling
about 2% more delivered
DC-coupled, isolated DC-to-DC converterAC → DC coupling with isolation
about 1% less delivered
Battery behind its own transformertwo extra passes at 0.99
about 2% less delivered
−5%0+5%
Watch out
  • These are screening values at 30–100% load; light-load hours and standby losses lower the real yearly figure.
  • Grid-charged energy reverses the result: AC coupling wins that path by about the same margin.
  • Battery losses here are new-system screening values; planning round trip, with cooling and controls, is lower; see Batteries.
Call an engineer when

When a guarantee or bankable energy estimate depends on it; a time-step simulation with real efficiency curves then replaces this.

Typical: Exact stage arithmetic; stage efficiencies are datasheet screening values.
Go deeper
PCS-027 · PCS-028 · PCS-033 · ROT-PCS-15 · ROT-PCS-16 · ROT-ESS-20
I-08Inverters and conversion · NumberFor engineering · salesRough guide

How much power does an inverter burn when it is not doing anything?

Quick answer
0.1–0.3%of rated kVA, awake at zero output
large inverter, no transformer; asleep about 0.005–0.02%
In plain words

An inverter that is switched on but idle still runs its controls, fans and filters, burning about 0.1–0.3% of its rated kilovolt-amperes (kVA) around the clock. Like a car idling in the driveway, the hours add up, and a sleep mode that shuts most of it down wins most of the loss back.

Quick math

Yearly standby energy = awake idle kW × hours + asleep kW × hours + running extras kW × hours

  1. 2,500 kVA inverter awake at zero output: 5.0 kW × 3,000 h = 15,000 kWh
  2. Asleep: 0.3 kW × 4,300 h = 1,290 kWh
  3. Extras outside the efficiency figure while running: 2.0 kW × 1,460 h = 2,920 kWh
  4. Total ≈ 19,200 kWh, about 19 MWh a year
About 19 MWh a year, about 1.3% of 1,460 MWh discharged
What moves this number
← lessmore →
Sleeps instead of idling awake3,000 h awake → asleep
about 73% less standby energy
Never sleepsall 7,300 idle hours awake
about 105% more, roughly double
Higher idle loss0.2% → 0.3% of kVA awake
about 39% more standby energy
−105%0+105%
Watch out
  • These figures leave out enclosure cooling, coolant pumps and the transformer, which add their own idle load.
  • Supplying reactive power at night keeps the inverter awake and adds losses even at zero kW.
  • Datasheet efficiency excludes standby energy; ask the maker for awake-idle and sleep kW separately.
Call an engineer when

When the system idles most hours, as backup-only batteries do, or supplies reactive power at night.

Rough guide: Author judgment from a sample of datasheets.
Go deeper
PCS-012 · PCS-006 · ROT-PCS-07 · ROT-ESS-28
M-01How a microgrid behaves · NumberFor engineering · salesTypical

What happens the instant the grid fails, and how big a battery inverter catches it?

Quick answer
1.1–1.2×(battery output + grid import + solar that may trip)
grid-forming inverter kVA, unplanned island
In plain words

When the grid fails, the utility breaker opens and one grid-forming source, usually the battery's inverter, has to pick up everything the grid was supplying. It also has to cover any solar that drops off, like a relay runner grabbing the baton at full speed while a second runner may also fall. Size for both, plus a little extra for motors speeding back up.

Quick math

Inverter kVA ≥ √[(battery output before + grid import + solar that may trip)² + (reactive import)²] × 1.1–1.2

  1. Before the outage: battery 150 kW, grid import 850 kW and 300 kvar, solar 600 kW
  2. Worst case, solar trips too: real power 150 + 850 + 600 = 1,600 kW
  3. Combine with 300 kvar: √(1,600² + 300²) ≈ 1,630 kVA
  4. Add 10–20% for motors speeding back up: 1,630 × 1.1 to 1.2 ≈ 1,790–1,950 kVA
About 1,790–1,950 kVA; a 2,000 kVA battery inverter would cover the worst case in this example
What moves this number
← lessmore →
Solar rides through the dip600 kW of solar stays on
about 36% smaller inverter
Grid import capped while connected850 kW → 400 kW import
about 27% smaller inverter, but the cap becomes a tested safety function
More motor loadmargin 10% → 20%
about 9% bigger inverter
−40%0+40%
Watch out
  • If the site was exporting when the grid failed, the step reverses: the battery needs room to absorb, not supply.
  • A generator alone can rarely take a step this large at once; a battery that forms the grid usually catches it.
  • The step size here is steady power; the actual voltage and frequency dip needs the vendor's dynamic model.
Call an engineer when

When the step exceeds about half the inverter rating, large motors are running, or the site may be exporting at the moment of failure.

Typical: Power balance is exact; the 10–20% motor margin is judgment.
Go deeper
MG-012 · MG-013 · ROT-MG-08 · MG-001 · MG-002 · ROT-MG-02
M-02How a microgrid behaves · CompareFor sales · engineering · everyoneTypical

How long do the lights blink when the grid goes down?

Quick answer
0 to 10+ s
set by the transfer type, not the brand
In plain words

How long the building goes dark depends on how the backup takes over. A generator has to start and get up to speed, while a battery that is already running can take over in a fraction of a second. Think of a standby driver asleep in the back seat versus one already holding the wheel.

Side by side
Break the load seesGood enough for
Generator with transfer switch, starts on outageabout 2–10 s and longer; one worked example is 8.2 sHeating, cooling, and code emergency loads in the 10-second class
Transfer switch to a source already runningabout 0.05–0.5 s of dead busLoads that ride through a short dropout
Utility breaker opens, battery takes over0 to about 0.15 s out of tolerance; one worked example is 120 msLoads tolerating 20 ms–0.2 s; drops unprotected computers and contactors
Fast electronic (static) switch, battery already formingunder half a cycle after detection; about 13 ms total in one exampleComputer power supplies without their own backup, motor contactors
Planned transfer, make before break0 if synchronizedPlanned islanding and return to grid only; not a sudden outage
Online uninterruptible power supply at the load0 while its battery lasts; its inverter always carries the loadSmall, critical loads such as servers and controls
Watch out
  • During detection the load sees a sagging grid voltage, not zero; whether that counts depends on the load.
  • "Quarter-cycle" claims usually describe detection only; the full break is longer.
  • Measure each step at commissioning with time-synchronized recorders; datasheet times are a first budget, not a result.
Call an engineer when

When any load cannot tolerate a 10-second break, or the customer needs a stated maximum interruption in the contract.

Typical: Device time classes from datasheets; confirm with the selected equipment and test.
Go deeper
MG-010 · MG-011 · ROT-MG-06 · ROT-MG-07
M-03How a microgrid behaves · DecideFor sales · engineeringTypical

Can we promise the customer a "seamless" transfer?

Quick answer
Specify in ms
voltage band and maximum duration at the loads
In plain words

"Seamless" is a sales word, not a test. What can honestly be promised is that named loads see no more than a stated time outside a stated voltage band, measured at the loads. Match the takeover method to the most sensitive load, like choosing a lifeguard by the weakest swimmer in the pool.

How to choose
Fast electronic (static) switch with the battery already forming
Choose when
  • Computer power supplies without their own backup ride through only about 20 ms
  • Motor contactors drop out after 1–3 cycles below about 60–70% voltage
  • Many sensitive loads, so one switch is simpler than many small backups
Avoid when
  • The sensitive loads already sit on their own uninterruptible power supplies
Utility breaker opens while the battery takes over
Choose when
  • The most sensitive load tolerates 20 ms–0.2 s
  • Variable-frequency drives have ride-through enabled
Avoid when
  • Unprotected computers or contactors would drop in a break of about 120 ms
Generator with transfer switch
Choose when
  • Loads tolerate a break of more than about 10 seconds: heating, cooling
  • Code emergency loads already designed for the 10-second class, as adopted locally
Avoid when
  • Anything that cannot tolerate a few seconds dark
Small backup units at the sensitive loads only
Choose when
  • Only a few loads are sensitive, such as controls with 10–20 ms hold-up
  • Restart after a dropout takes hours, so downtime cost decides
Avoid when
  • Sensitive loads are spread across the whole site
Watch out
  • Safe to say: "named critical loads see no more than X ms outside a stated voltage band, measured at the loads."
  • Where restart takes hours, downtime cost, not electrical tolerance, decides how fast the transfer needs to be.
  • Motor loads may need a deliberate 1–3 s pause before reconnecting, unless an in-phase check allows faster.
Call an engineer when

When a contract names an interruption limit, motors over about 500 hp share the bus, or loads cannot tolerate 20 ms.

Typical: Published equipment tolerance envelopes; confirm with equipment data and site test.
Go deeper
ROT-MG-06 · MG-010 · MG-011 · ROT-MG-07
M-04How a microgrid behaves · NumberFor engineering · salesRough guide

How does the system restart from dark, and how much battery charge should be held back for it?

Quick answer
5–25%of battery nameplate
restart energy alone; short handoff, light restored load
In plain words

A black start brings a dead site back with no grid: the battery wakes up, energizes the transformers and picks up loads in blocks until a generator takes over. Waking up uses almost nothing; waiting for the generator while carrying load drains the battery, like idling a car with the air on.

Quick math

Charge floor ≈ bottom limit + (restart energy ÷ discharge efficiency + standby energy) ÷ (nameplate × end-of-life health × cold factor)

  1. Restart sequence: wake 0.6 + transformers 0.8 + first tier 27.4 + second tier 95.7 + generator wait 95.7 ≈ 220 kWh
  2. Allow one failed attempt: + 28.8 kWh = 248.9 kWh, about 12% of a 2,000 kWh nameplate
  3. Battery side: 248.9 ÷ 0.96 + 5 kWh standby ≈ 264 kWh
  4. Floor: 0.05 + 264 ÷ (2,000 × 0.80 health × 0.95 cold) ≈ 0.224
Restart energy is about 12% of nameplate; with losses, battery health and cold, hold about 22% charge in reserve (about 42% if the handoff takes 60 minutes)
What moves this number
← lessmore →
Sized for a new battery onlyhealth 0.80 → 1.00
floor about 19%, but too low in later years
No failed attempt allowed fordrop the 28.8 kWh retry
floor about 20%
Generator takes 30 min longerhandoff 30 → 60 min
floor about 42%; waiting dominates
−90%0+90%
Watch out
  • A grid-forming label is not proof: ask for a witnessed restart from a dead bus on the as-built system.
  • Long handoffs or heavy restored load can need 40% or more; if the generator may not start, it is an autonomy question.
  • Cold cells can block a restart on power limits even with enough charge.
Call an engineer when

When no second source exists, the site is cold, the inverter energizes large transformers, or retries are automatic.

Rough guide: Arithmetic exact; the 5–25% range and handoff time are author judgment.
Go deeper
MG-018 · MG-019 · ROT-MG-11 · ROT-MG-14 · ESS-043 · ROT-ESS-22
M-05How a microgrid behaves · CompareFor sales · engineering · everyoneTypical

How much solar can an island run on?

Quick answer
15% to 100%
of load at any moment, by system type
In plain words

On an island the generators set the rhythm, and they should not run below roughly 30% of their rating for long. Solar can only fill the gap above that floor unless a battery takes over the rhythm and lets the generators switch off. Keep two numbers apart: a sunny noon can reach 100% solar while the whole year still runs on only about 40% solar energy.

Side by side
Solar share at any momentSolar share of the year's energy
Generators only, no storage or solar controlabout 15–25% of minimum daytime loadabout 2–5%; more solar needs cutback control
Generators plus fast solar cutback and reserveabout 30–60%about 10–25% before wasted solar climbs steeply
Battery of 1–3 hours that can form the gridabout 60–100%; generators can switch offabout 40–70%
Above about 80% of the yearas in the battery row, for most hoursneeds multi-day storage or a large, heavily wasted solar overbuild
What sets the limitgenerator minimum loading, commonly 30% (25–40%), plus reserveweather, night load, battery duration
Watch out
  • Ask which number is meant: share at a moment, or share of the year's energy. They differ widely.
  • Above roughly 50–70% inverter share at a moment, stability needs a dynamic study, not a ratio.
  • Ranges assume mid-latitude sun and a daytime peak; night-peaking loads and high latitudes shift every row.
Call an engineer when

When solar exceeds about a quarter of minimum daytime load on a generator island, or a renewable target above about 40% is promised.

Typical: Widespread hybrid practice; annual ranges low to medium confidence.
Go deeper
ROT-MG-16 · ROT-MG-17 · MG-028 · MG-029 · ROT-GEN-05 · GEN-007
M-06How a microgrid behaves · NumberFor engineeringRough guide

How much reserve should an island hold back?

Quick answer
Largest lossof supply, often a cloud on the solar
spare online kW until backup starts
In plain words

Reserve is spare power already running, enough to cover the biggest thing that could suddenly disappear until slower backup starts. On a solar island the biggest loss is often a cloud, not a generator. Think of a lifeguard already standing at the pool edge, not one still driving over.

Quick math

Reserve kW ≈ larger of (largest source online) or (ramp fraction × solar rating, capped at present solar output, + 10% of load); battery energy ≈ reserve × backup start time

  1. Load 900 kW; 600 kW of solar producing 450 kW; one 500 kW generator at 450 kW; 600 kW battery
  2. Cloud drop: lesser of 0.70 × 600 = 420 and 450, so 420 kW; plus 10% of 900 = 90 kW; total 510 kW
  3. Largest source online: the generator at 450 kW; the larger of 510 and 450 is 510 kW
  4. Battery energy held: 510 kW × 0.25 h for backup start ≈ 128 kWh
Hold about 510 kW of spare power and about 128 kWh of battery energy above the floor
What moves this number
← lessmore →
Steadier solarramp fraction 0.70 → 0.50
about 12% less; the generator trip now sets it
Choppier solarramp fraction 0.70 → 0.80
about 6% more; capped by present solar output
Slower backup start15 → 30 minutes
twice the battery energy held; kW unchanged
−100%0+100%
Watch out
  • Running one generator with the battery as reserve saves fuel but makes the battery the survival path; test that takeover.
  • Reserve in kW says nothing about speed; how deep frequency dips needs a dynamic study.
  • Hold this energy on top of the black-start reserve, not inside it.
Call an engineer when

When solar is a large share of load, the battery is the only reserve after a generator trip, or one-second solar data are missing.

Rough guide: Method is standard; the solar ramp fraction is author judgment.
Go deeper
MG-030 · MG-031 · ROT-MG-18 · ROT-GEN-07 · CTRL-036 · ROT-CTRL-18
M-07How a microgrid behaves · NumberFor engineering · everyoneTypical

How do generators and batteries share the load without talking to each other?

Quick answer
3–5%generator droop
frequency sag from no load to full load
In plain words

Each source follows one agreed rule: the more the frequency sags, the harder it pushes. They share a new load in proportion to how stiffly each is set, with no messages needed. It is like two people carrying a couch: whoever grips tighter takes more weight, and a slower controller later nudges the frequency back to 60 hertz.

Quick math

Frequency drop = load step ÷ sum of stiffness; stiffness = rating ÷ (droop × 60 Hz); each source's share = its stiffness ÷ total

  1. Generator 2,000 kW at 4%: 2,000 ÷ (0.04 × 60) ≈ 833 kW per Hz
  2. Battery 1,000 kW at 2%: 1,000 ÷ (0.02 × 60) ≈ 833 kW per Hz
  3. 900 kW load step: 900 ÷ 1,667 ≈ 0.54 Hz, so 60.00 → 59.46 Hz
  4. Equal stiffness, so each picks up 450 kW
Frequency settles about 0.54 Hz low and each source takes 450 kW until the slower control restores 60 Hz
What moves this number
← lessmore →
Softer battery settingbattery droop 2% → 4%
about 33% deeper sag (0.72 Hz); battery takes 300 kW
Battery holds frequency fixedbattery droop 2% → 0%
no sag; battery takes all 900 kW
Battery hits its limit2,400 kW step
1.68 Hz instead of 1.44 Hz, near load-shedding settings
−100%0+100%
Watch out
  • This is the settled value; the first seconds dip deeper, and the battery carries most of a sudden step at first.
  • Battery droop of 1–3% is common; choose it so the full swing stays 0.3–0.5 Hz inside the trip settings.
  • Only one source can hold frequency exactly fixed unless sources share a load-sharing link.
Call an engineer when

When frequency could approach load-shedding or trip settings, sources differ greatly in speed, or the battery may hit its limit.

Typical: Sharing arithmetic is exact; settings are vendor practice.
Go deeper
CTRL-011 · CTRL-012 · CTRL-008 · CTRL-010 · CTRL-014 · ROT-CTRL-05 · ROT-CTRL-06 · ROT-CTRL-07 · ROT-CTRL-08
M-08How a microgrid behaves · ChecklistFor engineering · salesTypical

What happens if the controller or communications fail?

Quick answer
Local fallback
if each device has a tested fallback setting
In plain words

A well-designed microgrid can keep running when the central controller or its network goes quiet, because every battery, inverter, generator and relay has its own fallback setting. What stops is the clever part, such as scheduling and bringing loads back, like an orchestra that keeps playing when the conductor leaves but cannot start a new piece.

Checklist

While islanded, each device on its own

While grid-connected

Timing to ask about

Proof at handover

Watch out
  • A failed controller cannot command its own fallback; each device has to carry its own.
  • Firmware updates have reset fallback timers; recheck them after every update.
  • Cellular and wide-area links need longer timeouts and more local independence than a site network.
Call an engineer when

When an export limit or safety function relies on communications, links are cellular, or a controller failure could leave a hazard.

Typical: Common vendor defaults and integration practice; confirm firmware supports each fallback.
Go deeper
CTRL-006 · ROT-CTRL-04 · ROT-CTRL-03 · ROT-CTRL-13 · CTRL-005 · CTRL-026
M-09How a microgrid behaves · ChecklistFor sales · engineering · everyoneRough guide

In what order do loads come back after a blackout?

Quick answer
Safety firstthen motors, then the rest
one block at a time, within source limits
In plain words

Loads come back in blocks, most important first, each block waiting until the voltage and frequency settle, because switching everything on at once would trip the source. Heating and cooling come last on purpose. After an hour or more off, they all restart together and can draw about twice their usual power, like a whole crowd reaching the same door at once.

Checklist

Before any load

Then, in this order

What it looks like in one worked example

Watch out
  • Each failed attempt adds a wait and a repeat; state restore times with and without one retry.
  • Code emergency loads have their own restore time limits on code-compliant sources, as adopted locally.
  • No automatic retry after a trip that points to a fault; that is a safety decision for the owner.
Call an engineer when

When large motors or transformers restart from an inverter, restore times are contractual, or automatic retries are wanted.

Rough guide: Order is common practice; step times and multiplier are author judgment.
Go deeper
MG-024 · MG-021 · MG-022 · MG-023 · ROT-MG-15 · ROT-MG-12 · ROT-MG-13 · ROT-MG-14 · ROT-CTRL-19 · CTRL-038
P-01Protection and safety · Don’t guessFor sales · engineering · everyoneTypical
Don’t guess: this card gives no design number

Can we reuse the grid protection settings when the site is islanded?

Quick answer
No: study it
settings need checking for every operating mode
In plain words

Usually not. Inverters protect their own electronics by holding current close to their own rating, so an island short circuit can look like ordinary load to breakers set for the grid. It is like a smoke alarm tuned for a bonfire that never notices a match.

The idea

On the grid, a short circuit pulls a huge current from the utility, and breakers and relays are set to see it. On an island fed by inverters, the controls clamp current within a fraction of a second. Fault current can then fall to a small fraction of the grid value, and the old settings may trip slowly, in the wrong place, or not at all.

Island fault current is set by each inverter's controls and firmware, not by the wiring, so only vendor data and a mode-by-mode study can give it.

What to ask for
  • A mode-by-mode fault study: grid-connected, battery only, generator only, mixed, and each with one source out
  • Each inverter maker's fault current versus time data at the installed firmware, for every fault type
  • Validated vendor electromagnetic transient (EMT) models wherever protection depends on inverter fault current, as on any inverter-dominated island
  • Relay setting groups for each mode, the logic that selects them, and a safe fallback group
  • A witnessed test of setting-group switching at commissioning
Watch out
  • Some inverters stop putting out current during a fault, so a source can vanish mid-fault.
  • Breaker interrupting ratings still have to be checked at the larger grid-connected fault current.
  • Inverter trip and momentary-cessation settings can make sources quit before protection clears; check timing both ways.
Call an engineer when

Always, before any site runs islanded: protection settings need a licensed engineer's mode-by-mode study and witnessed tests.

Typical: The concept is well established; actual current depends on each product.
Go deeper
PROT-015 · PROT-016 · PROT-017 · PROT-021 · PROT-022 · ROT-PROT-06 · ROT-PROT-07 · ROT-PROT-11
P-02Protection and safety · Don’t guessFor sales · engineeringTypical
Don’t guess: this card gives no design number

Why does everyone keep asking about fault current, and where does it come from?

Quick answer
Needs a study
both the largest and smallest values matter
In plain words

Fault current is the rush of current into a short circuit; breakers have to be strong enough to stop the biggest rush and sensitive enough to notice the smallest one. It is like a dam spillway that has to survive the flood of the century and still open for a light rain.

The idea

The utility supplies most of it on the grid, and generators add a large first burst that falls over the first second, held near three times rating only if the excitation supports it. Running motors briefly feed current back, and battery racks push a fast, large direct current into faults on their own side. Inverters hold their output near rated current, so every new source or operating mode changes both the largest and the smallest fault current at each panel.

Fault current depends on the utility's own system, every transformer, cable and machine, and each inverter's controls, so only a modeled study gives it.

What to ask for
  • A software short-circuit study by or under a licensed engineer covering every operating state, including transfers
  • The utility's fault levels in writing: maximum, minimum and future
  • Generator data sheets, the motor list, and each inverter maker's fault current versus time data
  • Tested short-circuit current from the battery rack maker for the direct current side
  • A table comparing every breaker and panel rating with the largest available fault current
Watch out
  • Hand calculations are screening only; any inverter source on site is a reason for a software study.
  • Adding a generator or battery can push old switchgear past its interrupting rating even when nothing else changes.
  • Battery direct current faults rise very fast and need devices rated for direct current, not just alternating current.
Call an engineer when

Whenever a source is added, switchgear is reused, or the site will run islanded: equipment ratings and settings need a short-circuit study.

Typical: Standard short-circuit practice; values depend entirely on site data.
Go deeper
PROT-002 · PROT-009 · PROT-011 · PROT-012 · PROT-014 · PROT-015 · ROT-PROT-02 · ROT-PROT-03 · ROT-PROT-05 · ROT-ESS-24
P-03Protection and safety · Don’t guessFor engineering · everyoneTypical
Don’t guess: this card gives no design number

What happens to grounding when the grid is gone, and does the transfer switch need to switch the neutral?

Quick answer
Design it
ground reference for each system and operating mode
In plain words

On the grid the building's electrical system is tied to earth at one spot at the utility service; when the site islands, the battery or generator running it has to provide that tie, and a three-pole or four-pole transfer switch decides where it is. Think of a tent with one center pole: take it away without putting another up and the whole thing sags.

The idea

Each separately derived system needs exactly one neutral-to-ground bond, and that bond has to follow the source through every transfer; sources paralleled on a common neutral share one. With no bond the island floats and healthy wires can rise far above their normal voltage to ground; with two bonds and a three-pole switch, neutral current spills onto the ground wires and can trip ground-fault protection falsely.

The right arrangement depends on whether each source is a separately derived system, how the neutral is shared, the transfer scheme and ground-fault protection, so it is a design choice, not a rule of thumb.

What to ask for
  • A grounding design for every operating mode (utility-connected, islanded, transfer), including transitions
  • A written three-pole or four-pole decision for every transfer and interconnect switch, showing where each bond sits
  • Ground-fault protection settings checked in every mode
  • The direct current grounding scheme and insulation monitoring settings from the battery and inverter makers
  • Grounding drawings in the permit set, reviewed by a licensed engineer
Watch out
  • A bonded generator or battery behind a three-pole switch is a common, hard-to-find wiring error.
  • Closed-transition and parallel-running microgrids need a case-by-case neutral design, not the standard answer.
  • Floating battery racks do not trip on a first ground fault; only the insulation alarm warns, so treat it as urgent.
Call an engineer when

On every project with a generator or battery that backs up a four-wire service, or any site that runs islanded or in parallel.

Typical: Neutral switching is settled practice; grounding details and alarm limits vary by product.
Go deeper
PROT-025 · PROT-028 · PROT-030 · ROT-PROT-12 · ROT-PROT-15 · ROT-ESS-25
P-04Protection and safety · Don’t guessFor sales · engineering · everyoneTypical
Don’t guess: this card gives no design number

What is arc flash, and why can an island be more dangerous than the grid?

Quick answer
Study by mode
incident energy changes with each operating mode
In plain words

An arc flash is a blast of heat and light when current jumps through air inside equipment. The burn it can cause depends on how much current flows, how long, and how close the worker stands. An island has less fault current, so breakers may trip slower and the blast can last longer, like a smaller fire that burns for much longer.

The idea

Incident energy, the heat that reaches a worker, grows with arcing time and falls with distance. On an island, lower current can move a fault out of a breaker's instant-trip range into its time-delay range, so the energy can rise even though current fell; no validated method yet exists for faults fed only by inverters.

Incident energy comes from the full study model for each location and mode; simple shortcuts can understate it badly.

What to ask for
  • An arc-flash study to IEEE (Institute of Electrical and Electronics Engineers) standard 1584-2018 for every operating mode, at full and reduced arcing current
  • Equipment labels from the worst mode, or by mode with clear instructions
  • A stated method for buses fed only by inverters, based on each maker's fault current versus time data
  • Arc-energy reduction measures wherever any mode exceeds the owner's target
  • A restudy whenever settings, sources or operating modes change
Watch out
  • Labels from a grid-only study can understate the hazard when the site runs islanded.
  • Less fault current does not mean safer: slower clearing can raise the energy.
  • Battery direct current equipment needs its own hazard evaluation; the alternating current model does not cover it.
Call an engineer when

Always before energized work on a multi-mode site: labels and protective equipment need a licensed engineer's arc-flash study for every mode.

Typical: Mechanism well established; inverter-fed arc flash lacks a validated method.
Go deeper
PROT-040 · PROT-041 · PROT-042 · PROT-044 · ROT-PROT-21
P-05Protection and safety · Don’t guessFor sales · engineering · everyoneTypical
Don’t guess: this card gives no design number

The vendor says the battery is UL certified. What does that actually prove?

Quick answer
Ask for proof
listing certificate plus full fire test reports
In plain words

A safety listing to UL 9540 means a nationally recognized laboratory, such as UL Solutions, tested that exact system and keeps checking the factory. A UL 9540A report is fire test data, not a listing; the 6th edition adds pass/fail criteria to its large-scale installation-level test. Treat it like a car's crash rating: it covers that model as built, not a different engine or a modified body.

The idea

Battery safety evidence comes in layers: cell, module and inverter certificates; a listing of the complete system to UL 9540; fire test data from UL 9540A at cell, module and unit level and, in the 6th edition, large-scale installation-level testing; and the installation code that uses both. Each piece covers only the configuration, edition and charge level tested.

A listing is yes-or-no and a fire test report is data, each for one specific configuration; no rule of thumb can stand in for reading them.

What to ask for
  • The UL 9540 certificate and directory entry matching the model and revision offered
  • Full UL 9540A reports for every level run, with the edition and the data, not a summary
  • A signed statement that cells, modules, enclosure, spacing and firmware match what was listed and tested
  • UL 1973 module and UL 1741 inverter certificates, plus cell gas data
  • A laboratory gap memo when the report's edition differs from the one the local code names
Watch out
  • "Designed to meet UL 9540" or "UL 9540 pending" carries no certification weight.
  • "Passed UL 9540A" is incomplete: name the edition, the test level and the criteria; the listing itself is UL 9540.
  • A change of cell, enclosure, spacing or firmware can void coverage until the certifier confirms in writing.
Call an engineer when

When the offered product differs from the listed one, the report edition differs from the code, or no listing exists.

Typical: Widespread reviewer practice; certifiers decide each change case by case.
Go deeper
STD-005 · STD-008 · ROT-STD-05 · ROT-STD-06 · ROT-STD-08
P-06Protection and safety · Don’t guessFor sales · engineering · everyoneTypical
Don’t guess: this card gives no design number

What does the fire code actually care about for a battery?

Quick answer
Gas and spread
how much energy, how close, and what happens next
In plain words

The fire code, as adopted locally, asks how much battery energy sits in one place and how far it is from people and buildings. It also asks what happens if a cell fails and vents flammable gas. A failing lithium battery often gives off gas before any flame, so the danger can be a gas explosion inside the box rather than a fire.

The idea

Fire codes for storage cover energy limits per space, separation, explosion control, detection and suppression, a hazard mitigation analysis where triggered, an emergency response plan, commissioning and decommissioning. The main ones are NFPA 855 (from the National Fire Protection Association) and the International Fire Code, as adopted locally. A 2019 battery explosion in Arizona injured firefighters when built-up gas ignited inside the enclosure.

Limits and spacing differ by code edition, occupancy and test data, and only the local fire official decides what applies.

What to ask for
  • The fire code edition the authority having jurisdiction actually enforces, confirmed at kickoff
  • A hazard mitigation analysis by a fire protection engineer where the code or official calls for one
  • An explosion control design based on the cell maker's gas data
  • Detection and suppression design documents tied to the fire test results
  • An emergency response plan agreed with the local fire department
Watch out
  • Many places still enforce older editions; the 2024 International Fire Code predates NFPA 855-2026, so confirm the adopted edition.
  • Clean agent puts out flame but does not cool cells and can let gas build up.
  • Spacing and clearances drive layout; see Site and space before promising a location.
Call an engineer when

Before promising any indoor location, small parcel, or site near occupied buildings: bring in a fire protection engineer and the fire official.

Typical: Code topics are stable; values change by edition and local adoption.
Go deeper
ESS-050 · ESS-051 · STD-006 · STD-007 · ROT-ESS-29
P-07Protection and safety · Don’t guessFor sales · engineering · everyoneTypical
Don’t guess: this card gives no design number

Who has to sign off before the system is safe to run?

Quick answer
More than one
utility, code officials and licensed engineers each sign
In plain words

No single approval covers everything. The utility approves running in parallel with the grid, local code officials approve the wiring, building and fire safety, and licensed engineers stand behind the studies. It is like buying a house: the inspector, the lender and the insurer each sign a different paper.

The idea

The utility approves interconnection and protection at the connection point and issues permission to operate; the electrical and building officials and the fire code official approve the installation. Qualified engineers, licensed where the state, utility or owner requires, own the fault, coordination, arc-flash and grounding studies, a fire protection engineer owns the hazard mitigation analysis, and a structural engineer owns pads and anchorage.

Who signs depends on the state, the utility and the local codes, so each project needs its own responsibility list.

What to ask for
  • A responsibility list naming who prepares, reviews and approves each study and safety document
  • The engineer of record for protection, grounding and arc flash, and their license state
  • The utility's written protection requirements at the connection point
  • A pre-application meeting with the building, electrical and fire officials
  • A witnessed commissioning test plan for protection and setting-group switching
Watch out
  • A utility permission-to-operate letter does not close the electrical permit, and a final inspection does not allow grid connection.
  • A vendor compliance letter is not a sign-off; listings and stamped studies are.
  • Permits, approvals and timelines are covered in Process, codes and schedule.
Call an engineer when

At project start: name the engineer of record and fire protection engineer before any safety claim reaches the customer.

Typical: Typical U.S. jurisdiction split; confirm on each project.
Go deeper
STD-007 · STD-008 · ROT-STD-07 · ROT-PROT-05
Y-01Site and space · NumberFor sales · engineeringRough guide

How much room does a battery need per megawatt-hour?

Quick answer
250–600 ft²per MWh, fenced yard
containerized lithium iron phosphate, 2–4 hour systems
In plain words

The battery boxes themselves are small; the space between them, around them and for trucks to reach them is most of the yard. It is like a parking lot: the cars take a fraction of the area and the aisles and driveways take the rest.

Quick math

Yard area ≈ site factor × number of units × (length + end clearance) × (width + side clearance), then ÷ installed MWh

  1. 22,000 kWh needed ÷ 5,016 kWh per 20 ft container = 5 containers (25.08 MWh installed)
  2. Each container with 6 ft end and 10 ft side clearance: about 466 ft²; each of 3 inverter-transformer skids: 468 ft²
  3. Equipment area 5 × 466 + 3 × 468 ≈ 3,733 ft²; × site factor 2.0 for roads, fence and drainage ≈ 7,465 ft²
  4. 7,465 ft² ÷ 25.08 MWh ≈ 298 ft² per MWh
About 300 ft² per MWh fenced (about 0.17 acre), nearly ten times the container footprint alone
What moves this number
← lessmore →
Lower-density containers5,016 → 3,700 kWh each
about 27% more area per MWh
More room for roads and drainagesite factor 2.0 → 2.5
about 25% more area
Tighter side clearance accepted10 ft → 5 ft
about 28% less area
−30%0+30%
Watch out
  • The whole parcel with setbacks, stormwater and a substation runs about 900–2,000 ft² per MWh, roughly 20–50 MWh per acre.
  • Example clearances are not code distances; separations, sound walls or flood berms can double area, and small systems are dominated by fixed clearances.
  • Leave crane and truck turning space and room for future added battery in the first layout.
Call an engineer when

When the parcel is tight, near occupied buildings or lot lines, in a flood zone, or the layout sets the land purchase.

Rough guide: Author judgment from 2022–2025 layouts; arithmetic is exact.
Go deeper
SYS-005 · ROT-SYS-05 · ESS-051
Y-02Site and space · NumberFor sales · engineeringTypical

How heavy is a battery container, and can my roof, slab or soil carry it?

Quick answer
250–600 psfpounds per square foot
over the enclosure footprint, installed, lithium containers and cabinets
In plain words

A 20 ft battery container weighs about 30,000–42,000 kg and sits on about 160 square feet, so it presses down far harder than most floors expect. Ordinary roofs are built for snow and people, so most containers end up on new pads or piers on the ground.

Quick math

Average load = weight ÷ footprint; load per support = unequal-support factor × weight ÷ supports; soil pressure = load per support ÷ footing area + footing weight

  1. Container 40,000 kg = 88,185 lb on a 159 ft² footprint: 88,185 ÷ 159 ≈ 555 psf
  2. Six pier footings with a 1.25 unequal-support factor: 1.25 × 88,185 ÷ 6 ≈ 18,370 lb each
  3. Footing 3.5 × 3.5 ft, 2 ft deep: 18,370 ÷ 12.25 + 150 × 2 ≈ 1,800 psf on the soil
About 555 psf on the footprint and about 1,800 psf under each footing
What moves this number
← lessmore →
More supports6 → 8 pier footings
about 21% less soil pressure
Bigger footings3.5 × 3.5 ft → 4 × 4 ft
about 20% less soil pressure
Uneven supportfactor 1.25 → 1.5
about 17% more soil pressure
−25%0+25%
Watch out
  • Roofs are designed for live loads in the tens of psf; a container usually needs new structure.
  • 1,800 psf can exceed presumptive values for clay but not sand or gravel, as adopted locally; a soils report decides.
  • Wind, seismic and anchorage often govern more than weight; walk-in 40 ft enclosures run lighter, about 175–250 psf.
Call an engineer when

Any roof, mezzanine or existing-slab location, and every ground pad: structural engineer plus a geotechnical report.

Typical: Arithmetic of published masses and footprints; range is judgment.
Go deeper
SYS-006 · ROT-SYS-06 · SYS-040
Y-03Site and space · Don’t guessFor sales · engineering · everyoneTypical
Don’t guess: this card gives no design number

How much clearance and access does the battery need around it?

Quick answer
Ask locally
set by the adopted fire code and the maker
In plain words

Space between battery units, and from buildings, property lines and walkways, comes from the fire code as adopted locally, the maker's installation manual and fire test data. Firefighters, cranes and service trucks also need a way in, the way a house needs a driveway as well as a footprint.

The idea

Spacing slows fire spread between units and protects neighbors, so the code sets defaults that the local fire official may relax on accepted test data. Access adds fire department routes, water supply, crane pads, truck turning and room for future added battery, which together often take more space than the spacing itself.

Clearances change with the code edition adopted, indoor or outdoor siting, occupancy and the product's fire test data, so any figure here could be wrong for the site.

What to ask for
  • The fire code edition enforced locally, confirmed with the fire official at a pre-application meeting
  • The maker's installation manual clearances, checked against the spacing in its UL 9540A fire test (UL is a nationally recognized testing laboratory)
  • A site plan showing separations, fire access, water supply, setbacks and crane paths
  • A hazard mitigation analysis where the official calls for one, or where reduced spacing is sought
  • Zoning setback and screening rules for the parcel
Watch out
  • Inadequate separation from buildings or lot lines has ended real projects on small parcels.
  • An installation manual that allows tighter spacing than the unit was tested at may not satisfy reviewers.
  • Clearances, crane paths and access belong in the concept layout, not after the product is chosen.
Call an engineer when

Before showing a customer a layout near buildings, lot lines or public ways: fire protection engineer and fire official review.

Typical: Principle is stable; distances depend on edition and local adoption.
Go deeper
ESS-051 · STD-006 · STD-007 · SYS-005 · ROT-SYS-05
Y-04Site and space · NumberFor sales · engineeringTypical

How loud will it be at the property line?

Quick answer
−6 dBper doubling of distance
one source, open ground, A-weighted decibels
In plain words

Sound in A-weighted decibels (dBA, the scale that matches human hearing) drops about 6 decibels each time you double the distance. Doubling the number of identical units raises it about 3 decibels. Battery cooling fans and generators usually set the level, and night limits are the ones that bite.

Quick math

Level at distance = level at reference − 20 × log10(distance ÷ reference); n equal units add 10 × log10(n)

  1. Four enclosures, each 70 dBA at 10 ft with cooling running: 70 + 10 × log10(4) ≈ 76.0 dBA at 10 ft
  2. At the property line 200 ft away: 76.0 − 20 × log10(20) ≈ 50.0 dBA, 5 dB over an example 45 dBA night limit
  3. Distance to meet 45 dBA: 10 × 10^((76.0 − 45) ÷ 20) ≈ 356 ft
About 50 dBA at 200 ft; move to about 356 ft or find 5 dB of reduction
What moves this number
← lessmore →
Twice as many enclosures4 → 8 units
about 41% more distance needed
Stricter night limit45 → 40 dBA
about 78% more distance needed
Quiet cooling mode or barrier5 dB less at the source
about 44% less distance needed
−80%0+80%
Watch out
  • Use the maker's sound power or a reference distance at least twice the enclosure length, in the loudest night state.
  • Transformer hum and other tones can draw ordinance penalties that this arithmetic ignores.
  • Ground, barriers and buildings change real results; a detailed prediction or ambient measurement may be required.
Call an engineer when

When the screen lands near or over the limit, homes are near, or the ordinance penalizes tones or low hum.

Typical: Physics is exact; field prediction is medium confidence.
Go deeper
SYS-039 · ROT-SYS-24
Y-05Site and space · ChecklistFor sales · engineering · everyoneTypical

What site problems should I check first, before anyone sizes anything?

Quick answer
Screen first
a fatal flaw ends the project; sizing can wait
In plain words

A few site problems kill projects no matter how well the system is sized, so check them before spending on design. It is like checking that a house has a road to it before choosing the paint.

Checklist

Utility and money

Ground and space

Neighbors and permits

Watch out
  • Any "no" should be investigated before sizing continues, not after.
  • Medium-voltage transformers, switchgear and the interconnection agreement, not the battery, usually set the schedule.
  • Interconnection rules and permits are covered in Process, codes and schedule.
Call an engineer when

When any screen comes back uncertain, or the owner needs the system within about 18 months of concept.

Typical: Author practice; the 18-month figure is low confidence.
Go deeper
SYS-007 · SYS-005 · SYS-006 · SYS-039 · ROT-SYS-07
Y-06Site and space · NumberFor engineering · salesTypical

Besides the batteries, what does the yard need: pad, cable runs and its own power feed?

Quick answer
2–4 kWper MWh, plus 1–2 kW per site
hot-day peak, liquid-cooled lithium, 4-hour; 2-hour runs higher
In plain words

Every battery container runs its own cooling and controls, so the yard needs a small power feed of its own, besides pads, cable runs and crane access. Size that feed for the hottest afternoon, the way a house panel is sized for the air conditioner, not the average day.

Quick math

Auxiliary feed ≈ kW per MWh × battery nameplate MWh + site controls + heaters and lighting

  1. Battery cooling and management: 2.7 kW per MWh × 3.48 MWh ≈ 9.40 kW
  2. Controls, relays, network and backup power: 1.0 kW; switchgear heaters and lighting: 0.8 kW
  3. Total: 9.40 + 1.0 + 0.8 ≈ 11.2 kW
About 11.2 kW of hot-day auxiliary feed for a 3.48 MWh battery
What moves this number
← lessmore →
Hotter site2.7 → 4 kW per MWh
about 40% bigger feed
Milder site2.7 → 2 kW per MWh
about 22% smaller feed
Twice the battery3.48 → 6.96 MWh
about 84% bigger feed
−85%0+85%
Watch out
  • Annual average draw is only about 0.8–1.5 kW per MWh; size the feed for peak, the energy budget for average. See Batteries.
  • Air-cooled walk-in enclosures, desert or arctic sites and long-duration chemistries differ; replace with the maker's budget early.
  • Pads carry concentrated loads at supports, and crane, truck and cable routes belong in the first layout.
Call an engineer when

When the auxiliary feed has to stay on during an outage, the site is very hot or cold, or the maker's budget differs.

Typical: Consistent with maker data classes; range is judgment.
Go deeper
SYS-002 · ROT-SYS-02 · ESS-049 · ROT-ESS-28
C-01Cost and value · NumberFor sales · engineering · everyoneTypical

What does an installed battery system cost, and what drives the price?

Quick answer
$450–1,000per usable kWh
commercial lithium-ion, 2–4 h, installed, 2022–2023 dollars (historical)
In plain words

A commercial battery system installed to the utility connection ran about $450–1,000 per usable kilowatt-hour in 2022–2023 dollars, and the battery modules are only about 30–45% of that; the rest is power electronics, wiring, concrete, labor, engineering, permits and the utility hookup. Like a kitchen remodel, the appliances are not the job: the installation and the surprises behind the wall are.

Quick math

Cost per kWh = total installed cost ÷ kWh on a stated basis (nameplate or usable); cost per kW = total ÷ inverter kW

  1. Synthetic 1,000 kW / 4,000 kWh nameplate system: battery $1.0M + inverter and transformer $0.18M + wiring and civil $0.32M + labor $0.40M + soft costs $0.20M + utility hookup $0.25M + controls $0.10M = $2.45M
  2. Per nameplate kWh: 2,450,000 ÷ 4,000 ≈ $613
  3. Per usable kWh (90% window, 3,600 kWh): 2,450,000 ÷ 3,600 ≈ $681
  4. Per kW: 2,450,000 ÷ 1,000 = $2,450; battery modules are 41% of the total
About $613 per nameplate kWh, $681 per usable kWh, $2,450 per kW (synthetic example, one dollar year)
What moves this number
← lessmore →
Same quote, other energy basisnameplate → usable kWh
about 11% higher per kWh, same project
Bigger project4,000 → 10,000 kWh, assumed scaling exponent 0.85
about 13% less per kWh than straight-line scaling (about 5–20% across exponents 0.75–0.95)
Early-stage estimateadd 20% feasibility contingency
about 20% higher budget; carry 20–30% at feasibility
−20%0+20%
Watch out
  • 2024–2025 utility contracts near $200–400/kWh (nominal) state no clear basis; never mix them with these benchmark ranges.
  • This range is history, in 2022–2023 dollars: lithium-ion prices moved over 30% within single years in 2022–2025, so use dated current quotes.
  • The utility hookup can add 0–30% and is the widest single unknown; carry it separately until the utility study is done.
Call an engineer when

Before quoting a budget: get vendor quotes on a written energy basis, and a utility study when the feeder is constrained.

Typical: Historical 2022–2023 benchmark with stated basis; only current quotes support a budget.
Go deeper
ECON-001 · ECON-003 · ECON-010 · ROT-ECON-03 · ROT-ECON-04 · ROT-ECON-09 · ROT-ECON-02
C-02Cost and value · NumberFor sales · engineeringTypical

Why does a longer-duration battery cost less per kWh but more per kW?

Quick answer
12–23% lowercost per kWh
2 h to 4 h; cost per kW rises 55–75%
In plain words

Part of the price follows energy (battery modules) and part follows power (inverters, transformers, switchgear). Adding hours spreads the power part over more kilowatt-hours but adds module cost to every kilowatt. Like a bigger fuel tank on the same truck: cheaper per gallon of tank, dearer per truck.

Quick math

Cost per kWh = energy part + power part ÷ hours; cost per kW = energy part × hours + power part

  1. Synthetic parts: energy $300 per nameplate kWh, power $400 per kW
  2. 2 h: 300 + 400 ÷ 2 = $500/kWh; 300 × 2 + 400 = $1,000/kW
  3. 4 h: 300 + 400 ÷ 4 = $400/kWh; 300 × 4 + 400 = $1,600/kW
  4. Change: 20% less per kWh, 60% more per kW
4 hours costs about 20% less per kWh and 60% more per kW than 2 hours (synthetic example)
What moves this number
← lessmore →
Go on to 8 hours4 → 8 h
about 12.5% less per kWh
Go on to 8 hours4 → 8 h
about 75% more per kW
Cheaper battery modulesenergy part $300 → $200/kWh
about 25% less per kWh at 4 h
−75%0+75%
Watch out
  • Real prices step in whole containers and inverter blocks; the smooth curve is a screening shape that breaks above 8 hours.
  • Site costs like the utility study and controls follow neither kW nor kWh; on small systems carry them as a separate lump.
  • A "4-hour" system on nameplate is about 3.6 hours on usable energy at a 90% window; compare on one basis.
Call an engineer when

When the utility hookup dominates cost, duration goes beyond about 8 hours, or quotes come in different block sizes.

Typical: Follows benchmark cost structure; the band is author judgment.
Go deeper
ECON-002 · ROT-ECON-01 · ECON-001
C-03Cost and value · NumberFor sales · engineering · everyoneTypical

What does a battery system cost to run each year?

Quick answer
1.5–3.5%of installed cost a year
all-in, lithium-ion, daily cycling, temperate climate
In plain words

Plan about 1.5–3.5% of the installed price every year for service, insurance, warranty, software, communications and the electricity the battery's own cooling and controls use. Like owning a car, the purchase is not the whole cost: insurance and upkeep arrive every year.

Quick math

Yearly cost = fixed service + per-MWh service + insurance + warranty + software + communications + auxiliary energy (average kW × 8,760 h × price)

  1. Fixed $15,000 + per-MWh $1,000 ($1 per MWh × about 1,000 MWh a year) + insurance $12,250 + warranty $10,000 + software $8,000 + communications $3,000 = $49,250
  2. Auxiliary energy: 8 kW × 8,760 h × $0.12/kWh ≈ $8,410
  3. Total ≈ $57,660 a year on a $2,450,000 system = 2.35%
About $57,700 a year, 2.35% of installed cost, $57.7 per kW-year (synthetic example, year one)
What moves this number
← lessmore →
Auxiliary energy left outdrop the $8,410 line
budget about 15% too low
Hot or cold climateauxiliary load 8 → 12 kW
about 7% higher yearly cost
Insurance market0.5% → 1.0% of installed cost
about 21% higher yearly cost
−25%0+25%
Watch out
  • Augmentation is extra (see C-11), unless the service price already includes it; a benchmark 2.5% figure may.
  • Service scope alone runs about $8–25 per kW-year (2022–2023 dollars); the all-in percentage adds insurance, warranty, software and energy.
  • Check service-contract exclusions: refrigerant, fire-suppression recharge, software and cyber patching.
Call an engineer when

When the site is hot or cold, the battery cycles less than daily, or the service contract scope is unclear.

Typical: Brackets the benchmark 2.5% assumption; added items are judgment.
Go deeper
ECON-004 · ROT-ECON-05 · ROT-ECON-06 · ECON-011 · ROT-ESS-28
C-04Cost and value · NumberFor sales · engineering · everyoneRough guide

What do demand-charge savings look like, and when are they worth chasing?

Quick answer
$15/kW-monthor more
demand rate where a detailed study usually pays
In plain words

A demand charge bills the month's single highest short interval, so a battery that trims that peak can save the kilowatts cut times the rate in each month it succeeds. For 2–4 hour lithium-ion at mid-2020s installed costs, rates of about $15 per kilowatt per month or more usually justify a detailed study. Below about $10, demand savings alone rarely pay.

Quick math

Yearly savings ≈ billed kW cut × demand rate × 12 months × realized share (0.70–0.90)

  1. 250 kW cut × $18/kW-month = $4,500 a month
  2. × 12 months = $54,000 a year, gross, with perfect foresight
  3. × 0.70–0.90 realized = about $37,800–48,600 a year
About $38,000–49,000 a year before charging energy, wear and financing (synthetic tariff)
What moves this number
← lessmore →
Lower demand rate$18 → $12 per kW-month
about 33% less saving
Weather-driven peaksrealize 70% of the simulation
30% below the perfect-foresight figure
One missed peak, 80% ratchet250 kW miss in the peak-setting month
up to about 82% of a year's gross saving lost
−85%0+85%
Watch out
  • Only a cut in the billed demand counts; if a later unshaved interval sets the month's peak, the shave earns nothing.
  • Hourly data understate the 15-minute billed peak by about 3–10%; get 15-minute interval data.
  • Night recharging can set a new facility peak; model charging in the same simulation as the shaving.
Call an engineer when

When the tariff has a ratchet, several demand charges, standby charges, or peaks that are weather-driven or erratic.

Rough guide: Savings arithmetic is exact; thresholds and realized share are judgment.
Go deeper
ECON-012 · ECON-014 · ECON-016 · ROT-ECON-10 · ROT-ECON-11 · ROT-ECON-12 · ROT-ECON-13
C-05Cost and value · NumberFor sales · engineeringTypical

What is time-of-use shifting worth?

Quick answer
$0.04–0.07per kWh
minimum peak-to-off-peak price gap before shifting pays
In plain words

Time-of-use shifting means charging when energy is cheap and using it when it is expensive. Some energy is lost in the round trip, and each cycle wears the battery a little. Like buying in bulk to resell, the markup has to beat the spoilage and handling, and gaps under about 4–7 cents per kilowatt-hour rarely do.

Quick math

Net value per kWh delivered = peak price − off-peak price ÷ round-trip efficiency − wear cost per kWh

  1. Charge cost per kWh delivered: $0.10 ÷ 0.87 ≈ $0.115
  2. Gross gap: $0.22 − $0.115 ≈ $0.105
  3. Less $0.03 wear: about $0.075 per kWh, $75 per 1,000 kWh cycle
  4. Year: 87 summer weekdays × $75.06 + 174 winter weekdays × $26.55 (winter $0.16 peak, $0.09 off-peak, same losses and wear) ≈ $11,150
About $11,150 a year, roughly a fifth of the $54,000 demand saving for a similar battery (synthetic tariff)
What moves this number
← lessmore →
Lower real efficiency0.87 → 0.80 round trip
about 13% less per cycle
Higher wear cost$0.03 → $0.05 per kWh
about 27% less per cycle
Winter prices$0.16 peak / $0.09 off-peak
about 65% less per cycle than summer
−65%0+65%
Watch out
  • The threshold assumes off-peak near $0.10/kWh, 85% efficiency and wear of $0.02–0.05/kWh; recompute for the actual tariff.
  • Use efficiency metered at the grid side both ways, including the battery's own cooling; datasheet efficiency overstates the value.
  • Charging that sets a new demand peak erases the gain, and tariffs change; run rate-change scenarios first.
Call an engineer when

When prices are hourly or dynamic, shifting adds cycles beyond the warranty allowance, or solar charging changes the energy cost.

Typical: Arithmetic is exact; the wear-cost range is author judgment.
Go deeper
ECON-017 · ECON-018 · ROT-ECON-14 · ECON-041
C-06Cost and value · CompareFor sales · everyoneTypical

Payback, NPV and IRR: what do they each tell me?

Quick answer
NPV decides
payback screens cash risk; it is not a value test
In plain words

Payback counts the years until the cash comes back; net present value (NPV) says how much wealth the project adds after charging for the wait at the owner's discount rate; internal rate of return (IRR) is the yearly return at which that added wealth is zero. Payback is how soon you get your stake back; NPV is how much richer you end up if the forecast holds.

Side by side
Simple paybackNet present value (NPV)Internal rate of return (IRR)
Question it answersHow many years to get the cash back?How much wealth does it add at my discount rate?What yearly return does it earn?
Counts the time value of moneyNoYesYes
Synthetic $1.6M battery, 15 years, 7% real7.6 years level; 8.3 with the year-8 augmentationabout +$225,000about 9.2%; modified IRR (MIRR) 7.9% with cash reinvested at 7%
Main trapIgnores everything after payback, including end-of-life costsOne rate for all risks; grows with project sizeCan mis-rank options or give several answers; MIRR fixes the reinvestment rate
How owners use itMany commercial owners want about 3–5 years; beyond 7–8 usually needs helpThe test for choosing between optionsCompared with the owner's hurdle rate
Watch out
  • At 7% the same project takes about 12.2 years to pay back in today's dollars; most of its value arrives late.
  • Tax credits and grants lower net cost in the year received; rates and eligibility change by statute, so confirm current law.
  • Use real dollars with a real rate, or nominal with nominal, never mixed; say which on every result.
Call an engineer when

Bring in a financial analyst and tax counsel when tax credits, depreciation, debt or third-party ownership enter the deal.

Typical: Definitions are exact; owner payback habits are common practice, not sourced.
Go deeper
ECON-022 · ECON-023 · ECON-024 · ECON-025 · ECON-036 · ECON-040 · ROT-ECON-16 · ROT-ECON-17
C-07Cost and value · NumberFor sales · engineeringTypical

What does levelized cost of storage mean, and when is a quoted figure meaningful?

Quick answer
6× highercost per kWh
50 cycles a year versus 300, same costs
In plain words

Levelized cost of storage spreads every dollar of owning a battery over every kilowatt-hour it actually delivers, so it reads like a price per kilowatt-hour. Like the cost per visit of a gym membership, it looks great if you go every day and terrible if you go twice a year.

Quick math

Levelized cost = present value of all costs ÷ present value of all kWh delivered (at the same discount rate)

  1. Costs: $1.6M installed + yearly operating cost + year-8 augmentation = $1,960,539 present value at 7% real
  2. Delivered: 300 cycles × 3,400 kWh = 1,020,000 kWh in year 1, fading 2% a year, restored by the year-8 augmentation; discounted total 8,769,383 kWh
  3. Divide: 1,960,539 ÷ 8,769,383 ≈ $0.224 per kWh
  4. Add charging at $0.060 ÷ 0.85 ≈ $0.071: about $0.29 per kWh
About 22 cents per delivered kWh for the system alone, 29 cents with charging energy (synthetic, real dollars)
What moves this number
← lessmore →
Rarely cycled300 → 50 cycles a year
about 6 times the cost per kWh
Charging energy countedadd $0.060/kWh at 85% efficiency
about 32% higher
Nameplate × cycles as energydenominator inflated 15–25%
result about 13–20% too low
−500%0+500%
Watch out
  • Compare levelized costs only at the same cycles per year and the same boundary; published studies differ mostly on these.
  • For backup or capacity batteries that rarely cycle, use cost per kW-year instead of cost per kWh.
  • Always say whether charging energy is included; here it added about a third.
Call an engineer when

When a levelized cost is used to compare storage with generation, or to price a contract or tolling agreement.

Typical: Follows directly from the definition; consistent with published sensitivity studies.
Go deeper
ECON-029 · ECON-030 · ECON-031 · ECON-008 · ROT-ECON-18
C-08Cost and value · DecideFor sales · engineeringRough guide

Which savings can one battery stack, and which collide?

Quick answer
60–85%of the sum
of standalone values, before a dispatch model; use 75%
In plain words

Some savings can share one battery discharge, some compete for the same stored energy or power, and a few are barred from overlapping by program rules. Like lending one car to two people: fine if they need it at different times, a fight if both need it Friday night.

How to choose
Compatible: count both
Choose when
  • Demand-charge cut plus time-of-use shifting: one on-peak discharge earns both
  • Demand-charge cut plus storing solar for use on site
Avoid when
  • The same kWh or kW is promised twice in the same interval
Partial: share the battery
Choose when
  • Any stream plus a backup reserve: energy held back cannot also be sold
  • Demand-charge cut or time-of-use shifting plus demand response: baselines and peak-hour energy can clash
  • Time-of-use shifting plus solar self-use: they draw on the same charging energy
Avoid when
  • Counting each at its standalone value
Exclusive: pick one
Choose when
  • Wholesale energy or regulation versus retail time-of-use shifting for the same kWh
  • Wholesale market participation versus a utility demand response program for the same kW
Avoid when
  • The program documents explicitly allow dual participation
Watch out
  • In the handbook example a $95,150 naive sum became $80,920 once energy was shared, about 85%.
  • Warranty throughput is shared by every stream; adding services can hit the yearly cycle allowance.
  • Dual-participation rules vary by market and utility; confirm with the program documents.
Call an engineer when

When three or more streams, any wholesale market service, or a backup reserve share one battery; a year-long dispatch model that optimizes all streams together settles it.

Rough guide: Compatibility is well described; the haircut band is author judgment.
Go deeper
ECON-021 · ROT-ECON-15 · ECON-041 · ROT-ECON-23
C-09Cost and value · ChecklistFor sales · engineering · everyoneTypical

What does a battery warranty really promise?

Quick answer
Inside limits
energy retention holds only inside the operating envelope
In plain words

A battery warranty is two promises: fix defects for a few years, and keep at least a stated share of energy each year. Both hold only while the battery runs inside the maker's limits on rate, temperature, charge level and cycles. Like a car's powertrain warranty, it pays only if the service log proves you stayed inside the rules.

Checklist

What it covers

What can void or shrink it

Basis to pin down in writing

Planning margins

Watch out
  • Throughput can end a warranty early: the handbook example stack hit its lifetime cap in year 12.3 of 15.
  • Rate, temperature and charge-level limits can be breached even when throughput is within the allowance.
  • Small commercial systems often carry no availability guarantee at all.
Call an engineer when

When the revenue plan cycles more than once a day, runs market services, or promises a customer anything the supplier warranty does not back.

Typical: Typical contract structures; margins are author judgment and contract-specific.
Go deeper
ECON-041 · ECON-042 · ECON-043 · ROT-ECON-23 · ROT-ECON-24
C-10Cost and value · CompareFor sales · engineering · everyoneTypical

What kills the economics of a battery project?

Quick answer
Savings & cost
a 20% miss on either flips this example negative
In plain words

Two numbers decide most projects: the yearly savings and the installed price. A 20% miss on either turns a healthy example into a money-loser, while operating and augmentation costs move it far less. Like a mortgage, your income and the purchase price matter far more than the cost of paint.

Side by side
Change (synthetic base net present value +$225,000, 7% real)Low caseHigh case
Yearly savings −20% / +20%−$212,000+$663,000
Installed cost −20% / +20%+$545,000−$95,000
Discount rate 5% / 9% real+$478,000+$17,000
Life 12 / 18 years−$19,000+$425,000
Operating cost −30% / +30%+$307,000+$143,000
Augmentation cost −50% / +50%+$269,000+$182,000
Watch out
  • Savings get overstated by hourly instead of 15-minute data, ignored ratchets, perfect-foresight dispatch and tariffs frozen for life.
  • Count incentives at face value only with a signed reservation or statutory certainty; haircut market revenue 20–40%.
  • Inputs move together, like a tariff redesign; run named scenarios, not just one-at-a-time swings.
Call an engineer when

When the savings case rests on one tariff, uncontracted market revenue, or an early-stage cost estimate; ask for a sensitivity and scenario run.

Typical: Swings are exact for the example; real ranges depend on estimate maturity.
Go deeper
ECON-022 · ECON-035 · ROT-ECON-20 · ROT-ECON-22 · ROT-ECON-12 · ROT-ECON-13
C-11Cost and value · NumberFor sales · engineeringRough guide

What does it cost to augment or replace a battery over its life?

Quick answer
15–30%more usable energy
added over 20 years, daily-cycled lithium iron phosphate
In plain words

Batteries fade, so a system promised to hold its energy for 15–20 years needs fresh modules added along the way. Plan on typically 15–30% more usable energy in two or three steps (see Batteries for why). Like topping up a leaking tank, it gets cheaper per gallon if prices keep falling, but budget for the case where they do not.

Quick math

Present cost = Σ energy added × today's price × (1 − yearly price decline) to the power of the year ÷ (1 + discount rate) to the power of the year

  1. Year 7: 500 kWh × $350 × 0.96 to the 7th power ≈ $131,500; ÷ 1.07 to the 7th ≈ $81,900
  2. Year 13: 450 kWh × $350 × 0.96 to the 13th power ≈ $92,600; ÷ 1.07 to the 13th ≈ $38,400
  3. Total ≈ $120,000 present value, real base-year dollars, 4% yearly decline, 7% real rate
About $120,000 today to hold 3,600 kWh usable for 20 years, about 5% of the $2.45M installed cost (synthetic)
What moves this number
← lessmore →
Prices stop fallingdecline 4% → 0% a year
about 45% more ($174,000)
Prices fall fasterdecline 4% → 6% a year
about 17% less
Replace instead of augmentfull $1M replacement at year 15
about 63% more present cost ($196,000)
−65%0+65%
Watch out
  • Do not add augmentation on top of a benchmark operating cost that already includes it; ask what the service price covers.
  • Added inverters or fault current can reopen utility review; reserve space, pads and inverter headroom at design.
  • Removal at end of life: plan about $10–40 per nameplate kWh in base-year dollars; few closed-out projects exist.
Call an engineer when

When a contract guarantees energy for 15 years or more, or the site cycles hard or runs hot; use the vendor's fade curve and offer.

Rough guide: Quantity and price decline are forecasts and author judgment.
Go deeper
ECON-005 · ECON-006 · ECON-007 · ROT-ECON-07 · ROT-ECON-08 · ROT-ESS-21
X-01Process, codes and schedule · ChecklistFor sales · engineering · everyoneTypical

How does interconnection work, and how long does it take?

Quick answer
Often longestpath to switch-on
the utility's tariff sets the steps and the clock
In plain words

Interconnection is the utility's permission to run your generation and storage connected to its grid. It moves through set steps: a pre-application report, an application, quick screens, and fuller studies only if a screen fails. Think of it as a building permit from the utility instead of the town, with its own queue, fees and clock that no local permit can shorten.

Checklist

Before applying

Application and screens

Studies, only if needed

Agreement, build and switch-on

Watch out
  • There is no reliable rule-of-thumb duration; ask the utility for its tariff timelines and your queue position.
  • Permission to operate comes from the utility; the town's final inspection does not authorize running in parallel.
  • The utility's protection practice, such as reclosing and transfer trip, often drives cost more than capacity limits.
Call an engineer when

When the site exports, has rotating generators, sits on a weak or heavily loaded feeder, or a study returns protection or grounding upgrades.

Typical: Steps follow the common federal pattern; each state tariff differs.
Go deeper
SYS-032 · ROT-SYS-21 · ROT-SYS-07 · ROT-STD-13 · ROT-STD-11 · STD-012
X-02Process, codes and schedule · NumberFor sales · engineeringTypical

Can we export to the grid, and which screens will the utility run?

Quick answer
15%of the feeder section's yearly peak
common fast-track limit for all generation there
In plain words

Utilities approve small projects quickly only if they pass simple screens. The best known says all generation on a stretch of feeder should stay under about 15% of that stretch's yearly peak load. A certified export cap often turns a study into a pass, like a speed limiter on a truck, but only if the tariff counts the cap, not the nameplate.

Quick math

Screen ratio = (generation already on the section + your studied size) ÷ section's yearly peak; pass at 0.15 or less

  1. Screen limit: 0.15 × 8,000 kW section peak = 1,200 kW
  2. Export capped at 500 kW by a certified control: 600 kW existing + 500 kW = 1,100 kW, passes
  3. No cap, studied at nameplate (1,500 kW solar + 1,000 kW battery): 600 + 2,500 = 3,100 kW, fails
Capped export uses about 92% of the limit and passes; full nameplate is about 2.6 times the limit and goes to study
What moves this number
← lessmore →
Non-export instead of a 500 kW capstudied size 500 kW → about 0
screen total about 45% lower, 600 kW
More projects queued ahead+200 kW on the section
total about 18% higher, 1,300 kW, fails
Tariff counts nameplate, not the capstudied size 500 → 2,500 kW
total about 182% higher, 3,100 kW, fails
−185%0+185%
Watch out
  • Some screens use full nameplate whatever the cap; fault contribution does not depend on the export setting.
  • The control holds back up to 1,600 kW here, at 400 kW minimum site load, even when the battery is full.
  • Fast track has its own size limit, commonly 2–5 MW by line voltage; check eligibility first. Passing the screen is not approval.
Call an engineer when

When any screen fails or is close, the site has rotating generators, or the feeder's grid strength ratio is below about 10.

Typical: Screens are published and common; thresholds and wording vary by tariff.
Go deeper
SYS-032 · SYS-033 · SYS-034 · SYS-035 · ROT-SYS-21 · ROT-SYS-22
X-03Process, codes and schedule · CompareFor sales · engineering · everyoneTypical

Which standard is which: UL 9540, UL 9540A, UL 1741, IEEE 1547, NFPA 855 and the electrical code?

Quick answer
Listing ≠ code
products are listed; installations follow codes as adopted locally
In plain words

Underwriters Laboratories (UL) and the Institute of Electrical and Electronics Engineers (IEEE) write the product and test standards a box is listed or tested to. The National Fire Protection Association (NFPA) writes the installation codes a state or town adopts and enforces. Think of a car's crash rating versus the local speed limit: one is about the product, the other about how and where you use it.

Side by side
Its role in plain wordsEdition to cite (November 2026)
UL 9540Safety listing for the complete storage system3rd edition (2023), revised 2025
UL 9540AFire test method showing how thermal runaway spreads; a report, not a listing. The 6th edition adds pass/fail criteria to the large-scale installation-level test6th edition published March 2026, effective January 2027; 5th edition (2025) still in use; confirm which one the laboratory and local authority accept
UL 1741Listing for inverters, including their grid-support functions3rd edition (September 2021), latest revision 2026; includes Supplement SB, the grid-support tests
IEEE 1547How generation and storage behave on the distribution grid: ride-through, voltage support, trip settings1547-2018 with amendment 1547a-2020, as the utility's tariff adopts it
IEEE 1547.1The test procedures that prove IEEE 1547 behavior1547.1-2020; older versions are superseded
NFPA 855Installation standard for stationary storage: siting, spacing, size limits, hazard analysisNFPA 855-2026 is newest; many places enforce earlier editions, as adopted locally
National Electrical Code (NEC), NFPA 70Wiring rules for the whole installation, including storage and power productionNFPA 70-2026 is newest; the enforced edition is often 1–4 years older, as adopted locally
International Fire Code (IFC)Model fire code many states adopt; its Section 1207 sets storage rules, closely aligned with NFPA 8552024 edition, which predates NFPA 855-2026; as adopted locally
Watch out
  • "Tested per UL 9540A" only means a report exists; read it for edition and configuration before relying on it.
  • "Designed to meet" or "pending" carries no certification; ask for the listing certificate or directory entry.
  • There is no UL 9540 4th edition; that label belongs to an older UL 9540A edition.
Call an engineer when

When the adopted code names a different edition than the test report, or cells, enclosure or firmware changed after listing.

Typical: Editions checked November 2026; the locally adopted edition governs.
Go deeper
ROT-STD-01 · ROT-STD-05 · ROT-STD-06 · STD-005 · STD-009 · ROT-STD-09
X-04Process, codes and schedule · NumberFor sales · engineering · everyoneRough guide

What permits do we need, who approves them, and how long does it take?

Quick answer
2–6 monthsbuilding, electrical and fire permits
use permitted by right; 6–12+ months with hearings
In plain words

The authority having jurisdiction (AHJ) is rarely one office. Building, electrical, fire and planning officials each approve their part under codes as adopted locally, while the utility separately approves running in parallel. Each permit is its own lane, and the slowest lane, often the one with the most review rounds, sets the date you can build.

Quick math

Each permit track = preparation + review rounds × review time + (rounds − 1) × resubmittal time + public process + issuance; the longest track sets the date

  1. Building, electrical and fire, in weeks: 6 + 3 × 4 + 2 × 2 + 1 = 23 weeks
  2. Zoning special use: 4 + 12 = 16 weeks; air permit: 3 + 12 + 4 = 19 weeks
  3. Longest track: 23 weeks
About 23 weeks in this example (just over 5 months) to construction-ready permits; the building track is critical
What moves this number
← lessmore →
Complete first submittal3 → 2 review rounds
19 weeks, about 17% sooner; the air permit becomes critical
Even-odds reviews40% approval chance per round (2.5 rounds expected)
20 weeks, about 13% sooner
Slower air agencyair review 12 → 20 weeks
air track 27 weeks, about 17% later
−20%0+20%
Watch out
  • Plan 2–3 review rounds for the first storage system a jurisdiction has seen, 1–2 where it has approved similar ones.
  • A generator that exports or shaves peaks is generally not an emergency engine for air permits; stricter rules apply.
  • Utility interconnection is separate and often longest, but it gates switch-on, not construction.
Call an engineer when

Before committing a date: hold a joint pre-application meeting with building, electrical, fire and planning officials and record their determinations.

Rough guide: Permit formula is exact arithmetic; durations are author judgment and exclude appeals and moratoria.
Go deeper
STD-002 · ROT-STD-02 · ROT-STD-03 · ROT-STD-13 · ROT-STD-01 · STD-003
X-05Process, codes and schedule · CompareFor sales · engineering · everyoneRough guide

What usually sets the schedule, and how long do long-lead items take?

Quick answer
12–36 monthsfor medium-voltage transformers
order to delivery, pad-mount to substation size
In plain words

The battery is rarely what holds a project up: big transformers, switchgear and the utility's interconnection agreement set the critical path. Projects that need power within about 18 months of the first idea have to order those items early, like booking the venue before printing the wedding invitations.

Side by side
Typical timeNote
Medium-voltage transformersabout 12–36 months, order to deliveryUsually the longest equipment item
Medium-voltage switchgearabout 9–24 monthsRelease early, with the transformer
Battery containers and inverterstypically shorter than the two aboveRarely the critical path
Interconnection agreementset by the utility's tariff and queueOften the critical path; gates switch-on
Building, electrical and fire permitsabout 2–6 months; 6–12+ with hearingsGates construction
Design submittal reviews2 rounds for major equipment, 3 for controls and settings, 10–15 working days eachBudget the rounds in the schedule
Certificate that does not cover the configurationabout 3–9 months of added testingOpen-ended if a test fails
Utility witness testabout 0.5–1 day for a fully type-tested inverter plantAdd 0.5–1 day per partly tested piece
Watch out
  • Lead times are volatile; refresh quotes every quarter rather than trusting these ranges.
  • Changing cell model, enclosure or thermal-management firmware can reopen the listing and fire test evidence.
  • Batteries stored on site while waiting for interconnection need periodic recharge to stay above the maker's storage floor.
Call an engineer when

When power is needed within about 18 months of concept, or the project needs a new medium-voltage service or substation transformer.

Rough guide: Trade press and quotes to 2025; refresh before quoting dates.
Go deeper
ROT-COM-06 · ROT-SYS-07 · ROT-COM-02 · ROT-STD-10 · ROT-STD-11 · ROT-STD-06 · COM-003
X-06Process, codes and schedule · ChecklistFor engineering · salesTypical

What documents does the project owe, and to whom?

Quick answer
Three sets
permit set, utility application, and closeout package
In plain words

Code officials want proof the installation is safe, the utility wants proof the equipment behaves on its grid, and the owner needs a record of what was actually built. Treat the paperwork like a passport application: one missing critical page stops the whole thing, however complete the rest is.

Checklist

To the code officials (the authority having jurisdiction, AHJ)

To the utility

At closeout, to the owner

Watch out
  • The settings sheet sent to the utility and the inverter settings file need to be the same revision.
  • Changes touching protection need incorporating before energization, not at closeout.
  • A fire test report on a different cell, module or enclosure revision is evidence of something else.
Call an engineer when

When the authority asks for a hazard mitigation analysis, the configuration differs from the test report, or protection settings change after the study.

Typical: Common practice; the authority, the utility and the contract add items.
Go deeper
STD-013 · STD-008 · STD-014 · ROT-STD-04 · ROT-STD-07 · ROT-STD-12 · ROT-SYS-23
X-07Process, codes and schedule · ChecklistFor engineering · salesTypical

Which studies happen when?

Quick answer
Screens first
utility screens before applying; safety studies before construction
In plain words

Cheap screening checks come first, to show which choices change the answer, and expensive detailed studies follow only where a screen fails or safety calls for them. It is like a checkup before any scans: the quick tests decide which detailed ones are worth paying for.

Checklist

Feasibility, before applying

Application

Detailed, only if screens fail

Design, before construction

Before switch-on

Watch out
  • A failed screen means study, not refusal; changing the export mode can avoid it.
  • Studies include projects queued ahead; if those withdraw, results and upgrade costs change.
  • Arc-flash studies need redoing after system changes; labels follow the study date.
Call an engineer when

Always for protection, arc flash and fire spacing; also when the grid strength ratio is below 10 or several inverter plants share the feeder.

Typical: Study sequence is common practice; ratio thresholds are not standardized.
Go deeper
ROT-SYS-22 · ROT-SYS-21 · ROT-SYS-23 · STD-007 · STD-006 · ROT-STD-15 · SYS-037
Q-01Commissioning and performance · ChecklistFor sales · engineering · everyoneTypical

What gets tested before the system is handed over?

Quick answer
7 test levels
from lab type test to an unattended run
In plain words

Testing climbs a ladder: lab certification, a factory check of each unit, and installation checks switched off and then on. After that the pieces are tested working together, and finally the system proves its energy, efficiency and an unattended run. Like a car's crash rating, its pre-delivery inspection and a test drive with you aboard, each rung answers a different question and none replaces another.

Checklist

Before it ships

On site, switched off

Working together (site acceptance test)

Performance and handover

Watch out
  • An analysis, inspection or reduced-condition test earns no pass credit unless the specification allows it.
  • Any change after a test sends testing back to the lowest level that change affects.
  • Recorders need synchronized clocks before any timed transfer test, or the timing results mean little.
Call an engineer when

When the site islands, black-starts or switches protection setting groups: those tests need written procedures from the protection and controls engineers.

Typical: Practice basis; test names vary by contract, so define them.
Go deeper
COM-007 · COM-009 · COM-010 · ROT-COM-09 · ROT-COM-07 · ROT-COM-12 · ROT-STD-11
Q-02Commissioning and performance · NumberFor engineering · salesRough guide

How is round-trip efficiency measured, and why does the meter location change the answer?

Quick answer
6–14 pointspercentage points lower at the grid meter, with auxiliaries
than at the battery terminals, same test cycle
In plain words

Round-trip efficiency is energy out divided by energy in. Each step between the battery and the grid meter (inverter, transformer, cables, cooling, controls) takes a cut, so one test reads higher at the battery than at the grid. It is like a car's fuel economy on the test bench versus on the commute: both are true, so the contract has to name the meter.

Quick math

Round-trip efficiency = energy discharged ÷ energy charged, both at the same meter; add separately fed cooling and controls energy to the charged side if the contract counts it

  1. Battery terminals: 2,000 ÷ 2,105 kWh = 95.0%
  2. Inverter output: 1,964 ÷ 2,144 kWh = 91.6%
  3. Grid meter: 1,944 ÷ 2,165 kWh = 89.8%
  4. Grid meter plus 60 kWh of separately fed auxiliaries: 1,944 ÷ 2,225 kWh = 87.4%
One test cycle reads from 95.0% down to 87.4%: a 7.6-point spread from meter choice alone
What moves this number
← lessmore →
Auxiliaries double60 → 120 kWh on the separate feed
reads 85.1%, about 3% lower
Quoted at inverter outputgrid meter → inverter meter
reads 91.6%, about 2% higher
Cheaper sub-metermeter accuracy class 0.2 → 0.5
uncertainty about ±0.7 → ±1.0 point if separate meters; less with one meter
−40%0+40%
Watch out
  • A new rated-power test in mild weather reads about 2–4 points higher than everyday operation at the same meter.
  • A guarantee that names no meter point can be met or missed by meter choice alone.
  • Revenue meters resolve round-trip efficiency to about ±0.5–1 point but cannot verify inverter efficiency.
Call an engineer when

When a guarantee margin is under about 1 point, auxiliaries are on a separate feed, or vendor and grid-meter figures disagree.

Rough guide: Definition is exact; loss per step is author judgment.
Go deeper
COM-014 · COM-012 · COM-015 · ROT-COM-13 · ROT-COM-14 · ROT-COM-11 · ROT-ESS-20
Q-03Commissioning and performance · NumberFor sales · engineeringRough guide

How is availability measured?

Quick answer
95–98%per year, capacity-weighted
common utility-scale guarantee, with defined exclusions
In plain words

Availability is the share of the hours that count during which the system could deliver its contracted power. Excused events such as utility outages drop out entirely, and a system running at half power earns half credit for those hours. Like a store's opening-hours promise, the fine print on what counts as closed matters as much as the percentage.

Quick math

Availability = (eligible hours − lost hours) ÷ eligible hours; excluded events leave both; partial capability counts as a fraction

  1. Month: 720 h − 12 h excluded (scheduled maintenance, utility outage) = 708 eligible hours
  2. Lost: 10 h forced outage + 36 h × 0.5 with one of two inverter blocks tripped + 2 h telemetry gap = 30 h
  3. Availability: (708 − 30) ÷ 708 = 678 ÷ 708
About 95.8% for the month
What moves this number
← lessmore →
Time-only definitionhalf-down block counted as fully up
reads about 98.3%, about 3% higher
Slower repairforced outage 10 → 20 h
about 94.4%, about 1% lower
Maintenance beyond the allowance8 h counted as down, not excluded
about 94.7%, about 1% lower
−5%0+5%
Watch out
  • Availability does not show whether the system performed when called; pair it with dispatch records.
  • Define available by demonstrated capability, not absence of alarms; settle low-charge, heat derate and curtailment rules in the contract.
  • Guarantees above about 98% usually need on-site spares; small commercial systems often carry no guarantee at all.
Call an engineer when

When availability carries damages, the plant has several blocks, or telemetry gaps and curtailment need contract treatment.

Rough guide: Formula is a contract definition; the guarantee range is author judgment.
Go deeper
COM-017 · ROT-ECON-24 · COM-025 · ROT-COM-19 · ROT-SYS-14
Q-04Commissioning and performance · NumberFor engineering · salesRough guide

How is battery capacity tracked over its life?

Quick answer
Yearly testsame procedure, same season
three tests before trusting a trend
In plain words

Once a year the battery repeats the exact energy test it passed at commissioning, and that result divided by the first test is its retention. Three points on a chart fit a straight line or a flattening curve about equally well. Plan for both until more tests come in, as a doctor would before calling a trend from three readings.

Quick math

Retention = this year's test energy ÷ commissioning test energy; fit a trend and project when it crosses the trigger

  1. Tests, years 0–3: 4,000, 3,872, 3,768, 3,676 kWh, so retention 1.000, 0.968, 0.942, 0.919
  2. Straight-line fit: about 2.7 points lost per year, so 80% at about 7.3 years
  3. Flattening (square-root-of-time) fit: 80% at about 22 years
The same three years of data put the 80% trigger at about 7 or about 22 years, depending on the model
What moves this number
← lessmore →
Flattening fade modelstraight line → square-root fit
80% reached about 203% later, at about 22 years
Earlier triggeract at 85% instead of 80%
about 5.5 years, about 25% sooner
Faster fade2.7 → 3.2 points per year
80% at about 6.2 years, about 16% sooner
−205%0+205%
Watch out
  • Trend against the commissioning test; warranty claims use the warranty's own reference and procedure; margins under 2 points sit inside test repeatability.
  • Rest 30–60 minutes after charge and discharge and run at least two cycles, or results drift.
  • Neither fit predicts when fade speeds up late in life; order added capacity about 6–12 months before the trigger date (see Batteries).
Call an engineer when

When a warranty claim is near, the trend approaches the augmentation trigger, or the battery's own health estimate disagrees with tests by over 3%.

Rough guide: Retention is a definition; cadence and model choice are author judgment.
Go deeper
COM-018 · ROT-COM-16 · ROT-COM-10 · ROT-COM-14 · COM-030 · ROT-COM-23
Q-05Commissioning and performance · ChecklistFor sales · engineering · everyoneTypical

What does routine maintenance look like?

Quick answer
Monthly–yearly
remote checks monthly, site visits quarterly, deep tests yearly
In plain words

Most of the watching is remote: monitoring flags cell voltage and temperature spreads every month. Technicians visit quarterly for filters, fans and cooling, and once a year they do the deeper checks and the capacity test. It is like a car's dashboard, oil changes and annual inspection, and the maker's manual and warranty, not this card, set the actual intervals.

Checklist

Monthly

Quarterly

Twice a year to yearly

Per code and the maker

Watch out
  • Infrared triage versus like parts: 1–3 °C hotter investigate, 4–15 °C repair soon, over 15 °C repair immediately.
  • Light load hides hot connections; scan near normal load or results read falsely clean.
  • One spare usually covers a part when expected failures during its lead time are few, but long-lead items still warrant a spare.
Call an engineer when

When an infrared rise exceeds 15 °C, cell temperatures climb at full cooling duty, or alarms flood operators repeatedly.

Typical: Typical maker and industry intervals; the manual and warranty govern.
Go deeper
ROT-COM-18 · ROT-COM-22 · ROT-COM-20 · ROT-COM-19 · COM-024 · COM-028 · COM-026
Q-06Commissioning and performance · CompareFor engineering · salesRough guide

What usually goes wrong first?

Quick answer
Settings
first-year trips trace mostly to settings, controls and communications
In plain words

In the first year, most unplanned trips come from protection settings, control logic, communication timeouts and firmware rather than broken parts. Check settings and event records before replacing anything. It is like a new phone that keeps dropping calls: the fix is usually a setting, not a new phone.

Side by side
Likely causeFirst check
Unexpected trip in year oneProtection or ride-through setting, communication timeout, firmwareCapture as-found settings and event records before any reset or reboot
Island protection misbehavesProtection setting group not switching when the site islandsSetting-group selection test
Control lost after a network blipCommunications timeout left at the vendor defaultCommunications-loss test
Less energy than specifiedBattery controls' charge limits narrower than specifiedCharge-limit and capacity tests
Efficiency below estimateAuxiliary load higher than estimatedEfficiency test with auxiliaries metered; investigate a month above 1.5 times the model
Battery derates on hot daysCooling low on charge, fouled coil or low airflowAir temperature drop across the coil, filters and setpoints
Growing cell voltage spreadAging or faulty module, high resistanceSpread trend, infrared scan of modules, capacity test
Odd power readings or relay behaviorCurrent transformer polarity or ratio wired wrongPhasor check at commissioning
Watch out
  • Resets, reboots and firmware loads overwrite the records that separate a design error from a failed part.
  • Early hardware failures also cluster in year one; settings first does not mean settings only.
  • The same failure on the same equipment twice within 90 days deserves a root cause analysis.
Call an engineer when

When a trip repeats, protection operates unexpectedly or fails to operate, or a fault involves batteries or fire systems.

Rough guide: Author judgment from commissioning practice, consistent with published incident reviews.
Go deeper
ROT-COM-21 · ROT-COM-17 · ROT-COM-22 · ROT-COM-18 · COM-019 · COM-029
N-01Project snapshots · Case studyFor sales · engineering · everyoneTypical
Project snapshot · a synthetic worked example from the handbook

What does a 500 kW / 2 MWh battery really do for an office's demand bill?

Headline result
About 350 kWof peak shaved, not 500 kW
design peak day, new battery; 325 kW at year 10
Site
Synthetic office and light-industrial site, 480 V service, 1,722 kW peak demand
Goal
Cut demand charges with no export to the grid and no backup duty

On a long, hot-afternoon peak the battery runs out of stored energy before it runs out of power, like a sprinter entered in a marathon. Its 500 kW inverter holds only about 350 kW when new and 325 kW at year 10. Demand savings alone did not earn back the $900,000 cost at an 8% return over ten years, even with a 30% tax credit.

The system
Battery500 kW / 2,000 kWh lithium iron phosphate, one container
Inverter500 kVA, grid-parallel only
Tariff$24/kW-month facility demand plus $20/kW-month summer on-peak demand
Installed cost$900,000 ($450/kWh)
The results
Peak shaved, design dayabout 350 kW new, 325 kW at year 10 (plan on 325 kW and 301 kW)
Energy delivered to the building1,739 kWh new from 2,000 kWh nameplate, 13% less
Demand savings, realized at 80% of simulationabout $89,000 a year
Round trip, with the battery's cooling and controlsabout 83% (89% without them)
Ten-year net present value at 8%−$396,000 with no tax credit; −$126,000 with a 30% credit, if the battery meets 2026 sourcing rules
Mid-life augmentationnot worth it: about $15,000 of gain for $44,000 of cost, present value
What drove the design
  • Energy, not power, set the shave: the last 100 kW of a full 500 kW shave alone would need about 1,049 kWh.
  • Shaving lowered the site's power factor; spare inverter capacity supplied reactive power so about one-seventh of August savings was not lost.
  • Non-export service: the battery gives no backup and stops when the grid fails.
Lessons
  • Buy usable energy delivered at the meter at a stated power and temperature, not nameplate kWh.
  • With the 30% credit, breakeven needed about 18% lower cost ($371/kWh) or a 15-year horizon; study a smaller battery.
  • The battery's own cooling and controls used 8.9% of discharge, well above the usual 1.5–4%, because peak shaving cycles rarely.
Watch out
  • All figures come from the handbook's synthetic example, not a real site, product, tariff or price.
  • Simulation assumes perfect knowledge of each peak; real savings run about 70–90% of that, lower for weather-driven peaks.
  • A tariff change from demand charges to energy or coincident-peak charges can erase the value.
Call an engineer when

Before quoting savings: a dispatch simulation with forecast error on 12+ months of meter data, plus written confirmation of the tariff and any tax credit.

Typical: Synthetic worked example; one year of data, perfect-foresight dispatch.
Go deeper
EX-A-01 · EX-A-02 · EX-A-03 · EX-A-07 · EX-A-08 · EX-A-09
N-02Project snapshots · Case studyFor sales · engineering · everyoneTypical
Project snapshot · a synthetic worked example from the handbook

What can solar and a battery add to a hospital that already has backup generators?

Headline result
34-yr paybackon bill savings alone
$2.9 million add-on; resilience has to carry the case
Site
Synthetic 200-bed acute-care hospital, 480 V service, 2,199 kW facility peak
Goal
Keep imaging running through utility loss, stretch generator fuel and trim demand charges

The code-required emergency power stays on the diesel generators. In the example, solar and a battery let the scanners ride through a grid blink, keep the diesels loaded and stretch the fuel from about 102 to 113 hours. On bill savings alone the add-on pays back in about 34 years, so it is bought like insurance, for outage resilience, not as an investment.

The system
Generators2 × 1,250 kW standby diesel; either one carries the full essential load (N+1)
Solar520 kW DC / 400 kW AC rooftop
Battery600 kW / 1,200 kWh, 750 kVA grid-forming inverter
Imaging transferstatic switch; scanners tolerate no more than a 20 ms break
Fuel2 × 5,000 gal; owner target 96 hours
The results
Imaging transfer gapabout 12 ms with a static switch; a fast breaker, about 88 ms, fails
Fuel autonomy, no refuelling102.5 h without solar and battery, 113.5 h with them (8,100 gal usable, design week)
Weekly fuel11% less (13,168 to 11,710 gal)
Battery reserve held for emergencies33% state of charge floor; 571–714 kWh left for bill savings
Demand shaved200 kW; a 250 kW shave would need 1,058 kWh and fails
Simple payback34.1 years; 27.1 years if a 30% credit applies to the eligible solar and battery cost (about $2.0M)
What drove the design
  • Code-required emergency branches stay on the diesels; solar and battery reach them only through a tie, as a beyond-code extra.
  • Each diesel needs at least 30% load; the battery soaks up midday solar so the diesels stay above that floor.
  • Only a static switch with a grid-forming battery already holding the bus meets the 20 ms imaging limit.
Lessons
  • A 15-year payback would need about $107,000 a year of resilience value the owner accepts.
  • A broad hospital load makes the energy needed grow fast with each extra kW of shave.
  • Hospitals rarely meter by branch; log each transfer switch before final sizing.
Watch out
  • Synthetic example: loads, tariff and costs are invented; code branches and timing follow the editions adopted locally.
  • Based on one synthetic week; a summer week raises load and shortens fuel autonomy.
  • A tax-exempt hospital would need elective (direct) pay; eligibility was not confirmed in the example.
Call an engineer when

Always for hospitals: the emergency-system boundary, transfer timing and grounding need licensed design, a transient study and the authority having jurisdiction's acceptance.

Typical: Synthetic worked example; one week of branch-level data.
Go deeper
EX-B-01 · EX-B-02 · EX-B-04 · EX-B-05 · EX-B-06 · EX-B-10 · EX-B-11
N-03Project snapshots · Case studyFor sales · engineering · everyoneTypical
Project snapshot · a synthetic worked example from the handbook

Does solar plus a battery beat diesel alone for an off-grid community?

Headline result
About 9% lesscost per kWh delivered
$0.486 vs $0.535/kWh, 20 years, $5.50/gal fuel
Site
Synthetic coastal settlement with no grid; fuel arrives by barge only mid-June to September
Goal
Lower delivered-energy cost across an 8.5-month gap between fuel deliveries

Solar plus a battery that can run the island with the diesels off cut fuel about 41% and delivered-energy cost about 9%. The extra $3.3 million paid back in about 8.7 years, but solar without the battery was the worst choice. The diesels have to stay loaded, so most of that solar is thrown away, like hiring a helper the foreman never lets work.

The system
Diesels3 × 250 kW prime-rated (N+1)
Solar900 kW DC / 720 kW AC, fixed tilt
Battery1,500 kWh lithium iron phosphate, 630 kVA grid-forming inverter
Load2,058 MWh a year; 422 kW peak, 123 kW minimum
The results
Fuel saved, load-following dispatch41% (68,286 gal a year); renewable share about 40%
Solar without a batteryonly 9% fuel saved; 72% of the solar curtailed
Cost per kWh delivered$0.535 diesel only; $0.486 with solar and battery; $0.604 solar without battery
Simple payback on the extra $3.3 millionabout 8.7 years
Break-even fuel priceabout $3.97/gal
Seasonal fuel tankage31% smaller, while annual fuel falls 41%
What drove the design
  • A median summer night needs about 2,212 kWh delivered, so no practical battery size carries every night.
  • With the diesels off, fault current falls to about 45% of one diesel's, so protection needs fresh study.
  • December solar is about 30% of an average month, so the winter fuel stockpile barely shrinks.
Lessons
  • The advantage rises and falls with delivered fuel price; test $4–10/gal.
  • Load-following dispatch beat cycle-charging: 41% against 36% fuel saved.
  • Solar sized for a diesel-only island is stranded capital until storage lets the diesels switch off.
Watch out
  • Synthetic example: load, fuel price and costs are invented; delivered diesel prices vary widely by site and year.
  • Hourly simulation leaves out sub-hourly solar swings, generator start failures, forecast error and load growth.
  • A 600 kW, 15-minute reserve needs 150 kWh (27% floor); the 23% floor holds 106.5 kWh for a 426 kW start.
Call an engineer when

Before procurement: sub-hourly dispatch, a stability study with diesels off, fault and grounding studies, and a measured year of load and solar data.

Typical: Synthetic worked example; hourly rule-based simulation, constant fuel price.
Go deeper
EX-C-01 · EX-C-03 · EX-C-04 · EX-C-05 · EX-C-08 · EX-C-09 · EX-C-10 · EX-C-12 · EX-C-13
N-04Project snapshots · Case studyFor sales · engineering · everyoneTypical
Project snapshot · a synthetic worked example from the handbook

Is a battery worth it for a factory that already runs combined heat and power (CHP)?

Headline result
−$537,000net present value, battery package
15 years at 8%, counting $150,000/yr outage value
Site
Synthetic plastics extrusion plant, 13.2 kV service, three shifts
Goal
Carry top-priority loads through outages, keep demand savings when the CHP trips, lower energy cost

In the example the battery lets the plant ride through outages, start a big compressor on the island and keep its demand savings when the gas engine trips. Even so, it loses about $537,000 over 15 years on the owner's own outage estimate. It pays only if avoided outages exceed about $213,000 a year, roughly four or five production stops, since demand savings, net of upkeep, cover only about a quarter of its yearly cost.

The system
CHP2,000 kW natural-gas engine with heat recovery
Battery2,000 kW / 4,000 kWh, grid-forming
Solar1,600 kW DC / 1,250 kW AC
Largest motor300 hp air compressor started across the line
Battery package cost$2.5 million with controls, switchgear and grounding
The results
Island adequacyCHP plus battery carries Tiers 1 and 2; battery alone a reduced Tier 1, for hours
Compressor start, CHP plus batteryvoltage holds at 0.867 per unit against a 0.85 limit
Compressor start, battery alone19.5% voltage dip; start blocked in that mode
Demand protection when the CHP tripsabout $106,000 a year
Battery package net present value−$537,000 (8%, 15 years)
Break-even outage valueabout $213,000 a year, about 4.3 events at $50,000
What drove the design
  • The grid-forming battery, not the gas engine, makes the island motor start possible; the engine is assumed to accept only about a 20% load step.
  • On battery alone ordinary overcurrent relays cannot see feeder faults; protection switches to voltage-based and differential schemes.
  • Without an island setting group, arc-flash exposure screened at about 1.8 times the grid case.
Lessons
  • Price the battery on the owner's outage cost; demand savings alone will not carry it.
  • Block big motor starts in weak island modes instead of oversizing for them.
  • Settle inverter fault behavior and the utility's demand treatment in the contract before ordering.
Watch out
  • Synthetic example; the outage cost is an owner estimate and dominates the answer.
  • A worst-case 2.5-hour summer engine trip outlasted the battery's stored energy.
  • The arc-flash figure is a relative screen, not an incident-energy result.
Call an engineer when

Before settings or labels: fault, coordination, arc-flash, motor-starting and harmonic studies for every mode, sealed by a licensed engineer, plus witnessed island tests.

Typical: Synthetic worked example; one year of trips, owner-estimated outage cost.
Go deeper
EX-D-01 · EX-D-02 · EX-D-03 · EX-D-04 · EX-D-07 · EX-D-08 · EX-D-10
N-05Project snapshots · Case studyFor sales · engineering · everyoneTypical
Project snapshot · a synthetic worked example from the handbook

What does it take for a 5 MW / 20 MWh grid battery to keep its promise for 20 years?

Headline result
+$30,900net present value, about 8.06% return
20 years at 8%, no tax credit
Site
Synthetic front-of-meter plant on a 12.47 kV distribution feeder, 45 °C design day
Goal
Sell 4-hour capacity and day-ahead energy arbitrage for 20 years

To deliver 20 MWh at the meter for 20 years, the plant buys 25 MWh of battery and adds a container in years 7 and 19, about $1.2 million cheaper in present value than building 7 up front. The result barely clears an 8% return, so energy prices and capacity payments, not the hardware, decide whether it makes money, like a shop living on a thin margin.

The system
Battery5 containers × 5.016 MWh lithium iron phosphate (25.08 MWh)
Inverters5 × 1,250 kVA
Step-up transformers5 × 1,500 kVA, 12.47 kV
Obligation5,000 kW for 4 hours at the meter, power factor ±0.95
The results
Nameplate bought per MWh promisedabout 1.25 (25.08 MWh for 20 MWh)
Round-trip efficiencyabout 89% before auxiliaries; 86.4% at the revenue meter with them
Auxiliary energy, year 1about 3.4% of net export
Augmentationone block in year 7, one in year 19; $1.19 million cheaper than overbuild
Net present value and return+$30,900; 8.06%
Levelized cost of storage$121/MWh without charging cost, $129/MWh with it
What drove the design
  • Losses, auxiliaries and fade stack up: the obligation holds only while battery health stays at or above 0.881.
  • At the 45 °C design day 5 MW holds with 5.6% margin; at 50 °C with full reactive power, output falls to about 4,825 kW (3.5% short), so the contract should excuse hot-day derate.
  • Whole-block augmentation keeps old and new cells off the same DC bus.
Lessons
  • Quote levelized cost with its convention; the $8/MWh charging gap here reflects cheap solar-hour charging.
  • Energy margin ±30% swings net present value by about ±$1.48 million, far more than the base result.
  • A 30% credit (needs wage, apprenticeship and sourcing compliance) lifts NPV to about $1.78 million.
Watch out
  • Synthetic example; perfect-foresight market revenue overstates real energy spreads.
  • Without augmentation, battery health falls to about 0.68 by year 20, about 17 MWh of nameplate.
  • Tax credit eligibility depends on current federal law and sourcing rules.
Call an engineer when

Before construction: utility interconnection studies, grounding and fault duty, stability, a vendor-warranted fade curve, fire hazard analysis and market dispatch simulation.

Typical: Synthetic worked example; datasheet-class equipment, fitted fade model.
Go deeper
EX-E-01 · EX-E-02 · EX-E-03 · EX-E-05 · EX-E-06 · EX-E-10 · EX-E-11 · EX-E-12
N-06Project snapshots · Case studyFor sales · engineering · everyoneTypical
Project snapshot · a synthetic worked example from the handbook

Should a data center use its batteries for demand response?

Headline result
15-yr paybackdedicated 3 MW battery
earns less than its yearly capital cost; needs incentives
Site
Synthetic 6 MW colocation data center, two 13.8 kV utility feeds
Goal
Fault-tolerant power to dual-corded servers, 48 hours of fuel, plus demand response revenue

The design keeps three jobs apart: generators for long outages, uninterruptible power supply (UPS) batteries for the first minutes, and a separate 3 MW battery for demand response. The separate battery is safe because it sits outside the path that feeds the servers, and it pays back in about 15 years. Selling spare UPS energy pays only by shrinking the reserve, like renting out the spare tire.

The system
UPS2N per hall: two sides of 3 × 1,000 kW lithium-ion modules
Generators6 × 2,250 kW at 13.8 kV (N+1)
Fuel40,800 gal in six sub-base tanks
Demand response battery3,000 kW / 9,200 kWh on its own medium-voltage bus
The results
Generator plant9,550 kW design load: 70.7% loaded with all 6 running, 84.9% with one out (5 carry it)
Fuel autonomy49.9 h at design load, 75.2 h at average load
UPS battery379 kWh per side for 5 minutes at end of life
2N vs N+1 UPSdowntime 1.03 vs 8.55 minutes a year per hall
Dedicated battery in demand response$246,000 a year net; payback 15.0 years
Spare UPS energy in demand response$28,800 a year; no end-of-life surplus if the reserve is set at design load
What drove the design
  • Backup, ride-through and energy management are sized separately, each for its own job.
  • 2N cuts unavailability 8.3-fold but saves only about $165,000 a year against $374,000 a year of annualized cost; maintainability and contracts justify it.
  • Once the UPS is 2N, the generator plant sets the reliability floor.
Lessons
  • Keep demand response off the ride-through reserve, and on one side of a 2N pair only.
  • Emergency engines in demand response face federal and state run-hour limits; the example left them out pending permits.
  • Expected-value math understates what one real outage costs at $5 million an event.
Watch out
  • Synthetic example; outage probabilities and correlation factors are judgment values.
  • If both UPS sides join demand response, one utility outage can drop servers on both power cords at once.
  • Simple reliability diagrams miss transfer failures, maintenance error and correlated weather.
Call an engineer when

Before selling demand response or availability terms: a Markov or Monte Carlo availability study, a pull-the-plug integrated test, and permits for any generator participation.

Typical: Synthetic worked example; generic reliability data, synthetic prices.
Go deeper
EX-F-01 · EX-F-02 · EX-F-03 · EX-F-06 · EX-F-10 · EX-F-12
T-01Toolkit · ChecklistFor sales · everyoneTypical

What should I ask on the first call, based on what the customer wants?

Quick answer
Goal first
rank resilience, savings and sustainability, then ask by goal
In plain words

Get the customer to rank what matters most, keeping the lights on, lower bills or cleaner energy, because each goal needs different data and leads to a different system. Skipping that step is like planning a trip without asking where they want to go.

Checklist

Every customer

Resilience: keep the lights on

Bill savings

Sustainability

Watch out
  • “Eight hours of backup” is not a requirement until it names the loads, the season and the tolerable break.
  • If the numbers only work with a resilience value, get the owner to name that value early.
  • Rough guide: critical load runs 15–35% of an office's peak but 40–70% at clinics; measure it.
Call an engineer when

When loads cannot take a break, life-safety loads are involved, large motors start on backup, or the customer wants to run islanded.

Typical: Owner's requirements template and screening rules; some thresholds are rough.
Go deeper
SYS-001 · ROT-SYS-01 · ROT-SYS-03 · ROT-ECON-10 · ROT-ECON-13 · ROT-MG-06 · ECON-012
T-02Toolkit · ChecklistFor sales · engineering · everyoneTypical

What red flags mean I should slow down before quoting?

Quick answer
Any one: pause
investigate before sizing or pricing
In plain words

Some problems end projects no matter how good the equipment is: the utility, the tariff, the site, the schedule or the money. Spotting one early is like a mechanic hearing a knock before the road trip, cheap to check now and expensive later.

Checklist

Utility and tariff

Site

Schedule

Money

Technical

Watch out
  • A red flag is a reason to investigate, not to walk away; most have a fix at a price.
  • Several thresholds here are rough screens from author practice; confirm with the utility and current quotes.
  • Lead times move with the market; refresh them with quotes each quarter.
Call an engineer when

On any flag: a utility pre-application meeting, a pre-application meeting with the local permitting authority, or a feasibility study before sizing or pricing.

Typical: Feasibility killers are author practice; some thresholds are low-confidence screens.
Go deeper
SYS-007 · ROT-SYS-06 · ROT-SYS-07 · ROT-SYS-08 · ROT-ECON-11 · ROT-ECON-12 · ROT-ECON-22 · ROT-MG-06 · ECON-014 · ECON-020
T-03Toolkit · ChecklistFor sales · everyoneTypical

What should I never promise, and what do I say instead?

Quick answer
Ranges + tests
every claim with its conditions and how it is measured
In plain words

Customers remember the first number they hear, so give ranges with their conditions and say what will be measured, and where. A promise with no boundary and no test is like a mileage claim that never says city or highway.

Checklist

Backup and switching

Size and performance

Money

Safety and approvals

Watch out
  • Never quote a perfect-foresight simulation as the savings number.
  • Every guarantee to a customer needs a matching supplier guarantee on the same metric, boundary and test.
  • The money haircuts here are rough screens; replace them with a dispatch model before contract.
Call an engineer when

Before any written performance, availability or savings guarantee: have engineering and contracts fix the metric, boundary, test method and remedy.

Typical: Wording follows handbook rules; some money figures are rough screens.
Go deeper
MG-010 · MG-011 · EX-A-01 · EX-A-07 · ROT-ECON-12 · ROT-ECON-15 · ECON-041 · ECON-042 · ECON-043 · ROT-PROT-06
T-04Toolkit · ChecklistFor sales · engineering · everyoneTypical

Who do I bring in, and which study answers which question?

Quick answer
By question
each open question has a study and an owner
In plain words

Each hard question has an owner: an engineer for fault current and protection, the utility for connection, the fire and building officials for siting, tax counsel for credits. Bringing them in at the right phase is cheaper than redesigning later, like calling the plumber before the drywall goes up.

Checklist

Will the utility let us connect?

Is it worth it?

Will the lights stay on, and how long is the blink?

Is it safe?

Does it fit?

Does it work as promised?

Watch out
  • Short-circuit, protection, arc-flash, grounding and stability studies need licensed engineering review before construction.
  • Replace screening sizes with chronological simulation results before 30% design.
  • Long-lead transformers and switchgear may need ordering before every study is final.
Call an engineer when

At concept for any islanding, inverter-heavy or life-safety project; by 30% design for any project with new switchgear or a new interconnection.

Typical: Study-by-phase matrix is author practice; utilities and projects vary.
Go deeper
SYS-001 · MG-010 · PROT-017 · PROT-022 · ROT-PROT-11 · ROT-SYS-07 · ECON-022

No cards match. Clear the search or a filter.

Fundamentals

Three sentences or fewer, one thing to remember.

Power and energy

F-01What is the difference between kW and kWh in a battery system?

Kilowatts (kW) are how fast the battery can deliver energy; kilowatt-hours (kWh) are how much it holds. Both numbers are needed to describe a system, and they are sized separately.

Like a water tank: kW is the size of the tap, kWh is the size of the tank.

Go deeper: L-02, B-04

F-02What does "500 kW / 2 MWh" mean?

The system can deliver up to 500 kW at once and stores 2 megawatt-hours (2,000 kWh). Divide energy by power and it runs about 4 hours at full output. If the 2 MWh is the label size rather than usable energy, expect less than 4 hours.

2,000 kWh ÷ 500 kW = 4 hours at full power.

Go deeper: B-04, N-01

F-03What do MW and MWh mean in a project headline?

A headline like "5 MW / 20 MWh" gives power first (megawatts) and stored energy second (megawatt-hours); divide the second by the first for hours at full output. A headline that quotes only megawatts says nothing about how long the plant can run. Ask whether the energy is at the meter or on the label: in one worked example, a grid plant buys about 25 MWh of battery to promise 20 MWh at the meter.

20 MWh ÷ 5 MW = 4 hours; megawatts alone say nothing about hours.

Go deeper: N-05, B-04

F-04What is the difference between kW and kVA?

Kilowatts (kW) are the power that does useful work; kilovolt-amperes (kVA) are the total load the wires and equipment have to carry, including the part that only shuttles back and forth. Inverters, generators and transformers are limited by kVA, so they are sized above the kW they serve.

Size an island inverter at about 1.1–1.3 times peak kW, stated in kVA.

Go deeper: I-01

F-05Why do solar quotes show both AC and DC ratings?

Panels are rated in direct current (DC) kilowatts and inverters in alternating current (AC) kilowatts, and the array is deliberately bigger, usually 1.2–1.3 times the inverter rating. The AC rating is what the site actually receives, so compare quotes on the same basis. In an island, the inverter's AC rating, not the panels, sets what solar can deliver.

1,000 kW of panels on an 800 kW inverter is normal: a ratio of 1.25.

Go deeper: S-03, I-01

F-06What is the difference between peak demand and energy use?

Peak demand is the highest power the site draws, in kW, usually averaged over 15 minutes on the bill; energy use is the total over time, in kWh. Peak sizes inverters, generators and demand charges, while energy sizes the battery or the fuel tank. Load factor, average power divided by peak, shows how peaky the site is.

The pipe handles the busiest moment; the tank has to last the whole outage.

Go deeper: L-02, L-03
Batteries

F-07What is the difference between nameplate, usable and delivered energy?

Nameplate is the label size, and usable is the part the controls let you use, about 90–95% of nameplate for a new lithium iron phosphate system. Delivered is what reaches the building after conversion losses, about 83–91% of the label when new, before the battery's own use and less after aging and cold. For a backup mission sized to end of life, buy about 1.5–1.8 times the energy the load needs.

A 1 MWh label does not mean 1 MWh at the plug.

Go deeper: B-03, B-01

F-08What does a battery's duration mean?

Duration is how many hours a battery can run at its rated power: usable energy divided by power. Power jobs such as bridging until a generator starts or frequency regulation need under an hour, peak shaving needs 1–4 hours, and backup of critical loads commonly 2–8 hours.

Sprinter or marathon runner: the job, not the brand, sets the hours.

Go deeper: B-04

F-09What is C-rate, in plain words?

C-rate is charge or discharge power divided by the battery's energy: a 1,000 kW / 4,000 kWh battery runs at 0.25C, a 2-hour battery at 0.5C. Higher rates make more heat, so a 2-hour battery runs warmer than a 4-hour one and needs more cooling. Recharging also takes about 15–30% longer than energy divided by power.

0.25C means about four hours to empty at full power.

Go deeper: B-14, B-08

F-10What is the difference between state of charge and state of health?

State of charge (SOC) is how full the battery is right now, like a fuel gauge. State of health (SOH) is how big the tank still is compared with new. Systems are commonly planned to reach end of life at 70–80% state of health.

State of charge: fuel gauge. State of health: how big the tank still is.

Go deeper: B-13, B-05

F-11What is round-trip efficiency?

It is the share of energy put into a battery that comes back out. The answer depends on where it is measured: the same test reads 6–14 points lower at the grid meter, once transformers, cooling and controls are counted, than at the battery terminals. A guarantee that names no meter point can be met or missed by meter choice alone.

One test, two meters: 95.0% at the battery, 87.4% at the grid.

Go deeper: Q-02

F-12What counts as a battery cycle?

One cycle is a full charge and discharge, or partial ones that add up to the same throughput. Ratings of 3,000–8,000 cycles for lithium iron phosphate are cell tests at 25 °C. At about one cycle a day in a cooled enclosure, calendar aging usually ends the battery's life first, at about 10–15 years.

Two half discharges count as one cycle.

Go deeper: B-05, B-06

F-13Why do batteries fade, and what is augmentation?

Batteries lose capacity both with time and with use, faster when hot or kept full. Augmentation means adding battery blocks partway through the project to make up for fade, instead of buying all the extra on day one. Over 20 years at about one cycle a day, expect about 15–30% of first usable energy added, in two or three events.

About 10 °C hotter roughly doubles idle aging.

Go deeper: B-09, B-07

F-14Why is lithium iron phosphate the common choice?

Lithium iron phosphate (LFP) lasts more cycles, about 3,000–8,000 against 1,000–4,000 for nickel manganese cobalt (NMC), and needs more heat before a cell runs away. NMC stores more energy per kilogram, which matters more in a car than on a concrete pad. Compare the specific product's datasheet, warranty and fire test report, not the chemistry name.

Runaway trigger about 200–280 °C for LFP, about 150–230 °C for NMC.

Go deeper: B-06

F-15What is thermal runaway?

Thermal runaway is a cell failure that heats itself, vents flammable gas and can spread to neighboring cells. A failing lithium battery often gives off gas before any flame, so the danger can be a gas explosion inside the enclosure rather than a fire. That is why fire codes ask about energy per space, spacing, explosion control and fire test data.

Lower risk is not no risk: lithium iron phosphate vent gas is flammable.

Go deeper: P-06, B-06

F-34What does 'bankable' mean for a battery?

A battery is bankable when lenders and insurers will finance and cover it on normal terms because the evidence is in hand: field operating history, third-party test data, safety listings and a warranty from a supplier strong enough to honor it. Chemistry alone never makes a battery bankable. As of late 2026, most sodium-ion and long-duration types are still building that evidence.

Lenders finance track records, not promises.

Go deeper: B-15, B-16, B-17
Equipment

F-16What does an inverter (PCS) do?

An inverter turns a battery's or panel's direct current into the alternating current a building uses, and for a battery it also works in reverse to charge. The battery inverter with its controls is often called the power conversion system (PCS). A large modern unit passes on about 98% of the energy one way, and it is rated in kVA because its real limit is current.

About 98 of every 100 kWh come through; the rest becomes heat.

Go deeper: I-02, I-01

F-17What is the difference between a BMS, an EMS and a microgrid controller?

The battery management system (BMS) is the battery's own guard and gauge: it watches every cell, estimates charge and health, and opens the battery's switches if a limit is crossed. An energy management system (EMS) decides when the battery charges and discharges to save money or meet a schedule. A microgrid controller does that for the whole site and also runs islanding, bringing loads back and returning to the grid.

BMS keeps the battery safe; EMS makes it useful; the microgrid controller runs the site.

Go deeper: B-11, M-08

F-18What is the difference between grid-forming and grid-following?

A grid-following inverter tracks the grid's voltage and pushes current in step with it, so something else has to set the beat. A grid-forming inverter sets voltage and frequency itself, the way a generator does, and every island needs at least one grid-forming source. Most solar inverters are grid-following.

Followers play along with the drummer; with no drummer, there is no song.

Go deeper: I-04

F-19What is the difference between AC-coupled and DC-coupled solar-plus-storage?

AC-coupled means solar and battery each have their own inverter and meet on the building's AC wiring; DC-coupled means they share one inverter on the DC side. AC coupling usually suits retrofits and grid charging, while DC coupling suits new builds where clipping exceeds about 2% of solar energy. The efficiency gap is small, about 0.2–1.0% of yearly delivered energy.

Separate front doors versus one shared door.

Go deeper: I-05, I-07
Microgrids

F-20How is a microgrid different from a backup generator or a UPS?

An uninterruptible power supply (UPS) bridges a few loads with no break, usually for minutes. A backup generator starts after the outage begins, so its loads have to tolerate a break of about 10 seconds or longer. A microgrid controls several sources and loads together, can disconnect from the grid and keep running, and can also earn savings while grid-connected.

UPS: no blink, minutes. Generator: a blink, hours to days. Microgrid: a whole site, both modes.

Go deeper: M-02, M-03

F-21What is islanding?

Islanding is when a site disconnects from the utility and runs on its own sources. At least one source has to be grid-forming, setting voltage and frequency the way the utility normally does. Protection settings that worked on the grid may not work on the island.

The site becomes its own small power grid, with its own rules.

Go deeper: M-01, P-01

F-22Why can't solar alone run a building in an outage?

Most solar inverters are grid-following: they need a steady voltage from something else and shut off without it. Solar output also swings with clouds and stops at night, so planners count it as zero firm capacity on an island. A battery or generator has to form the grid and cover the gaps.

Plan solar at zero firm capacity in an island.

Go deeper: S-06

F-23What is a black start?

A black start brings a dead site back with no grid: a grid-forming battery wakes up, energizes the transformers and picks up loads in blocks until a generator takes over. Carrying load while waiting for the generator is what drains the battery, so hold back a reserve: restart energy alone is often 5–25% of nameplate for a short handoff, and the charge floor is higher once losses, aging and cold are counted. Ask for a witnessed restart from a dead bus; a grid-forming label is not proof.

In one example, the battery never drops below about 22% charge when counted on to restart the site.

Go deeper: M-04, M-09

F-24What does a "seamless" transfer really mean?

Seamless is a sales word, not a test. What can honestly be promised is that named loads see no more than a stated time outside a stated voltage band, measured at the loads. Real breaks run from zero with an online UPS, to tens of milliseconds with a fast static switch (about 13 ms in one example), to 10 seconds or more with a generator that has to start.

Specify milliseconds and a voltage band, not "seamless".

Go deeper: M-03, M-02
Money

F-25What is the difference between behind-the-meter and front-of-meter?

Behind-the-meter systems sit on the customer's side of the utility meter and earn by cutting that customer's bill, through demand charges, time-of-use shifting and backup. Front-of-meter systems connect directly to the utility grid and earn from wholesale energy, capacity payments or utility contracts. The hardware can be the same; the meter position decides which rules and revenues apply.

Behind the meter cuts a bill; in front of the meter sells to the grid.

Go deeper: N-01, N-05

F-26What is a demand charge?

A demand charge bills the month's single highest short interval, often 15 minutes, at a price per kW. A battery that trims that peak saves the kilowatts cut times the rate, but only if no later interval sets a new peak that month. Rates of about $15 per kW-month or more usually justify a detailed study; below about $10, demand savings alone rarely pay.

One bad 15-minute interval can set the whole month's demand charge.

Go deeper: C-04, B-02

F-27What is the difference between installed cost and levelized cost of storage?

Installed cost is what you pay up front, roughly $450–1,000 per usable kWh for commercial lithium-ion in 2022–2023 dollars. Levelized cost of storage (LCOS) spreads every lifetime cost over every kWh actually delivered, so it depends heavily on use: the same hardware costs up to about 6 times more per kWh at 50 cycles a year than at 300. Compare levelized costs only at the same cycles per year and the same boundary.

Like a gym membership: cheap per visit if you go daily, terrible if twice a year.

Go deeper: C-01, C-07

F-28What is capacity factor?

Capacity factor is a source's actual yearly energy divided by what it would make running at full rating all year. Each kilowatt of solar makes about 1,050–1,900 kWh a year in the lower 48 states, a capacity factor of roughly 12–22% on the panel (DC) rating; figures quoted on the inverter (AC) rating run higher. Wind at a site with measured average winds of 6–7 meters per second runs higher, about 20–36%.

1,500 kWh a year ÷ 8,760 hours ≈ 17% for a kilowatt of solar.

Go deeper: S-01, S-09

F-29What does "value stacking" mean?

Value stacking means earning more than one kind of saving or revenue from the same battery. Some streams share one discharge, some compete for the same stored energy, and some are barred from overlapping by program rules. Before a dispatch model, count about 60–85% of the sum of standalone values, with 75% as a default.

Lending one car to two people: fine on different days, a fight on Friday night.

Go deeper: C-08

F-30Payback or net present value: which one should decide?

Simple payback counts the years until the cash comes back; net present value (NPV) says how much wealth the project adds after charging for the wait at the owner's discount rate. Payback ignores everything after the break-even year, so it screens cash risk but is not a value test. NPV is the test for choosing between options.

A synthetic $1.6M battery: 7.6-year payback, about +$225,000 NPV at 7%.

Go deeper: C-06
Rules and process

F-31What is the difference between UL 9540, UL 9540A and NFPA 855?

UL 9540 (3rd edition, 2023, revised 2025) is the safety listing for a complete energy storage system. UL 9540A is a fire test method, a report rather than a listing; its 6th edition (March 2026, effective January 2027) adds pass/fail criteria to the large-scale installation-level test, and the 5th edition (2025) is still in use. NFPA 855 (2026 edition newest, earlier editions still enforced in many places) is the installation standard the authority having jurisdiction (AHJ) adopts locally for spacing and fire protection.

Product listing, fire test report, installation rule: three different jobs.

Go deeper: X-03, P-05

F-32What is interconnection, and why does it take so long?

Interconnection is the utility's permission to run your generation and storage connected to its grid. It moves through steps set by the utility's tariff: pre-application report, application, fast screens, and fuller studies only if a screen fails, each with its own queue and clock. There is no reliable rule-of-thumb duration, and it is often the longest path to switch-on.

A building permit from the utility instead of the town, with its own queue.

Go deeper: X-01, X-02

F-33Who is the AHJ?

The authority having jurisdiction (AHJ) is the local official or office that enforces codes and approves the installation, and it is rarely one office: building, electrical, fire and planning officials each approve their part. Permits commonly take 2–6 months where the use is permitted by right, and 6–12 months or more with hearings. The utility approves grid connection separately.

Each permit is its own lane; the slowest lane sets the date you can build.

Go deeper: X-04, P-07

No questions match.

Twelve numbers to know

Always say the basis with the number.

BUsable energy vs nameplate
90–95%
of nameplate, new lithium iron phosphate system

Nickel manganese cobalt 85–92%; backup reserve comes out of this.

TypicalCard B-13
BLabel energy that reaches the building
83–91%
of nameplate, new lithium iron phosphate system, mild weather, before own use

Less with aging and cold; see B-01 for backup sizing.

TypicalCard B-03
SSolar performance ratio
0.75–0.85
yearly AC output ÷ ideal output from panel rating

Hot sites or flush roof mounts lose about 5% more.

TypicalCard S-04
SSolar DC/AC ratio
1.20–1.30
panel kW ÷ inverter kW, starting point

Utility fixed tilt up to 1.40; DC-coupled storage 1.40–2.00.

TypicalCard S-03
GDiesel fuel per kWh
0.065–0.080 gal
per kWh, sets 250 kW and up, 75–100% load

Smaller sets about 14% more; light loading burns more still.

TypicalCard G-02
GMinimum generator loading
about 30%
of rated kW, for sustained running, diesel

25–40% by maker; follow light running with a loaded run.

TypicalCard G-03
BBattery's own use
1.5–4%
of discharged energy, daily cycling, liquid-cooled, mild climate

4–8% in hot or cold climates, or when air-cooled.

TypicalCard B-10
BEnd-of-life battery capacity
70–80%
of new capacity, after 10–15 years at one cycle a day

Lithium iron phosphate in a cooled enclosure; the warranty curve governs.

TypicalCard B-05
IInverter efficiency, one way
98.0–98.8%
no built-in transformer, above 50 kVA, 30–100% load

About 96–97.5% with a built-in isolation transformer.

TypicalCard I-02
BBattery duration by use
1–4 h | 2–8 h
peak shaving | islanded backup

Frequency regulation 0.25–1 hour; energy shifting commonly 4 hours.

TypicalCard B-04
CBattery O&M per year
1.5–3.5%
of installed cost, all-in, daily cycling

Service, insurance, warranty, software, own-use energy; augmentation is extra.

TypicalCard C-03
CInstalled battery cost
$450–1,000
per usable kWh, commercial lithium-ion, 2–4 h, 2022–2023 dollars (historical)

A 2022–23 benchmark: get current quotes before budgeting.

TypicalCard C-01

No numbers match.

Number finder

Just the number, and the card that owns it.

QuantityValueBasisConfidenceCard
Battery duration by use1–4 h | 2–8 hpeak shaving | islanded backupTypicalB-04
Battery O&M per year1.5–3.5%of installed cost, all-in, daily cyclingTypicalC-03
Battery's own use1.5–4%of discharged energy, daily cycling, liquid-cooled, mild climateTypicalB-10
Besides the batteries, what does the yard need: pad, cable runs and its own power feed2–4 kWper MWh, plus 1–2 kW per site; hot-day peak, liquid-cooled lithium, 4-hour; 2-hour runs higherTypicalY-06
Can the battery inverter start my motors when the grid is down4–6×motor running kVA; grid-forming inverter, motor started straight across the lineTypicalI-03
Can we export to the grid, and which screens will the utility run15%of the feeder section's yearly peak; common fast-track limit for all generation thereTypicalX-02
Diesel fuel per kWh0.065–0.080 galper kWh, sets 250 kW and up, 75–100% loadTypicalG-02
End-of-life battery capacity70–80%of new capacity, after 10–15 years at one cycle a dayTypicalB-05
How big a battery do I need to ride through an outage1.5–1.8×the energy the load needs; battery nameplate, sized to end of lifeTypicalB-01
How big a battery do I need to shave my demand peak1–4 hof energy per kW shaved; delivered energy; nameplate about 1.7× moreTypicalB-02
How big a generator do I need1.2–1.4×the critical peak, in site-rated kW; running fleet, plus one spare unit for redundancyTypicalG-01
How big an inverter do I need, and why is it rated in kVA instead of kW1.1–1.3×peak kW, stated in kVA; island serving mixed commercial loadTypicalI-01
How do generators and batteries share the load without talking to each other3–5%generator droop; frequency sag from no load to full loadTypicalM-07
How does the system restart from dark, and how much battery charge should be held back for it5–25%of battery nameplate; restart energy alone; short handoff, light restored loadRough guideM-04
How fast can the battery recharge after it is used+15–30%more time than energy ÷ power; lithium-ion, mild weather; less at slow charge rates, slower when coldTypicalB-08
How fast does solar output fade with ageabout 0.5%less output per year; modern panels; 0.5–0.75% at whole-system levelTypicalS-05
How heavy is a battery container, and can my roof, slab or soil carry it250–600 psfpounds per square foot; over the enclosure footprint, installed, lithium containers and cabinetsTypicalY-02
How is availability measured95–98%per year, capacity-weighted; common utility-scale guarantee, with defined exclusionsRough guideQ-03
How is battery capacity tracked over its lifeYearly testsame procedure, same season; three tests before trusting a trendRough guideQ-04
How is round-trip efficiency measured, and why does the meter location change the answer6–14 pointspercentage points lower at the grid meter, with auxiliaries; than at the battery terminals, same test cycleRough guideQ-02
How loud will it be at the property line−6 dBper doubling of distance; one source, open ground, A-weighted decibelsTypicalY-04
How many cycles and years will the battery last10–15 yearsto 70–80% of new capacity; lithium iron phosphate, one cycle a day, cooledTypicalB-05
How many days will my fuel tank last85–90%of the tank is usable fuel; then divide by real hourly burn, not averageRough guideG-06
How many kWh a year will each kW of solar make1,050–1,900kWh per kW a year; of panel rating, fixed tilt, lower 48 statesTypicalS-01
How much does a hot or high-altitude site cut the inverter's rating2–2.5%/°Cof rating lost; above about 40–45 °C at the air inletRough guideI-06
How much energy is lost between the panels and the inverter output15–25%of ideal output lost; panel rating to inverter output, new system, yearlyTypicalS-04
How much energy is lost going from solar to battery to the buildingabout 89–91%delivered; solar stored in the battery, then usedTypicalI-07
How much fuel does a diesel generator burn per kWh and per day0.065–0.080gallons of diesel per kWh; 75–100% load, sets 250 kW and largerTypicalG-02
How much heat does a battery make1–3%of battery power becomes heat; lithium iron phosphate, 2–4 hour rates, inverter outsideTypicalB-14
How much load can we turn down instead of buying more battery50–80%of tested flexible kW; credit toward battery sizing; zero if untestedTypicalL-09
How much power does an inverter burn when it is not doing anything0.1–0.3%of rated kVA, awake at zero output; large inverter, no transformer; asleep about 0.005–0.02%Rough guideI-08
How much reserve should an island hold backLargest lossof supply, often a cloud on the solar; spare online kW until backup startsRough guideM-06
How much roof or land does solar need3–5 acresper megawatt of panels (DC); whole site: near 3 for fixed tilt, 4–5 for trackersTypicalS-02
How much room does a battery need per megawatt-hour250–600 ft²per MWh, fenced yard; containerized lithium iron phosphate, 2–4 hour systemsRough guideY-01
Installed battery cost$450–1,000per usable kWh, commercial lithium-ion, 2–4 h, 2022–2023 dollars (historical)TypicalC-01
Inverter efficiency, one way98.0–98.8%no built-in transformer, above 50 kVA, 30–100% loadTypicalI-02
Label energy that reaches the building83–91%of nameplate, new lithium iron phosphate system, mild weather, before own useTypicalB-03
Minimum generator loadingabout 30%of rated kW, for sustained running, dieselTypicalG-03
Solar DC/AC ratio1.20–1.30panel kW ÷ inverter kW, starting pointTypicalS-03
Solar performance ratio0.75–0.85yearly AC output ÷ ideal output from panel ratingTypicalS-04
Usable energy vs nameplate90–95%of nameplate, new lithium iron phosphate systemTypicalB-13
We have several buildings. Can I just add up their peaks0.75–0.95× the summed peaks; 2–10 similar commercial buildings, 15-minute demandRough guideL-04
What do demand-charge savings look like, and when are they worth chasing$15/kW-month or moredemand rate where a detailed study usually paysRough guideC-04
What do heat and cold do to a batteryabout 2×faster aging per 10 °C hotter; midpoint of 1.3–3×; cells 20–45 °C, idle agingTypicalB-07
What do hot and cold weather do to solar output0.24–0.37%less power per °C; of cell temperature above 25 °C, silicon panelsTypicalS-07
What does a bad week of sun look like for an island10–25%of an average day's solar; poor winter day, cloudy northern climateRough guideS-08
What does electric vehicle charging add to the load70–100%of charger ratings; unmanaged fleet depot; managed, 25–50%TypicalL-08
What does it cost to augment or replace a battery over its life15–30%more usable energy; added over 20 years, daily-cycled lithium iron phosphateRough guideC-11
What does levelized cost of storage mean, and when is a quoted figure meaningful6× highercost per kWh; 50 cycles a year versus 300, same costsTypicalC-07
What does load factor tell me about a siteAverage ÷ peaklow means peaky, high means flatTypicalL-03
What happens the instant the grid fails, and how big a battery inverter catches it1.1–1.2×(battery output + grid import + solar that may trip); grid-forming inverter kVA, unplanned islandTypicalM-01
What is time-of-use shifting worth$0.04–0.07 per kWhminimum peak-to-off-peak price gap before shifting paysTypicalC-05
What permits do we need, who approves them, and how long does it take2–6 monthsbuilding, electrical and fire permits; use permitted by right; 6–12+ months with hearingsRough guideX-04
Why do motors matter so much when the building runs on backup power6–8×full-load current; standard induction motor started straight across the lineTypicalL-06
Why does a longer-duration battery cost less per kWh but more per kW12–23% lowercost per kWh; 2 h to 4 h; cost per kW rises 55–75%TypicalC-02

No numbers match.

Glossary

Dotted terms on cards open these definitions.

AC-coupledF-19

Solar and battery each have their own inverter and meet on the building's AC wiring. Not the same as: DC-coupled

Across-the-line startalso: Direct-on-line startL-06

Starting a motor by switching it straight onto full voltage, which gives the largest starting surge.

Air permitX-04

An air agency permit that limits an engine's emissions and running hours; engines run only for emergencies and testing fall in a lighter category.

Alternating currentACF-05

Electricity that reverses direction many times a second; what the grid and buildings use. Not the same as: Direct current (DC)

AmpereAL-06

The unit of electric current, often called an amp.

Anti-islandingQ-01

The protection that stops a source from energizing the utility's line after the utility side opens.

Arc flashP-04

The burst of heat and light from an electrical fault through air; the heat that reaches a worker, called incident energy, is calculated with the IEEE 1584 guide.

AugmentationF-13

Adding battery blocks during a project's life to replace capacity lost to fade.

Authority having jurisdictionAHJF-33

The local officials who enforce codes, in the editions and with the amendments adopted locally, and approve the installation.

Auxiliary loadalso: Own useB-10

Power a battery system uses for its own cooling, heating, controls and safety systems; also called its own use.

AvailabilityQ-03

The share of time, weighted by how much capacity works, that a system is ready to deliver, not counting excused events such as utility outages.

Backup generatorF-20

An engine generator that starts after an outage begins, so its loads see a break. Not the same as: Microgrid; uninterruptible power supply (UPS)

Backup reserveB-13

Battery energy held back for outages or a restart, which daily savings jobs may not use. Not the same as: Reserve (spare online power)

Ballasted roof systemS-02

Roof solar held down by weights rather than bolted through the roof.

Bankablealso: BankabilityB-15

Accepted by lenders and insurers on normal terms because the evidence, such as field history, test data, listings and a sound warranty, is in hand.

Battery management systemBMSF-17

The battery's own monitoring and protection electronics, which measure every cell, balance them, estimate charge and set limits. Not the same as: Energy management system (EMS)

Behind-the-meterBTMF-25

A system on the customer's side of the utility meter that earns by cutting that customer's bill and providing backup. Not the same as: Front-of-meter

Black startF-23

Restarting a site's power system from a dead bus, fully dark, without help from the grid.

BreakerP-02

A switch that opens automatically to stop current during a fault or overload; the utility breaker is where the site connects to the grid.

BridgingB-04

Carrying load for seconds to minutes until another source, usually a generator, takes over in the handoff.

British thermal unitBtuG-02

A unit of heat energy, about 3,412 per kWh; a gas generator's heat rate is the Btu of fuel it burns per kWh made.

C-ratealso: Hour rateF-09

Charge or discharge power divided by battery energy, so a 2-hour rate is 0.5C; charging power tapers near full, the slow finish.

Calendar agingB-07

Battery capacity lost with time alone, faster when hot and full, on top of cycle aging from use; late in life fade can speed up at a knee.

Capacity factorF-28

Yearly energy divided by what the system would make running at full rating every hour. Not the same as: Performance ratio

Capacity testQ-04

A controlled full discharge, repeated the same way each year, that measures delivered energy; retention is that result divided by the commissioning result.

CathodeB-16

The positive side of a battery cell; its material largely sets the cell's voltage, energy and life.

CellB-11

The smallest battery unit; cells are packaged into modules, wired into strings and set in racks.

ClippingI-05

Solar energy lost when the panels could produce more than the inverter can pass.

Coincidence factorL-04

The combined peak of a group of buildings or loads divided by the sum of their own peaks; adding connected nameplates overstates the peak even more.

Cold-load pickupL-04

The extra load when power returns and heating, cooling, chillers and refrigeration all restart together.

Combined heat and powerCHPG-08

Making electricity on site and putting the engine's waste heat to use.

CommissioningQ-01

The tests that prove a finished system works as designed before handover, from first energization through site acceptance to an unattended run.

Connected loadL-04

The sum of the nameplate ratings of everything wired in, whether or not it runs at once.

ContactorB-11

An electrically held heavy-duty switch, used to connect battery strings or run motors, that drops out if its control voltage dips too far.

Critical loadL-01

Equipment that needs to stay powered during an outage; its combined highest demand is the critical peak. Not the same as: Total facility load

Critical pathX-05

The chain of tasks that sets the earliest finish date; any delay on it delays the project.

CurtailmentS-06

Deliberately cutting solar output because nothing can use or store it, common when solar is overbuilt.

CycleF-12

One full charge and discharge, or partial ones that add up to the same throughput; for alternating current, one full swing.

Day tankG-06

A small fuel tank beside the generator, refilled from the main tank; stored fuel needs polishing to stay usable.

DC-coupledF-19

Solar and battery share one inverter and meet on the DC side. Not the same as: AC-coupled

DC-to-DC converterDC/DCI-07

A device that changes one DC voltage to another, such as a battery's voltage to a shared DC line.

DC/AC ratioS-03

Solar panel rating divided by inverter rating; above 1.0 means the panels are oversized on purpose.

DecibeldB, dBAY-04

A logarithmic unit of sound level, where every 10 dB is ten times the sound power; A-weighted decibels (dBA) match human hearing.

DecommissioningC-11

Removing, transporting and recycling the system at end of life and restoring the site.

DeflagrationB-06

A fast burn of built-up flammable gas that can over-pressure an enclosure.

DegradationS-05

The slow yearly loss of solar panel output with age, after a 1–2% drop in the first months for older p-type panels; n-type panels fade more slowly.

Delivered energyF-07

The energy that actually reaches the load after aging, temperature, conversion losses and own use. Not the same as: Usable energy; nameplate energy

Demand chargeF-26

A monthly charge per kW on the highest short-interval demand, often 15 minutes; a ratchet can carry a high peak into later months. Not the same as: Energy charge

Demand responseC-08

A utility or market program that pays a customer to cut or shift load when called.

DerateG-01

A reduction from the label rating for heat, altitude or other site conditions, judged at the air inlet; what remains is the site rating.

Direct currentDCF-05

Electricity that flows one way only; what batteries and solar panels produce. Not the same as: Alternating current (AC)

Discharge efficiencyB-03

The share of energy leaving the cells that arrives as building power after the inverter, about 0.92–0.96. Not the same as: Round-trip efficiency

Discount rateC-06

The yearly rate that converts future dollars into today's dollars (present value); the hurdle rate is the lowest return an owner accepts.

Discounted paybackC-06

Years until savings recover the cost after each year's cash is discounted to today's dollars.

DispatchC-08

The schedule deciding when each source and the battery run; off-grid systems either run engines hard and store the surplus or run them only as load needs.

DroopM-07

A setting that makes a source push more power as frequency falls, so sources share load without messages; an isochronous source holds frequency fixed instead.

DurationF-08

How many hours a battery can run at its rated power: usable energy divided by rated power.

Electromagnetic transient studyEMTP-01

A detailed simulation of how voltage, current and frequency move in the first moments after an event, using the inverter makers' own models.

Emergency standby ratingG-05

A generator's highest kW label, for utility-outage backup only, limited to about 200 hours a year. Not the same as: Prime rating

End of lifeB-01

The planned point where battery capacity has faded to its limit, commonly 70–80% of new; sizing to it takes about 1.5–1.8 times the energy needed.

Energy management systemEMSalso: Site controllerF-17

The site controller software that decides when a battery charges and discharges to save money or meet a schedule. Not the same as: Battery management system (BMS)

Energy retentionC-09

The warranted minimum share of starting energy the battery still holds in each year.

Energy useF-06

The total energy a site consumes over a period, in kWh. Not the same as: Peak demand (kW)

Explosion controlP-06

Venting or ventilation, designed from the cell maker's gas data, that keeps built-up battery gas from exploding inside an enclosure.

Exportalso: BackfeedX-02

Power flowing from the site back onto the utility's lines.

Export modeX-02

Whether a site may send power to the grid: full export, export up to a set limit, or non-export.

Factory acceptance testQ-01

Testing a specific unit at the factory before it ships; a type test is done once on the model's design in a laboratory.

Fault currentP-02

The current that flows into a short circuit, calculated for each operating mode in a short-circuit study, which breakers and relays need to detect and stop.

Feasibility stageC-01

The earliest cost estimate, made before design starts, which carries the widest contingency; design then passes checkpoints at about 30%, 60% and 90%.

FeederM-09

The utility line that carries power from a substation to a group of customers; its hosting limit is how much generation it can take without upgrades.

Fire pathwayS-02

A clear walkway kept free of panels so firefighters can reach and work on the roof.

Fire protection engineerP-06

An engineer who designs fire detection, suppression such as water or clean-agent gas, and hazard controls.

Fire test reportP-05

The UL 9540A report showing how a cell failure spreads in the product; it reports behavior and is not a listing. Not the same as: Listing

Firm capacityF-22

Output you can count on when needed; solar and wind count as zero in an island plan.

FirmwareM-08

The software built into a device such as an inverter or relay.

Fixed tiltS-01

Panels mounted at one fixed angle, usually facing south, unlike single-axis trackers that turn east to west with the sun.

Flexible loadL-09

Load that can be turned down, delayed or shifted on known notice; it often rebounds when released.

Floating systemP-03

An electrical system with no deliberate connection to earth, watched by an insulation monitor that warns when it starts leaking to ground.

Flood elevationY-05

The design flood level equipment is kept above, by raising it or with a berm, with stormwater drained away from the pad.

Flow batteryB-12

A battery that pumps liquid electrolyte, most often vanadium, from tanks through a stack, so the tanks set the hours and the stack sets the power.

Flush mountS-07

Panels mounted close to the roof with little air behind them, so they run hotter than panels on an open rack.

FootprintY-01

The plan area equipment covers; a site factor adds roads, fence offset, drainage and crane access.

FrequencyHzM-07

How many times per second alternating current swings, in hertz (Hz); 60 Hz in North America, and it sags when load outruns supply.

Frequency regulationB-04

A grid service in which a battery charges and discharges in seconds to keep grid frequency steady.

Front-of-meterFTMF-25

A system connected directly to the utility grid that earns from wholesale markets, capacity payments or utility contracts. Not the same as: Behind-the-meter

Fuel cellPEMG-08

A device that turns fuel into electricity chemically without burning it; PEM cells run on hydrogen and respond fast, solid-oxide cells are efficient but slow.

Geotechnical reportY-02

A soils engineer's report on what the ground can carry; without one, the building code's cautious default soil value applies.

Grid-followingGFLF-18

An inverter that needs a steady voltage from another source and shuts off without it. Not the same as: Grid-forming

Grid-formingGFMF-18

An inverter or generator that sets voltage and frequency, so an island has a reference to follow. Not the same as: Grid-following

Ground-fault protectionP-03

A device that trips when current leaks to ground; it can trip falsely if neutral current takes the wrong path.

Half cellB-16

A lab test cell that pairs one electrode with pure sodium or lithium metal; it tests the material, and a full commercial cell usually keeps less. Not the same as: Full cell (a complete battery cell)

Hazard mitigation analysisP-06

A fire protection engineer's study of how a battery failure could unfold and how it is controlled, paired with a response plan for firefighters.

HeartbeatM-08

A regular signal proving a control link is alive; after a timeout without it, a device switches to its fallback.

Heat rateG-02

Fuel heat burned per kilowatt-hour made, in Btu per kWh; lower is more efficient.

Higher heating valueHHV, LHVG-08

Fuel energy counted with the heat in the water vapor formed (HHV) or without it (LHV), and quoting on LHV makes the same gas machine look about 10% more efficient.

HorsepowerhpL-01

The usual unit for motor size; one horsepower is about 0.75 kW of output.

Hub heightS-09

The height of a wind turbine's rotor center, where wind is measured; output then follows the certified power curve and the swept rotor area.

Hurdle rateC-06

The minimum return an owner requires before approving a project.

Hybrid inverterI-05

One listed box with solar inputs, a battery port and an AC output, common in homes and small businesses.

IEEE 1547X-03

The standard for how generation and storage behave on the distribution grid, with IEEE 1547.1 giving the tests that prove it.

IncentiveC-10

A tax credit, grant or rebate that lowers a project's net cost; rules and eligibility change, so confirm current law.

Incident energyP-04

The heat from an arc flash that reaches a worker at a set distance, in calories per square centimeter.

Independent engineeralso: Lender's engineerB-15

An engineering firm hired for the lenders to check a project's technology, contracts, tests and risks before money is lent. Not the same as: Owner's engineer (works for the owner)

Installed costC-01

Everything paid to build the system up to the utility connection, including soft costs such as engineering and permits; it grows more slowly than size. Not the same as: Levelized cost of storage

Institute of Electrical and Electronics EngineersIEEEP-04

The engineering body that publishes many electrical standards, such as IEEE 1547 and IEEE 1584.

InterconnectionF-32

The utility's process, queue and signed agreement for connecting on-site generation or storage to run in parallel with its grid.

InterlockQ-01

A device or logic that blocks one action unless a safe condition is met, such as a door that cannot open while power is on.

Internal rate of returnIRRC-06

The discount rate at which a project's net present value is exactly zero.

Internal resistanceB-14

The opposition to current inside a cell; it turns some power into heat and grows with age and cold.

International Fire CodeIFCP-06

The model fire code many U.S. jurisdictions adopt; its battery rules sit in Section 1207 and refer to NFPA 855.

Interrupting ratingP-02

The largest fault current a breaker or fuse can safely stop.

Interval dataL-01

Meter readings taken every 15 minutes or so, rather than monthly totals.

InverterPCSalso: Power conversion systemF-16

The device that converts direct current to alternating current, and back for a battery; a battery inverter with its controls is also called a power conversion system (PCS).

Inverter efficiencyI-02

The share of power going into an inverter that comes out converted, one direction only; weighted efficiency averages set load points. Not the same as: Round-trip efficiency

Iron-air batteryB-12

An emerging battery aimed at about 100 hours of storage, now at first pilots; round-trip efficiency and field life are still to be shown.

IslandingF-21

Disconnecting a site from the utility and running it on its own sources; the site is then an island.

Kilovolt-amperekVA, MVAF-04

The total electrical load wires and equipment have to carry, including the part that does no useful work; 1,000 kVA is one megavolt-ampere (MVA). Not the same as: Kilowatt (kW)

KilowattkWF-01

A rate of power: how fast energy is being delivered at a moment. Not the same as: Kilowatt-hour (kWh); kilovolt-ampere (kVA)

Kilowatt-hourkWhF-01

An amount of energy: one kilowatt delivered for one hour. Not the same as: Kilowatt (kW)

Layered oxidealso: Layered oxide cathodeB-16

A sodium-ion cathode in which sodium sits between sheets of metal oxide, often nickel, iron and manganese.

Lead timeX-05

Time from order to delivery; long-lead items such as medium-voltage transformers often set the critical path, the chain of tasks that fixes the finish date.

Lean-burn engineG-04

A gas engine running on extra air for efficiency and low emissions, taking load in smaller steps than a rich-burn engine; both can run on natural gas or biogas.

Levelized cost of storageLCOSF-27

Lifetime cost divided by lifetime delivered energy, in today's dollars, as a price per kWh; levelized cost of energy does the same for a power system. Not the same as: Installed cost

Licensed engineerP-07

A professional engineer licensed in the project's state who seals studies and drawings; the engineer of record takes responsibility for the design.

Life-safety loadalso: Code emergency loadsL-05

Equipment the codes require to keep people safe in an outage, such as exit lighting, fire alarms and fire pumps. Not the same as: Critical load

Liquid coolingY-06

Cooling battery modules with circulating coolant rather than air, sized to the maker's heat-rejection data.

ListingP-05

A recognized testing laboratory's certification of a product, published in its directory with ongoing factory inspection. Not the same as: Fire test report (a test report, not a listing)

Lithium iron phosphateLFPF-14

The most common battery chemistry for stationary storage: long life, lower energy per pound. Not the same as: Nickel manganese cobalt (NMC)

Lithium-ionB-06

The family of rechargeable batteries that move lithium between electrodes; includes lithium iron phosphate and nickel manganese cobalt.

Load bankQ-01

A portable bank of resistors that draws a set load so sources can be tested without real building load.

Load factorL-03

Average power divided by peak power over the same period; near 1.0 means a flat base load, low means short sharp peaks.

Load sheddingL-05

Switching off lower-priority loads, by plan or automatically when frequency falls, so the sources can carry the rest.

Load stepG-04

A block of load added to a source all at once, such as a transfer switch closing.

Load tieralso: TierL-05

A priority group of loads kept on, shed or restored together; loads that can wait sit in the last tier.

Locked-rotor currentL-01

The surge a motor draws while starting, typically 6–8 times its full-load running current; the nameplate code letter gives it as kVA per horsepower.

Long-duration storagealso: Long-duration energy storageB-17

Storage built to discharge for many hours to days, well beyond the few hours of most lithium-ion projects.

Managed chargingL-08

Controls that share a set power limit among vehicle chargers, including 50–350 kW fast chargers, so they do not all run at full power.

Medium voltageMVY-05

Distribution voltages above 1,000 volts, typically 4–35 kV.

MegawattMWF-03

A thousand kilowatts; a rate of power, not an amount of energy. Not the same as: Megawatt-hour (MWh)

Megawatt-hourMWhF-03

An amount of energy equal to 1,000 kilowatt-hours. Not the same as: Megawatt (MW)

Meter pointQ-02

Where energy is measured: battery terminals, inverter output, transformer or grid meter, each giving a different answer.

Meters per secondm/s, mphS-09

A wind speed unit; 1 m/s is about 2.24 miles per hour (mph).

MicrogridF-20

Local sources and loads controlled together that can run with the grid or on their own. Not the same as: Backup generator

Microgrid controllerF-17

The site-level controller that dispatches every source and runs islanding, load restoration and return to the grid. Not the same as: Energy management system (EMS)

MicroturbineG-08

A small gas turbine, about 30–1,000 kW, connected through power electronics.

MillisecondmsM-02

One thousandth of a second.

Minimum loadingalso: Minimum loadG-03

The lowest share of rating a diesel should run at for long periods, about 30%, to avoid fouling.

Modified internal rate of returnMIRRC-06

A yearly return that assumes cash is reinvested at a stated rate instead of at the project's own return.

ModuleB-11

A packaged group of cells with its own monitoring board.

N+1G-01

One more unit than the load needs, so any single unit can fail or be serviced; 2N means two complete systems, each able to carry everything.

Nameplate energyalso: NameplateF-07

The rated size on the equipment label; for a battery, its energy when new, before reserves, losses and aging. Not the same as: Usable energy; delivered energy

National Electrical CodeNECX-03

NFPA 70, the wiring rules for buildings and sites, enforced in the edition adopted locally.

National Fire Protection AssociationNFPAP-06

The body that publishes model fire codes and standards, including NFPA 855.

Net present valueNPVF-30

All future cash in and out converted to today's dollars at a discount rate and added up; above zero means the project adds wealth. Not the same as: Simple payback

Neutral-to-ground bondP-03

The single connection between the neutral, the return conductor, and the grounding system for each service or separately derived system; paralleled sources on a shared neutral share one.

NFPA 855F-31

The installation standard for stationary energy storage, enforced in the edition the local authority has adopted. Not the same as: UL 9540 (a product listing)

Nickel manganese cobaltNMCF-14

A lithium-ion chemistry with more energy per pound but shorter cycle life and lower heat tolerance. Not the same as: Lithium iron phosphate (LFP)

Noise ordinanceY-04

A local law setting maximum sound levels, often stricter at night.

Offtake contractalso: Offtake agreement, OfftakeB-15

The contract under which a buyer pays for a project's energy, capacity or service; it sets the performance the battery is held to.

One-in-ten poor yearS-01

A year, or a day in a given month, with solar output so low that nine in ten do better.

One-line diagramX-06

A simplified drawing of the electrical system showing sources, protection, transformers and meters, updated to as-built at closeout.

Open transitionM-02

A transfer that breaks from one source before connecting the other, so loads go briefly dark; a closed transition connects first, for planned transfers only.

Operating envelopeC-09

The rate, temperature, charge and cycle limits a battery warranty requires, inside which its energy retention promise holds.

Operating modeP-02

One arrangement of running sources, such as grid-connected, battery only or generator only.

Operations and maintenanceO&MC-03

The yearly cost of running and servicing a system, including insurance and warranty.

Organic growthL-07

Gradual load growth with no specific project behind it, expressed as a percentage a year.

Overload ratingI-03

How far above its continuous rating an inverter can run, and for how long.

Panel ratingS-01

A solar panel's label power, measured in bright laboratory sun at a cell temperature of 25 °C.

Peak demandF-06

The highest average power a site draws over a stated window, such as 15 minutes or 1 minute. Not the same as: Energy use (kWh over time)

Peak shavingG-05

Using a generator or battery to hold a site's demand below a target during its highest-use periods.

Per unitN-04

A value expressed as a fraction of its normal or rated value, so 0.85 per unit voltage is 85% of normal.

Perfect foresightC-04

A simulation that knows every future load and price, so it overstates real savings; a realization haircut cuts results to about 70–90%.

Performance ratioS-04

A solar system's actual output divided by what its panel rating and the sunshine would ideally give, after soiling, mismatch, heat and other losses. Not the same as: Capacity factor

Permission to operateP-07

The utility's written go-ahead to run in parallel with its grid, given after its review and any witness test it requires.

Polyanionalso: Polyanion cathode, Sodium iron phosphate, Sodium vanadium phosphateB-16

A sodium-ion cathode family built on a sturdy phosphate framework: long life, lower energy per kilogram.

Pounds per square footpsfY-02

Load spread over an area; how floors, roofs and soil capacities are stated.

Power factorF-04

The share of kilovolt-amperes that does useful work, kW divided by kVA; at unity power factor the two are equal.

Pre-application reportX-01

An optional early utility report on the feeder, its fault level and the generation already on it.

Present valueC-07

A future amount of money expressed in today's dollars at a stated discount rate.

Preventive maintenanceQ-05

Scheduled inspection, such as infrared scans for hot connections, and replacement done before something fails.

Prime ratingG-05

A generator's kW label for unlimited hours at varying load, about 10% below standby; the continuous rating is lower still, for constant full load. Not the same as: Emergency standby rating

Protection settingsP-01

Pickup currents and time delays that tell relays when to trip, stored in a settings file and grouped so a site can switch a whole set per operating mode.

Prussian blue analogalso: Prussian blue, Prussian whiteB-16

A sodium-ion cathode family with high capacity and fast rates, but limits in cycle life and packing density.

Reactive powerkvaralso: Kilovolt-ampere reactiveI-01

Power, in kvar, that flows back and forth to magnetize motors and transformers but does no useful work; it still uses inverter and generator capacity.

Real dollarsC-06

Dollars of constant buying power in a base year; nominal dollars include inflation, and the two are never mixed.

Reclosingalso: RecloseX-01

Closing a breaker again automatically shortly after a fault trips it, common on utility lines.

Regional yieldS-01

Yearly AC energy per kW of panel rating for a region, with normal losses included; sun hours express the same idea per day.

RelayM-08

A protective device that measures current and voltage through sensors such as current transformers and tells a breaker when to open.

Renewable fractionM-05

The share of a period's energy served by renewables, unlike the instantaneous solar share at one moment.

ReserveG-03

Spare online power held to cover a source loss or a sudden solar drop when a cloud passes. Not the same as: Backup reserve (stored energy)

RetentionQ-04

Today's tested battery energy divided by the energy measured at commissioning.

Revenue meterQ-02

The utility-grade meter used for billing at the grid connection; its accuracy class, such as 0.2, is its rated error in percent.

Ride-throughP-01

A rule that a source keeps running through a brief voltage or frequency disturbance.

Root cause analysisQ-06

A structured investigation of why a failure happened, starting from settings and records captured before anything is reset.

Round-trip efficiencyF-11

The share of energy put into a battery that comes back out, measured at a stated point. Not the same as: Inverter efficiency (one way only)

Run-of-river hydroS-09

Small hydro with little or no pond, whose power follows the stream's flow and head, the vertical drop.

ScreenX-02

A pass-or-fail check, often run on a feeder section, that lets low-impact projects take the fast track; failing one leads to supplemental review, not refusal.

Seamless transferF-24

A sales term for a source change the loads should not notice; specify it as a maximum time outside a voltage band.

SecondsM-02

Unit of time; used here for how long a transfer or step takes.

SetbackY-01

The minimum distance code or zoning requires between equipment and a property line, building or other equipment, including clearance for service and fire.

Setting groupP-01

One complete set of relay settings; a microgrid may switch between groups for each operating mode.

Short-circuit ratioalso: Grid strength ratioI-04

Grid strength at a connection point divided by the inverter rating there; below about 3 the grid counts as weak.

Simple paybackalso: PaybackF-30

Years of net savings needed to recover the installed cost, without discounting; discounted payback converts each year to today's dollars first. Not the same as: Net present value (NPV)

Site ratingalso: Site-derated ratingG-01

What a generator can actually deliver at the site's altitude and air temperature, after derating its label value.

Sodium chromium oxidealso: NaCrO2, Sodium chromiteB-16

A layered-oxide sodium-ion cathode built on chromium, with published half-cell cycling results but little public full-cell data as of late 2026.

Sodium-ionB-12

A battery that works like lithium-ion but uses sodium; no lithium, nickel or cobalt, early in the market.

Sodium-sulfur batteryalso: Sodium-sulphur batteryB-17

A high-temperature sodium and sulfur battery, in commercial service since 2002 from one main maker.

Soft starteralso: Soft startI-03

An electronic device that raises a motor's voltage gradually to cut the starting surge; a wye-delta starter is a different reduced-voltage method.

Specific fuel consumptiongal/kWh, gal/hG-02

Fuel a generator burns per unit of energy, here gallons per kWh; gallons per hour is the burn rate at a given output.

Square feetft²Y-01

Area; about 10.8 square feet in a square meter.

Standby chargeY-05

A utility charge for keeping grid capacity ready behind on-site generation; a departing-load charge bills load that leaves the grid.

Standby lossI-08

Power an inverter uses while switched on but delivering nothing, much lower in sleep mode.

State of chargeSOCF-10

How full the battery is right now, as a percentage; the fuel gauge. Not the same as: State of health (SOH)

State of healthSOHalso: HealthF-10

How much capacity the battery has left compared with new, for example 0.85. Not the same as: State of charge (SOC)

Static switchM-02

A fast electronic switch with no moving parts that can separate a site from the grid in under a cycle.

StringS-07

Panels or battery cells wired in series so their voltages add, switched as one unit.

Structural engineerY-02

A licensed engineer who checks that roofs, slabs, footings and anchors can carry the equipment's weight plus snow, wind and earthquake loads.

SubmittalX-05

Equipment data and drawings sent for review before purchase or build, often with a compliance matrix showing how each code provision is met.

SwitchgearL-07

Assemblies of breakers, switches and buses that distribute and protect power, gathered in a substation at larger sites.

Synchronizealso: ResynchronizationM-09

Matching voltage, frequency and timing of two sources before connecting them, as when an island rejoins the grid.

System impact studyX-01

A utility study of how a project affects voltage, loading and protection; a facilities study then prices and schedules the upgrades.

TariffC-04

The utility's rate schedule: energy, demand, time-of-use, standby and export charges.

Tax creditI-05

A federal incentive that reduces the owner's tax bill by a share of project cost or per kWh produced; rules change, so confirm with tax counsel.

TelemetryQ-03

The remote data feed that shows what the system is doing, tuned so alarms do not flood operators.

Temperature coefficientS-07

How much panel power changes per degree of cell temperature, which runs 25–45 °C above the air in full sun.

Temperature factorB-03

The fraction of usable energy left when cells are colder than their preferred band, 1.0 when warm.

Thermal runawayF-15

A cell failure that heats itself, vents flammable gas and can spread to neighboring cells.

ThroughputC-09

The total energy a battery charges or discharges, which warranties cap per year and for life, often as a number of full cycles.

Time-of-useTOUC-05

A rate where energy costs more in some hours of the day than others.

Time-step simulationalso: Hour-by-hour simulation, Chronological dispatch simulationI-07

A computer model that steps through a year hour by hour or faster, tracking every energy flow; run carefully on each scenario, it gives the estimate lenders expect to review.

Transfer switchATSG-04

A switch that moves loads between the utility and a backup source; a four-pole switch also switches the neutral, a three-pole one leaves it connected.

Transfer tripY-05

A utility signal that trips a customer source when the utility breaker opens.

TransformerL-07

Equipment that changes voltage from one level to another, such as a step-up unit to utility voltage, often skid-mounted with the inverter.

Type testX-01

A laboratory test of a product design, done once for the model rather than for each unit.

UL 1741SBalso: UL 1741 Supplement SBP-05

The listing standard for inverters, now including the grid-support tests once published as Supplement SB.

UL 1973P-05

The safety standard for battery modules and battery systems.

UL 9540F-31

The safety listing standard for a complete energy storage system. Not the same as: UL 9540A (a test method, not a listing)

UL 9540AF-31

A fire test method that reports how thermal runaway spreads; cited by edition because reports are edition-specific. Not the same as: UL 9540 (the listing)

UnderwriterB-15

The insurance specialist who decides whether a risk is covered and on what terms.

Underwriters LaboratoriesULalso: ULX-03

The safety-science organization that publishes product safety standards such as UL 9540 and UL 1741.

Uninterruptible power supplyUPSF-20

A battery-backed unit that keeps selected loads running with no break, usually for minutes. Not the same as: Backup generator

Usable energyF-07

The part of nameplate energy the controls allow you to use between the upper and lower charge limits. Not the same as: Nameplate energy; delivered energy

Usable windowalso: Usable SOC window, SOC windowB-01

The allowed charge range as a fraction of nameplate, for example 10% to 90% gives 0.80.

Value stackingF-29

Earning more than one kind of saving or revenue from the same battery.

Variable-frequency driveVFDalso: Variable frequency driveM-03

Electronics that run a motor at adjustable speed and start it gently, keeping the starting surge near normal current.

VoltV, kVL-06

The unit of electrical pressure; buildings use 208, 480 or 600 volts, and a kilovolt (kV) is 1,000 volts.

Voltage dipalso: Voltage sagL-06

A brief drop in voltage, such as during a motor start; a device's hold-up time is how long it keeps running through one.

Walk-in enclosureY-02

A battery building or large container with an inside aisle for service.

Watt-hours per kilogramWh/kgB-12

Energy stored per kilogram of cell or liquid; higher means lighter for the same energy.

Wear costC-05

The share of future replacement and augmentation cost charged to each kWh the battery delivers.

Wet stackingG-03

Unburned fuel and oil building up in a lightly loaded diesel's exhaust, which also stops newer engines cleaning their exhaust filters.

Wholesale marketC-08

The regional market where plants and batteries sell energy and grid services; some owners instead lease a battery's control under a tolling agreement.

Witness testX-01

Field tests a utility watches before granting permission to operate.

Zinc-based batteryalso: Zinc battery, Zinc hybrid batteryB-17

A battery family built on zinc rather than lithium; one maker lists safety certifications for a stationary type, with little public fleet data.

ZoningY-03

Local land-use rules on what may be built where; a use not allowed by right needs a special use permit, usually with a hearing.

No terms match.

From the author

Why this guide exists

Energy projects run on first answers.

Someone asks how big the battery needs to be, how much room it takes, or what it will cost. They ask in a sales meeting, on a site walk, or in a boardroom, and they want a number before anyone has run a study. Whoever answers sets the direction for everything after.

In twenty years of energy projects, the expensive mistakes I've seen rarely came from hard math. They came from a first number nobody questioned. A battery sized on the label instead of what it delivers. A generator that looked big enough on paper. "Seamless" promised before anyone measured a transfer.

This guide is my attempt to make the first answer a good one.

Every card starts with a question the way people ask it. You get a range you can say out loud, what it's measured against, what moves it, and where it breaks. Each card also tells you when to stop and call an engineer. On protection, grounding, arc flash and fire code, the cards give no numbers at all. Those need a study, and I'd rather say so than hand you something to guess with.

A few things you should know.

These are rules of thumb. They are not designs, and they are not a licensed engineering opinion.

Every number traces back to a source in the handbook this guide draws on, and every worked example was recomputed by script and reviewed. The full source list, with links, is free and open at matthuber.net/references. The confidence badges are honest. Most cards say "typical." Some say "rough guide," and I left them that way on purpose.

If you're new to this, start with the Fundamentals and the twelve numbers. If you're in front of a customer, say the number with its basis attached.

Matt HuberRochester, New YorkNovember 2026