Engineering Ministries International ยท March 2026

Kikuyu, Kenya

A 250-bed mission hospital outside Nairobi, a two-week trip, and the electrical master plan that came out of it. Volunteer work with Engineering Ministries International, in partnership with Medical Benevolence Foundation.

PCEA Kikuyu Hospital has been caring for patients since 1908. Today, the 250-bed mission hospital serves a community of roughly half a million people. Its two campuses have grown to more than 80 buildings, some over a century old. As demand grows, the hospital faces a difficult challenge: dramatically expanding its capabilities while keeping an aging infrastructure and a busy hospital running.

In March 2026, I spent two weeks in Kenya with a multidisciplinary team from Engineering Ministries International, working alongside Medical Benevolence Foundation and the hospital on a long-term campus master plan. I led the electrical infrastructure planning. We assessed existing conditions, identified priorities for safety and reliability, and developed an infrastructure strategy designed to support decades of growth.

The proposed plan brings separate electrical services together through a resilient underground distribution network, integrates solar generation and battery storage, and coordinates power, water, sewer, and communications around a new campus ring road. Just as importantly, the work was organized into manageable phases so the hospital could address its most pressing needs, secure funding, and continue caring for patients as the campus evolves.

A single-story stone hospital building under tall palms and jacaranda trees on the PCEA Kikuyu Hospital campus
The main campus. Some of these buildings have served patients for more than a century.

The principle behind the whole trip was simple: leave things better than we found them, and hand the hospital a plan its own people can carry forward.

Proposed masterplan at a glance

  • 80+

    Buildings

    Across two hospital campuses

  • 20 years

    Planning horizon

    Infrastructure designed for long-term growth

  • ~1.9 MWp

    Proposed solar

    Rooftop and ground-mounted generation

  • 2.5 MWh

    Proposed storage

    Battery energy storage system

The fundamental change

Not an engineering drawing. The shapes are the campus in outline, and the lines are the idea: three separate services today, one connected system in the plan.

Conceptual diagram of the campus today: three separate utility services, each feeding its own group of buildings, with no connection between them Utility grid 2 1 3 Three services, no connection between them
Today Three independent utility services, each feeding its own group of buildings. None can back up another, and the systems behind them are aging.
Conceptual diagram of the proposed masterplan: one utility service feeding four switching nodes on an underground ring loop around the main campus, with spurs to the outlying clusters and a solar field and battery feeding the ring Utility grid Solar field Battery 1 2 3 4 One service One ring loop: power, water, sewer, fiber Masterplan concept
Proposed masterplan concept One utility service, four switching nodes on an underground ring loop, so every building has two paths to power. Solar and battery feed the same ring. The loop runs under a new ring road that also carries water, sewer, and fiber, and it is built in phases.

What the plan proposes

  1. Resilient power infrastructure

    Consolidated utility service, a four-node underground distribution architecture, coordinated emergency power, and integrated solar and battery storage.

  2. Connected campus infrastructure

    A shared utility corridor supporting electrical distribution, water, wastewater, and communications, designed around long-term campus expansion.

  3. A practical path forward

    Phased improvements that prioritize safety, accommodate future construction, and allow the hospital to continue operating as funding becomes available.

Rendered aerial view of the proposed campus masterplan, with new multi-story medical buildings around a central green and the existing covered walkways
The architectural masterplan concept for the main campus, prepared by Engineering Ministries International. Supporting context for the electrical plan above. A proposal, not yet built.

How it grows

Each construction phase adds buildings and roof area, so solar is added in step with demand. Old buildings come down as new ones open, which is why demand barely moves after Phase 2. Battery storage stays at 2.5 MWh throughout. Proposed figures from the master plan.

Campus demand, kVA
  1. 432Today: 432 kVA
  2. 658New hospital: 658 kVA
  3. 655Phase 1: 655 kVA
  4. 729Phase 2: 729 kVA
  5. 726Phase 3: 726 kVA
  6. 721Phase 4: 721 kVA
  7. 781Phase 5: 781 kVA
Solar installed, kWp
  1. 1,046Today: 1,046 kWp
  2. 1,296New hospital: 1,296 kWp
  3. 1,531Phase 1: 1,531 kWp
  4. 1,764Phase 2: 1,764 kWp
  5. 1,756Phase 3: 1,756 kWp
  6. 1,745Phase 4: 1,745 kWp
  7. 1,889Phase 5: 1,889 kWp

What it means on the ground

  • Two paths to power for every building

    The ring loop can isolate any one segment without dropping the rest of the campus. Today, three separate services each stand alone.

  • Surgery doesn't stop when the grid does

    The battery is designed to pick up the whole campus the instant utility power drops, with no gap. Generators at the operating theatres and ICU cover anything longer.

  • Goats mow the solar field

    The ground array is laid out for rotational grazing by local herders. The goats keep the grass down, the herders gain pasture, and the hospital skips the mowing.

  • Zero net grid import

    At full build-out, solar and battery carry the campus 18 of every 24 hours and yearly net grid import is zero. About 750 kWp of rooftop capacity stays in reserve.

A long covered walkway between hospital wards, lined with hedges and planting beds
Covered walkways connect the wards. The new utility corridor follows the same logic underground.
A covered corridor at the hospital with stone walls, red steel columns, and a sign pointing to the wards and theatre
The campus stays open through every phase. The plan is sequenced so care never stops.