Engineering Ministries International ยท March 2026
Kikuyu, Kenya
A 250-bed mission hospital outside Nairobi, a two-week trip, and the electrical master plan that came out of it. Volunteer work with Engineering Ministries International, in partnership with Medical Benevolence Foundation.
PCEA Kikuyu Hospital has been caring for patients since 1908. Today, the 250-bed mission hospital serves a community of roughly half a million people. Its two campuses have grown to more than 80 buildings, some over a century old. As demand grows, the hospital faces a difficult challenge: dramatically expanding its capabilities while keeping an aging infrastructure and a busy hospital running.
In March 2026, I spent two weeks in Kenya with a multidisciplinary team from Engineering Ministries International, working alongside Medical Benevolence Foundation and the hospital on a long-term campus master plan. I led the electrical infrastructure planning. We assessed existing conditions, identified priorities for safety and reliability, and developed an infrastructure strategy designed to support decades of growth.
The proposed plan brings separate electrical services together through a resilient underground distribution network, integrates solar generation and battery storage, and coordinates power, water, sewer, and communications around a new campus ring road. Just as importantly, the work was organized into manageable phases so the hospital could address its most pressing needs, secure funding, and continue caring for patients as the campus evolves.
The principle behind the whole trip was simple: leave things better than we found them, and hand the hospital a plan its own people can carry forward.
Proposed masterplan at a glance
80+
Buildings
Across two hospital campuses
20 years
Planning horizon
Infrastructure designed for long-term growth
~1.9 MWp
Proposed solar
Rooftop and ground-mounted generation
2.5 MWh
Proposed storage
Battery energy storage system
The fundamental change
Not an engineering drawing. The shapes are the campus in outline, and the lines are the idea: three separate services today, one connected system in the plan.
What the plan proposes
Resilient power infrastructure
Consolidated utility service, a four-node underground distribution architecture, coordinated emergency power, and integrated solar and battery storage.
Connected campus infrastructure
A shared utility corridor supporting electrical distribution, water, wastewater, and communications, designed around long-term campus expansion.
A practical path forward
Phased improvements that prioritize safety, accommodate future construction, and allow the hospital to continue operating as funding becomes available.
How it grows
Each construction phase adds buildings and roof area, so solar is added in step with demand. Old buildings come down as new ones open, which is why demand barely moves after Phase 2. Battery storage stays at 2.5 MWh throughout. Proposed figures from the master plan.
What it means on the ground
Two paths to power for every building
The ring loop can isolate any one segment without dropping the rest of the campus. Today, three separate services each stand alone.
Surgery doesn't stop when the grid does
The battery is designed to pick up the whole campus the instant utility power drops, with no gap. Generators at the operating theatres and ICU cover anything longer.
Goats mow the solar field
The ground array is laid out for rotational grazing by local herders. The goats keep the grass down, the herders gain pasture, and the hospital skips the mowing.
Zero net grid import
At full build-out, solar and battery carry the campus 18 of every 24 hours and yearly net grid import is zero. About 750 kWp of rooftop capacity stays in reserve.